ArticlePublisher preview available

Coordination and optimum design of hybrid circuit breakers for operation in multi-terminal HVDC systems

Authors:
  • IDIADA Automotive technology S.A.
To read the full-text of this research, you can request a copy directly from the authors.

Abstract and Figures

The protection of multi-terminal HVDC systems by means of hybrid circuit breakers is a challenge because without coordination between the circuit breakers some unfaulted sections of the system could be disconnected. This paper proposes a new hybrid circuit breaker operation that accounts for the response of all circuit breakers installed to protect a multi-terminal HVDC system in order to coordinate them and avoid a false operation. The paper also includes the optimum selection of the main circuit breaker parameters installed to protect a multi-terminal HVDC system. The application of the procedure, based on a parallel MATLAB-EMTP application previously presented by the authors, shows that the resulting ranges of parameter values that optimize circuit breaker operations when the goal is to protect a multi-terminal HVDC system can be different from those obtained for a two-terminal system.
This content is subject to copyright. Terms and conditions apply.
Electrical Engineering (2018) 100:2603–2616
https://doi.org/10.1007/s00202-018-0719-3
ORIGINAL PAPER
Coordination and optimum design of hybrid circuit breakers
for operation in multi-terminal HVDC systems
Javier A. Corea-Araujo1·Juan A. Martinez-Velasco1
Received: 2 October 2017 / Accepted: 13 July 2018 / Published online: 2 August 2018
© Springer-Verlag GmbH Germany, part of Springer Nature 2018
Abstract
The protection of multi-terminal HVDC systems by means of hybrid circuit breakers is a challenge because without coor-
dination between the circuit breakers some unfaulted sections of the system could be disconnected. This paper proposes a
new hybrid circuit breaker operation that accounts for the response of all circuit breakers installed to protect a multi-terminal
HVDC system in order to coordinate them and avoid a false operation. The paper also includes the optimum selection of the
main circuit breaker parameters installed to protect a multi-terminal HVDC system. The application of the procedure, based
on a parallel MATLAB-EMTP application previously presented by the authors, shows that the resulting ranges of parameter
values that optimize circuit breaker operations when the goal is to protect a multi-terminal HVDC system can be different
from those obtained for a two-terminal system.
Keywords EMTP ·Fault current limiter ·Genetic algorithm ·Hybrid circuit breaker ·MATLAB ·Multi-terminal HVDC
system ·Parallel computing ·Transient analysis
1 Introduction
A multi-terminal HVDC system is a feasible option for
future transmission systems due to advances in HVDC tech-
nologies: a looped HVDC system configuration can provide
increased system redundancy or reduced investment and
operational costs [1]. However, the protection of a multi-
terminal HVDC system by means of the hybrid circuit
breaker (see [24]) is a challenge since, depending on the
system configuration, ratings and parameters, many (if not
all) circuit breakers can open in front of a faulted condition;
see, for instance, [5].
Some coordination between the circuit breakers installed
to protect the HVDC system is then required to avoid false
operations and allow the unfaulted system to continue operat-
ing. The main goal of this paper is to propose a coordination
method between hybrid circuit breakers in order to isolate
only the faulted system section.
The simulation of a circuit breaker model based on the
hybrid design has been presented in some previous works
[59]. The optimum design of the hybrid circuit breaker using
BJavier A. Corea-Araujo
corea.javier@gmail.com
1Universitat Politecnica de Catalunya, Barcelona, Spain
a MATLAB-EMTP environment that combines the applica-
tion of a genetic algorithm (GA) and parallel computing was
proposed in [10] when the hybrid design was used to protect
a two-terminal HVDC system. Simulations are carried out
using the ATP version of the EMTP.
The goals of this paper are then to propose coordination
between hybrid circuit breakers that could avoid false oper-
ations and perform an optimum selection of circuit breaker
parameters that could obtain acceptable transient responses
when protecting a multi-terminal HVDC system [10].
