ArticlePDF Available

A Preliminary Comparative Study of Seepage Behaviour Behind Retaining Walls with Crumb Rubber and Geocomposite

Authors:

Abstract and Figures

A retaining wall is built to provide support to the soil when there is a change in elevation of the ground. Weep holes present in the retaining wall help water to seep through it. Filter protection should be made behind the weep holes to prevent soil erosion around the weep holes. The classic filter material that is widely used is gravel, which is packed according to Hudson’s law. Laboratory experiments were conducted to understand the seepage function of alternative material such as crumb rubber and geocomposite (fabricated) in a homogenous sand layer and in-situ soil. The time taken by the water to reach the weep holes was calculated and compared. From the results, it is suggested to use crumb rubber as an alternative packing material behind the weep hole.
Content may be subject to copyright.
CIVIL AND ENVIRONMEN TAL ENGINEERING REP O R TS
E-
ISSN 2450-8594
CEER 2020; 30 (1): 171-184
DOI: 10.2478/ceer-2020-0013
Original Research Article
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE
BEHAVIOUR BEHIND RETAINING WALLS WITH CRUMB
RUBBER AND GEOCOMPOSITE
Vijayasimhan SIVAPRIYA
1
, Chinnusamy SUDHARASAN
2
,
Ravikumar SURAJ
2
, Kalyansundaram ABINAYA
2
Department of Civil Engineering, SSN College of Engineering, India
A b s t r a c t
A retaining wall is built to provide support to the soil when there is a change in elevation
of the ground. Weep holes present in the retaining wall help water to seep through it.
Filter protection should be made behind the weep holes to prevent soil erosion around
the weep holes. The classic filter material that is widely used is gravel, which is packed
according to Hudson’s law. Laboratory experiments were conducted to understand the
seepage function of alternative material such as crumb rubber and geocomposite
(fabricated) in a homogenous sand layer and in-situ soil. The time taken by the water to
reach the weep holes was calculated and compared. From the results, it is suggested to
use crumb rubber as an alternative packing material behind the weep hole.
Keywords: crumb rubber, geocomposite, permeability, experimental study
1. INTRODUCTION
A retaining wall is constructed to retain the soil on one side and making the
other side convenient for human purposes. It is designed for the following
stability conditions; safety against overturning, safety against sliding, safety
against allowable soil bearing pressure and stress within the components that are
1
Corresponding author: Department of Civil Engineering, SSN College of Engineering, Chennai,
India – 603110; e-mail: sivapriyasv@ssn.edu.in.
2
Department of Civil Engineering, SSN College of Engineering, India, Undergraduate students
172
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
within codal provisions (Brooks, 2010). The main cause of the retaining wall is
due to improper design and poor construction practice (Figure 1).
Fig. 1. Failure modes of reinforced earth wall (External failure (a) basal sliding, (b)
overturning, (c) bearing capacity failure, (d) overall sliding; internal failure (e) pull-out
failure, (f) breakage of reinforcement, (g) internal sliding, (h) breakage of connector, (i)
shear failure of facing wall, (j) failure of upper facing block) (Shin et al., 2011)
Soil and water interaction behaviour leads to various problems. When the water
penetrates into the voids of the soil, soil erosion takes place. Permeability is
defined as the velocity of flow under a hydraulic gradient of unity (Ranjan and
Rao, 2005). The piping effect occurs if the permeability of material used in
drains is not studied to a maximal extent. Hence, soil permeability behaviour
should be understood clearly.
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
173
During rainy seasons, water tends to penetrate into the retained soil and seeps
through the weep holes. The purpose of these weep holes is to drain the water
into a proper drainage system, which is constructed along the bottom of the
retaining wall (Figure 2). If the water is not drained properly, hydrostatic
pressure built behind the retaining wall increases, where the retaining wall may
not be designed to carry that pressure. Due to high generation of hydrostatic
stress, the face of the retaining wall tends to crack (Figure 3) where the backside
of weep holes will have a soil packing from smaller particles to larger particles
towards the face of the retaining wall. In a recent trend, geocomposite material is
widely used as the cost reduces by 35% compared to a conventional system
(Pietro, 2013).
Few case studies discuss the erosion of soil slope and the importance of drains.
Leeves, an important flood protection structure, was damaged by improper
seepage. When the soil is mixed with short fibre as reinforcement (length 10 –
100 mm), it shows a high erosion resistance (Furumoto et al., 2002). Rainfall
intensity also plays a vital role in causing instability (Dahal et al., 2006), and
therefore should be considered as an important parameter while designing. In
addition, improper wall design against stability leads to failure of the retaining
wall (Souza et al., 2017).
Crumb rubber is a largely produced solid waste after recycling used tyres and
crumbed into uniform angular pieces. It was reported that every year, about 100
crores of used tyres were turned into crumb rubber (Thomas et al., 2014). This
solid waste was used widely in pavement and concrete as a replacement material
for aggregates.
In order to understand the importance of permeability characteristics of CR,
a laboratory study was conducted in homogenous sand and in-situ soil with
packing material as crumb rubber in single and triple layers near the weep holes.
To compare it with the modern material, geocomposite material (laboratory
fabricated) was used behind the weep holes.
174
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
Fig. 2. Location of drains in retaining wall (Froehlich, 2017)
Fig. 3. Excessive settlement and deformation (a) cracking of facing wall, (b) differential
settlement of facing wall, (c) settlement of REW, (d) excessive settlement of facing wall,
(e) differential settlement of REW, (f) deformation of wall) (Lee and Cho, 2011)
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
175
2. MATERIALS PROPERTIES
2.1. Soil Properties
For laboratory experiments, two soils were used: pure sand (S1) and in-situ soil
(S2), which were collected from the college premises. The characteristics of the
soil were found using Indian Standard codes (Table 1).
The particle size distribution of S1 and S2 is shown in Figure 4. From the graph,
Coefficient of Uniformity (c
u
) and Coefficient of Curvature (c
c
) is calculated by
the following equation (2.1,2.2).
10
60
D
D
c
u
=
(2.1)
1060
2
30
DD
D
c
c
=
(2.2)
Where, D
10
, D
30
and D
60
are the particle size corresponding to 10, 30 and 60 %
finer.
Table 1. Properties of the soil
Properties Values for Soil IS Code
S1 S2
c
u
2.857 9.2 IS 2720 (4) : 1985
c
c
1.03 0.735
Specific gravity 2.7 2.2 IS 2720 (3)-1980
Dry Density, kN/m
3
18.36 16.79 IS 2720 (7)- 1987
Optimum Mositure
Content, %
6.8 6
Angle of internal
friction, deg
38 38 IS 2720(13) -1986
Permeability,
mm/sec
2.105 x 10
-
3
IS 2720 (17) -1979
Classification SP (Poorly graded
sand)
SP (Poorly graded
sand)
IS 1498 -1970
176
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
Fig. 4. Soil distribution curve
2.2. Materials used and its properties
Crumb rubber and geocomposite materials were used as drains for the
experiments and its properties were listed below;
1. Crumb Rubber (CR): Recycled material from used tires and its properties are
listed in Table 2. The reuse of used tires is an emerging engineering aspect. It
is widely used as replacement material in concrete for fine aggregate.
Table 2 . Properties of CR
Description and Properties Specification
Ash Content 4.0 - 5.5%
Acetone Extraction 7 - 10
Moisture Content 0.5 % Max
Carbon Black 20 - 25%
Specific Gravity 1.17
Fineness through 30 microns 100%
2. Geocomposite (GC): Due to its longevity, currently geocomposite materials
are widely used in reinforcing and stabilizing the soil. In the current study,
non- woven geotextile sandwiched with geogrid was used as a filter material
(laboratory fabricated – Figure 5) with its properties listed in table 3.
0
20
40
60
80
100
0.01 0.1 1 10
Percentgae Finer,%
Particle Size,mm
S1 S2
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
177
Fig. 5. Geocomposite material
Table 3. Range of values for some properties of Geosynthetics
(Lawson and Kempton, 1995)
Types Thickness,
mm
Mass per
unit area,
gsm
Ultimate
max. tensile
strength,
kN/m
Extensio
n at max.
load, %
Apparent
opening
size, mm
Non-woven
geotextiles 0.25 - 0.75 100 -2000 5 - 100 20 - 100 0.02 - 0.6
Woven -
Geotextiles 0.25 - 3 100 - 1500 20 - 400 10 - 50 0.05 - 2
Geomembranes 0.25 - 3 250 - 3000 10 - 50 50 - 200 0
Geogrids 5 - 15 200 - 1500 10 - 200 5 - 25 10 - 100
Geonets 3 - 10 100 - 1000 - - 5 - 15
3. METHODOLOGY
3.1 Test Tank Set-up
An acrylic tank of 0.3 x 0.3 x 0.3 m tank was fabricated with a scaling factor of
20 as per Buckingham π theorem.