The paper is organized as follows. Section 2presents
the multi-terminal test system configuration and the circuit
breaker model used in this paper. Section 3provides an
analysis of the fault currents that can occur under different
scenarios in the multi-terminal test system. The results are
used in Sect. 4to justify the coordination between circuit
breakers proposed in this work. The optimum selection of
circuit breaker parameters for operation in a multi-terminal
system using the procedure previously proposed in [10]is
presented in Sect. 5. A discussion about the results presented
in this paper is provided in Sect. 6.
123
Content courtesy of Springer Nature, terms of use apply. Rights reserved.
... For the estimator of confidence interval, it can be assumed that X (1) , · · · , X (k) is the former k > 3& k ∈ Z + of the sample in the two-parameter Weibull distribution with size n. Third-order statistics, where the shape parameter is β, and the scale parameter is η. ...
... where ϕ X (1) , · · · , X (k) , t is the solution of σ X (1) , · · · , X (k) , β ...
... where ϕ X (1) , · · · , X (k) , t is the solution of σ X (1) , · · · , X (k) , β ...
Article
Full-text available
This paper presents an electrical endurance design method of multi-operation isolators using semi-physical simulation via algebraic multigrid iteration (AMG). The mathematical model of Magnetohydro dynamics (MHD) is built by simultaneous equations of mass conservation, horizontal momentum, vertical momentum, conservation equation of ion energy, as well as electromagnetic equation. In addition, the physical properties of plasma medium in non-solid state, including thermal conductivity, electrical conductivity, dielectric density over temperature are used to dynamically update the coupled multi-physics. The established model can thus be solved via AMG, which is a fast iterative method for solving large-scale sparse normal equations based on geometric multigrid method. The finite element method (FEM) is likewise conducted under the various operating conditions to seek arc plasma temperature, the electric potential, electromagnetic distribution. The electrical endurance reliability can be reckoned using the maximum likelihood estimator of the desired shape parameters and scale parameters of Weibull's distribution, by integrating analogical semi-physical simulation. The physical experiment is carried out which involves electrical safety test, the withstanding voltage test, also called Hipot test or dielectric test, arc ignition test, resistance test. It proves that the proposed method can realize the endurance design of electrical equipment with high convergence efficiency and low residual error, and is especially suitable for the analysis under multiple working conditions.
Patent
Full-text available
A device (13) to break an electrical current flowing through a power transmission or distribution line (14) comprises a parallel connection of a main breaker (8) and a non-linear resistor (11), where the main breaker (8) comprises at least one power semiconductor switch of a first current direction. The device (13) further comprises a series connection of a high speed switch (10) comprising at least one mechanical switch and of an auxiliary breaker (9), the auxiliary breaker having a smaller on-resistance than the main breaker (8) and comprising at least one power semiconductor switch of the first current direction. The series connection is connected in parallel to the parallel connection. In a method to use the device (13) first the auxiliary breaker (9) is opened, thereby commutating the current to the main breaker (8), afterwards the high speed switch (10) is opened and afterwards the main breaker (8) is opened thereby commutating the current to the non-linear resistor (11). The device (13) can further be used in a current limiting arrangement.
Article
The optimum design of power system components is becoming a relevant topic in power system studies. Genetic algorithms (GAs) are considered as a proper approach for optimisation problems in which non-linear elements are involved. Several trends are presently leading GAs to a new level; for instance, its combination with parallel computing can facilitate the solution of problems where individual evaluations of the fitness function require an important computational effort. This study presents a procedure based on a MATLAB-EMTP application and the usage of a multicore environment for the optimum selection of hybrid high-voltage DC (HVDC) circuit breaker parameters; the goal is to obtain a transient response of the hybrid design with voltages, currents and fault clearance times within specified limits.