The height of the wall was taken as 6 m, with a wall thickness of 1 m as per
Indian standard 14458 -1 for masonry retaining walls, with toe drain at a height
of 1 m above the foundation and central weep holes with spacing, not more than
3 m (Figure 6). A freeboard of 50 cm was left in the top of the soil. In order to
understand the mean behaviour of the permeability characteristics of soil behind
the retaining wall, weep holes were provided for seepage of water. Five weep
holes were made in an interlaced format with two holes in the top and bottom
and one hole in the centre; for the purposes of the study, a central hole was
considered.
178
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
Fig. 6. Fabricated Tank
3.2 Sample Preparation
The prefabricated acrylic mould was coated with oil/grease in order to avoid
wall friction and leakage of water. Sandy (S1) soil was filled in a mould at an
optimum height of fall - 5 cm determined by relative density test for various
height of fall (Figure 7). In the case of in-situ soil (S2), the soil was cut from an
excavation pit and placed directly into the mould. The water was supplied to the
sample by maintaining constant head delivered from a height of 0.3 m. Initially,
all the holes were blocked, it was let open when the soil was fully saturated
(Figure 8). The water draining from the soil sample through weep holes was
collected and the corresponding time taken was noted.
Fig. 7. Height of fall Vs relative density
0
5
10
15
20
25
55 60 65 70
Heigth of Fall,mm
Relative Density%
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
179
Fig. 8. Setup for the experiment
3.3 Placing of Material
CR: CR was packed at the back of the weep holes in single and three layers and
allowed for water to flow.
GC: The composite materials were placed near the central weep hole and then
the soil was filled.
4. RESULTS AND DISCUSSION
The test was conducted by keeping the water head as a variable – simulating the
falling head permeability condition. The time is taken to collect 1 litre of water
was measured.
Initially, all the tests were conducted by opening all the five weep holes upon
filling the test tank and the results were observed (Figure 9). As the holes were
closed initially and opened upon filling the tank, the time taken for the water to
flow through 5 weep holes was reduced by 66.3% compared to a single hole. As
the time taken was very quick, the central weep-hole alone was chosen for the
study.
180
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
Fig. 9. Comparison of time taken between single and five weepholes
4.1 With S1 soil
For cohesionless, homogenous sand, the time taken to collect one litre of water
through single weep holes was 7.24 minutes. This value was considered as the
base value for further comparison.
Crumb rubber retained on 600-micron sieve (available size) was used in the back
of the weep hole, as smaller particles provided better seepage. However, usage
of CR reduced the time taken to seep by 26.52% and 53.45 % respectively for
single and multiple layers, for example 3 layers. It was observed during the
experiment that the CR started coming out of the weep holes and subsequently,
the CR packing was disturbed due to its finer particle size. In the case of GC, the
time taken had a reduction of about 39.64% (Figure 10).
4.2 With S2 soil
In order to understand the real-time behaviour of the soil, in-situ soil was used
for the tests collected from the college premises. Field soil, otherwise termed as
in-situ soil, showed a heterogeneous combination, which contains a negligible
percentage of fine particles. The presence of organic matter in the top of the soil
was removed manually, as it affects the water flow. The entire test for in-situ
soil was carried out by providing single weep holes.
The time taken to collect 1 litre of water through the in-situ sample was
calculated as 8.47 minutes, which was mainly due to the presence of
heterogeneity. When crumb rubber was placed near the weep holes, the time
Single Five
Serie1 7.24 2.44
0
2
4
6
8
10
Time Taken,min
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
181
was reduced to 5.58 minutes for a single layer. For multiple layers, the seepage
was increased to 50 minutes. During the experiments, it was observed that the
particles started moving and the larger particles clogged the weep holes,
resulting high time taken. In-situ soil with GC shows an appreciable behaviour
by reducing the seepage by 58.68 %, reducing the pressure acting on the wall
(Figure 11).
Fig. 10. Comparison of seepage for various materials - S1
Fig. 11. Comparison of seepage for various materials - S2
S1 S1+CR S1+CR in
layers S1+GC
Serie1 7.24 5.32 3.37 4.37
0
2
4
6
8
10
Time, min
S2 S2+CR S2+CR in
layer S2+GC
Serie1 8.47 5.58 50 3.5
0
10
20
30
40
50
60
Time, min
182
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
There was a decrease in seepage time between 26 and 53.45 % for sandy soil
with crumb rubber (S1) as its packing material behind the weep holes; for
geocomposite material, the seepage time decreased to 39.64%. A non-
degradable man-made material, geocomposite showed a conventional reduction
in seepage time. S1 with three layers of crumb rubber showed more than a 30%
reduction in seepage time compared to S1+GC, which is highly appreciable. For
in-situ soil (S2), the decrease in seepage time was 34.12% for a single layer of
crumb rubber, and for geocomposite material it was 58.68%, which showed a
reduction in time by 42%. Hence, CR can be ideally reused in retaining walls for
drainage purposes, thus providing an effective avenue for water management.
Due to the difference in seepage behaviour of single and multiple layers of CR,
the function of multiple layers should be modelled in the laboratory before
commencing installation work in the field.
5. LIMITATIONS
In order to get a better understanding of the water flow, the top and bottom two
weep holes were closed by keeping the central hole open. The study is a basal
attempt to understand the seepage behaviour, hence the intensity of the rain is
not varied. As the study in this area is limited, an attempt on one to compare the
parameters considered was not possible due to the almount of literature in the
existing area.
6. CONCLUSIONS
From the experiment, the importance of seepage time when various materials are
used behind weep holes retaining walls is important. Here, the packing of
materials also showed a high degree of variation. If CR, a solid waste material, is
used as a single layer, it reduces the seepage time by 34%. In the case of
multiple layers, there was a reduction in time taken for homogenous sandy soil
and an increase in the time taken for in-situ soil as the coarser particles present
by nature itself act as a filter media and retard the seepage flow. This retardation
leads to stagnation of water over its freeboard thickness and reduces the time
taken. Due to the low permeability behaviour of GC, the time taken reduced for
both the soil types.
The largely available solid waste material (CR) showed good improvement in
seepage time, which can be used as an alternative material in the back of
drainpipes to prevent erosion. Seepage time of crumb rubber in the back of weep
holes was compared with conventional geocomposite material.
A PRELIMINARY COMPARATIVE STUDY OF SEEPAGE BEHAVIOUR BEHIND
RETAINING WALLS WITH CRUMB RUBBER AND GEOCOMPOSITE
183
REFERENCES
1. Brooks, H 2010. Basics of retaining wall design. HBA Publ., 11,
220.
2. Gopal, R, Rao, ASR 2014. Basic and applied soil mechanics. 2nd
edition, New Age International Publishers.
3. Froehlich, D 2017. Guidelines for safety inspections of dams.
www.damsafety.in.
4. IS 2720 Part III/Sec 1 (1980 Reaffirmed 2007) Indian
Standard methods of tests for soils- Part III – Determination of
specific gravity, Section 1 – drain pipe soils. Bureau of Indian
Standards, New Delhi.
5. IS 2720 – Part IV (1985 – Reaffirmed 2006) Indian Standard
methods of tests for soils-Part 4 Grain size analysis. Bureau of
Indian Standards, New Delhi.
6. IS 2720 – Part VII (1980- Reaffirmed 2011) Indian Standard
methods of tests for soils - Determination of water content-dry
density relation using light compaction. Bureau of Indian
Standards, New Delhi.
7. IS 2720 – Part XIII (1986 – Reaffirmed 2002) Indian Standard
methods of tests for soils-Direct shear test. Bureau of Indian
Standards, New Delhi.
8. Furumoto, K, Miki, H, Tsuneoka, N and Obata, T 2002. Model
test on the piping resistance of short fibre reinforced soil and its
application to river levee, Geosynthetics - 7 ICG - Delmas, Gourc
and Girard (eds),1241-1244.
9. Lee, KW, Cho, SD 2011. Case of damage and practice of
reinforced earth wall in the country III; Damage cases of
reinforced earth wall. Journal of the Korean Geosynthetics
Society, 10 (1), 8-13.