Article
The hybrid circuit breaker design offers a fast low-loss operation that can be of paramount importance for the development of future meshed HVDC systems. This paper summarizes the main results obtained from a parametric analysis based on a simplified representation of both the circuit breaker and the test system. The main goals are to investigate the operation of the new device when running as a fault-current limiter and find out the influence that some breaker and system parameters (e.g. prospective short-circuit current in the test system, operation time of the mechanical switch, cable length, fault position, rated voltage of arrester) can have on the overcurrents and overvoltages that will occur during breaker operation. The results derived from this study can be useful for choosing some breaker parameters and to lesser extent for improving the breaker design.
Article
ABB and its predecessor companies pioneered HVDC (high-voltage direct current) technology, permitting low loss transmission of power over long distances. All HVDC lines realized so far have been point-to-point links. The scope of application of the technology could be greatly increased if lines could be built with more than two terminals, enabling them to develop into HVDC grids. However, the absence of a suitable breaker for the required voltages and speeds and with acceptable losses has hitherto prevented the advent of such topologies for HVDC. All this has changed with the launch of ABB's new HVDC breaker.
Article
The modelling principles for hybrid DC circuit breakers (CBs) which is developed to support DC grid protection studies and transient studies involving DC protection are studied. The coordinated control and interlocking of the four subunits (two semiconductor valves and two mechanical switches) are analysed. The model represents accurately the opening sequence, closing sequence and a modified model which includes DC fault current limiting mode (for short duration). The CB self-protection and driver-level valve protection are included in the model. Unidirectional DC CB and bidirectional DC CB are presented. Simulations on EMTP-RV are used to verify the proposed models. The key operating conditions are tested, such as: opening the DC CB under fault current, malfunction of upper layer protection system, re-closing a DC CB under rated DC current, re-closing a DC CB to DC fault and current limiting (for short duration) control of the DC CB.
Conference Paper
The requirements of dc circuit breakers used to protect multiterminal HVDC networks are specified by the prospective fault current. The fault current, however, strongly depends on the grounding scheme of the network. Low-ohmic and high-impedance earthing practices with different grounding points are presented and compared with each other in terms of fault currents and overvoltages during a pole-to-ground fault. To do so, monopolar and bipolar configurations of a multiterminal HVDC cable network are implemented in PSCAD and simulations are performed.
Article
In a multiterminal HVDC network, dc circuit breakers (CBs) are required at each end of a line to selectively isolate a fault. Several CB concepts have been implemented in PSCAD, which differ significantly in their structure and performance. This paper describes the interaction of the different HVDC CB topologies with a meshed four-terminal network and assesses their performance in terms of maximum currents and voltages. The tradeoff between network parameters and CB requirements is analyzed.
Conference Paper
The development of a large scale high voltage direct current (HVDC) power grid requires a reliable, fast and low-loss circuit breaker. The load commutation switch (LCS) is an essential part of ABB's 1200 MW hybrid HVDC breaker concept which builds up a low-loss conducting path for the load current. The technical requirements for the LCS are expressed in this paper by studying the operation principle of the hybrid HVDC breaker. The voltage stress over the LCS is calculated and simulated based on a dc grid with 320kV and 2kA rated voltage and current. A system model of the hybrid HVDC breaker is developed in PSCAD/EMTDC software to study the design criteria for snubber circuit and arrester blocks. It is observed that conventional snubber circuits are not suitable for a bidirectional hybrid HVDC breaker as the current of snubber capacitors prevent the fast interruption action. A modified snubber circuit is proposed in this paper along with two more alternatives for the load commutation switch to overcome this problem. Moreover, the power loss model for a semiconductor device is discussed in this paper based on the 4.5 kV StakPak IGBT. The model is used to calculate the conduction power losses for different LCS topologies. Ultimately, a matrix of 3x3 IGBT modules is selected to provide a reliable LCS design which can handle several internal fault cases with no interruption of operation. A full-scale prototype has been constructed and tested in ABB HVDC Center, Ludvika, Sweden. The experimental test results are also included in the paper in order to verify the calculation and simulation study.