10. Decorla-Souza, P 2013. Estimation of benefits for benefit-cost
analysis: some troubling issues.
11. Paolo Di Pietro 2013. Geocompositesfor Drainage Experiences
and Applications
https://geosynt.files.wordpress.com/2013/04/maccaferri.pdf.
12. Dahal, RK, Hasegawa,S, Masuda, T and Yamanaka, M 2006.
Roadside slope failures in nepal during torrential rainfall and
their mitigation road construction practice in Nepal. Proc.
184
Vijayasimhan SIVAPRIYA, Chinnusamy SUDHARASAN, Ravikumar SURAJ,
Kalyansundaram ABINAYA
Interpaevent Int. Symp, Niijigata, Disaster Mitig. debris flow,
slope Fail. Landslides. 503-514.
13. Shin, EC, Cho, SD and Lee, KW 2011. Case study of reinforced
earth wall failure during extreme rainfall. In: International
symposium on backward problems in geotechnical engineering
TC302-Osaka, 146-153.
14. Thomas, BS, Gupta, RC, Kalla, P and Cseteneyi, L 2014.
Strength, abrasion and permeation characteristics of cement
concrete containing discarded rubber fine aggregates,
Construction and Building Materials, 59, 204-212.
15. IS 2720 Part XVII (1986 Reaffirmed 2002) Indian Standard
methods of tests for soils - Laboratory determination of
permeability. Bureau of Indian Standards, New Delhi.
16. IS 1498 (1970- Reaffirmed 2002) Indian standard classification
and identification of soils for general engineering purposes.
Bureau of Indian Standards, New Delhi.
17. IS 14458 -1 (1998 – Reaffirmed 2002) Retaining wall for hill area
- guidelines, selection of type of wall. Bureau of Indian Standards,
New Delhi.
18. Lawson, CR and Kempton, GT 1995. Geosynthetics and their use
in reinforced soil. Terram Ltd., Mamhilad, Pontypool, Gwent,
UK.
Editor received the manuscript: 18.11.2019
... If a weepholes is present at various intervals, the pressure exerted by the water table is reduced. Sivapriya et al., [10] made an attempt in understanding the influence of packing material behind the weepholes. ...
... Experimental Set-up[10]. ...
Article
Full-text available
The purpose of retaining wall is used to retain the soils of different elevations. The weepholes are present along the retaining wall to facilitate seepage of water collected in the backfill soil. The purpose of weepholes is to drain the water through drainage constructed along the bottom of the retaining wall. The main factors influencing the seepage in a retaining wall are surface water entry, seepage in utilities and sudden rise in the water table. In this study, the behaviour of weepholes is when a geocomposite is placed in the back of the retaining wall is studied and which is compared to the conventional. Weephole is packed with larger particles in its back. The geocomposite used in the study is a laboratory fabricated material and it is a low density polyethylene with perforation. The test is conducted for two different types of soil; i. soil with specified relative density and ii. Soil with in-situ density. The behaviour of weep holes for the two different soil with a geocomposite is different. Numerical analysis is done to understand the deformation and the pressure along the wall.
... In soil stabilization, various stabilizers, such as lime and cement, are used to improve the mechanical properties of clayey soils [3][4][5][6]. Most of the industrial and agro waste found its way into civil engineering applications either as a primary or binary additive as an effective way of waste management [1,[7][8][9][10][11][12]. ...
Article
Clayey soils can be strengthened and stabilized primarily using a variety of binder materials, such as lime, cement, fly ash, etc., which have been extensively researched. Despite that, recent studies focus on solid waste as binary and tertiary additives along with the activators to improve the strength of clay by considering the aspect of the environment and economy. In this study, bio-stabilized waste ash (BSWA) is considered as a binary additive which was added in the range of 0–25% (% by weight) with 4.5% (% by weight) initial consumption of lime (ICL) into the clay and cured for 0, 7, 14, and 28 days to enhance the index properties and compressive strength of untreated clay. The compressive strength of soil with an optimum percentage of BSWA (15%) and ICL shows a fourfold increase when compared to the virgin soil's strength cured for 28 days. Scanning Electron Microscopy, Fourier Transform Infrared, and X-ray Diffraction analysis depict the noticeable changes in microstructure and mineralogical composition of BSWA-amended clay.
Technical Report
Full-text available
The Central Water Commission is initiating, coordinating and furthering the schemes for control, conservation, and utilization of water resources throughout the country. As part of its institutional strengthening initiatives, CWC published several guidelines and manuals on several topics associ-ated with design, construction, operation, maintenance and rehabilitation of dams. CWC is coor-dinating the implementation of Dam Rehabilitation and Improvement Project (DRIP) with finan-cial assistance from the World Bank. CWC took up the revision of two of the existing guidelines and development of 11 new guidelines along with three dam design review manuals under the aegis DRIP. In revising the guidelines for safety inspection of dams published in June 1987, CWC used the experience gained, and the technological developments over the years. Best practices adopted across the world and experience were also considered in revising the guidelines. Dam Health and Rehabilitation Monitoring Application (DHARMA), the online tool for capturing asset and health data of all the large dams in India is being developed under DRIP. Standardization of inspection reporting formats helps in uploading the inspection reports and for the analysis of the outcomes. The revised guidelines comprehensively cover all the types dam safety inspections specific to different types of dams like embankment dams, concrete and masonry dams, composite dams and the appurtenances such as spillways and outlets. There are more than 5000 large dams in the country, and the detail and frequency of inspections carried out by State Agencies may be at vari-ance. Consolidation of the inspection results and their analysis to develop policy initiatives for sustainable dam safety become difficult. Implementation of these guidelines will improve the effi-cacy of these inspections and provide consistency in report writing and facilitate their analysis. Users may freely download these guidelines from DRIP (www.damsafety.in) and CWC (www.cwc.gov.in) websites.
Article
Full-text available
Nepal is a mountainous country situated in the heart of the Himalaya. The Himalaya is also famous worldwide for its very active tectonics. In Nepal, over 80% of the rainfall occurs within a short three months during the monsoon period and extreme rainfall events are very common such as over 400 mm of rainfall can occur within 24 hours. Thus, these geological and climatic factors make the mountain slopes of Nepal most susceptible for rainfall triggered landslides. In Nepal, to provide transportation facilities to all people, in last ten years, road construction projects are considered as a major part of infrastructure development and the growth of the roads shows exponential increase from 376 km in 1950 to 15,308 km by 2000 within a period of 50 years. In which nearly half of total road length is earthen roads. These road construction and maintenance programs are widely aected by both shallow and deep seated landslides triggered by monsoon rainfall. This paper comprehensively deals with roadside slope failures during torrential rainfall events in major road of Nepal such as Tribhuvan Highway, Siddhartha Highway, Prithivi Highway, Arniko Highway, Dhulikhel-Sindhuli Road, Mugling-Narayanghat Road, Dharan-Dhankuta Road, Pokhara-Baglung Road, Beni-Jomsom Road, as well as some rural roads. Similarly, in this paper, mitigation measures used to stabilize the slopes are also discussed with some illustrations.
Basics of retaining wall design
  • H Brooks
Brooks, H 2010. Basics of retaining wall design. HBA Publ., 11, 220.
Basic and applied soil mechanics
  • R Gopal
  • Rao
Gopal, R, Rao, ASR 2014. Basic and applied soil mechanics. 2nd edition, New Age International Publishers.
Case of damage and practice of reinforced earth wall in the country III; Damage cases of reinforced earth wall
  • K W Lee
  • Cho
Lee, KW, Cho, SD 2011. Case of damage and practice of reinforced earth wall in the country III; Damage cases of reinforced earth wall. Journal of the Korean Geosynthetics Society, 10 (1), 8-13.
Estimation of benefits for benefit-cost analysis: some troubling issues
  • Decorla-Souza
Decorla-Souza, P 2013. Estimation of benefits for benefit-cost analysis: some troubling issues.
Case study of reinforced earth wall failure during extreme rainfall
  • E C Shin
  • Cho
  • Lee
Shin, EC, Cho, SD and Lee, KW 2011. Case study of reinforced earth wall failure during extreme rainfall. In: International symposium on backward problems in geotechnical engineering TC302-Osaka, 146-153.
Geosynthetics and their use in reinforced soil
  • Lawson
  • G T Kempton
Lawson, CR and Kempton, GT 1995. Geosynthetics and their use in reinforced soil. Terram Ltd., Mamhilad, Pontypool, Gwent, UK.