New Era of Project Delivery – Project as Production System

Authors:
  • The RBR Group
  • Project Production Institute

Abstract and Figures

Project management can be viewed as having developed over 3 distinct time frames, or Eras, in response to the evolving nature and needs of projects over time. Viewing project management through the framework of the 3 Eras provides a number of useful insights described in this article. Conventional project management, as codified by the Project Management Institute, spans the first two Eras. It has two fundamental gaps, preventing the satisfactory management and execution of today's complex and dynamic capital projects. Understanding these gaps explains why some traditional responses to recover from cost and schedule overruns in projects do not work. We describe how Project Production Management (PPM) provides the two missing elements of conventional project management. We conclude with the perspective that PPM ushers in a new third era of project management to address today's complex major projects operating in dynamic environments.
Content may be subject to copyright.
© 2016 Project Production Institute | Volume 1
New Era of Project Delivery –
Project as Production System
Ram Shenoy, PhD1 and Todd R. Zabelle 2
1Tehnical Director, Project Production Institute, 716 Montgomery Street, San Francisco, CA 94111
* Ram Shenoy (rshenoy@projectproduction.org)
2 Founder & President, Strategic Project Solutions, Inc., 1040 Battery St, San Francisco, CA 94111
* Todd R. Zabelle (tzabelle@spsinc.net)
ABSTRACT
Project management can be viewed as having developed over 3 distinct time frames, or Eras, in response
to the evolving nature and needs of projects over time. Viewing project management through the
framework of the 3 Eras provides a number of useful insights described in this article. Conventional
project management, as codified by the Project Management Institute, spans the first two Eras. It has two
fundamental gaps, preventing the satisfactory management and execution of today’s complex and
dynamic capital projects. Understanding these gaps explains why some traditional responses to recover
from cost and schedule overruns in projects do not work. We describe how Project Production
Management (PPM) provides the two missing elements of conventional project management. We
conclude with the perspective that PPM ushers in a new third era of project management to address
today’s complex major projects operating in dynamic environments.
Keywords: Project Management; Project Production Management; Production System; Variability;
Buffers
INTRODUCTION
The engineering and construction industry is in crisis. The situation now affects shareholder value for
asset owners, developers, operators, contractors, suppliers and society in general. It is of particular
concern for energy, manufacturing and processing companies. As producers, these companies must
continue to invest capital to bring new solutions to market, optimize production capacity and comply with
regulatory requirements. Addressing less than desirable project outcomes has now become a priority for
executives and corporate boards.
Capital project outcomes continue to frustrate business executives and their shareholders across a range of
industries. A 2014 Ernst & Young survey1 concluded that nearly 65% of major capital projects in the oil
& gas industry suffered cost overruns, and over 75% suffered schedule overruns. Professor Paul Teicholz
1 “Spotlight on oil and gas megaprojects”, Ernst & Young, 2014
© 2016 Project Production Institute | Volume 1
of Stanford University has conducted research studies2 comparing productivity in the manufacturing
industry with productivity in the construction industry, concluding that the productivity in the
construction industry has stagnated over the last half century, whereas manufacturing productivity has
increased 150% over same period. Statista, an online statistics portal, presents a capital projects “hall of
fame”, seen in Figure 1, comparing recent over-budget construction projects across the world, starting
with the Channel Tunnel. The top 12 projects have cost overruns ranging from 100% of planned budget to
300% of planned budget.
Figure 1: “Hall of fame” for major infrastructure projects with cost overruns
Recognizing the current critical state of the industry and associated impact on business and shareholder
value, companies involved in the delivery of capital projects are implementing a host of solutions,
including multi-party relational contracts, increased levels of project controls, methods to ensure supply
of information and goods to the workface, and more. Despite these attempts however, performance
continues to decline.
2 “Trends in labor productivity in the construction industry”, P. Teicholz, PPI Symposium, Dec 2015
© 2016 Project Production Institute | Volume 1
Historical analysis of the evolution of project delivery methods sheds light on why project performance
continues to degrade despite the proliferation of conventional project management practices. The subject
of project management can be viewed as an evolution over three major eras, as illustrated in Figure 2.
Figure 2: The 3 Eras of Project Delivery
Era 1 - Scientific Management
Era 2 - Project Management
Era 3 - The emerging construct of Projects as Production Systems
By viewing Era 1 + Era 2 as “conventional project management,” the lens of the 3 Eras highlights a few
gaps in conventional project management practices when applied to today’s complex and dynamic
projects. The first gap is that conventional project management does not include detailed project work
execution - operations management - within its scope. The second gap of conventional project
management is that it does not systematically account for the impact of variability and work-in-process
(WIP, or inventory) during project execution. Understanding these gaps explains why some typical
responses from conventional project management practitioners to cost and schedule overruns are
ineffective, as described here.
The emerging Era 3, Projects as Production System construct, addresses the gaps of conventional project
management. We conclude that implementing Project Production Management ushers in a new era of
project delivery to produce major capital project outcomes superior to the recent past.
ERA 1 – SCIENTIFIC MANAGEMENT
Starting in the early 1900’s, Frederick Taylor was in the vanguard of a movement preoccupied with
organizing and managing the work of laborers in factories. The primary task Taylor focused on was “how
to get more out of workers,” with a view to improve overall productivity through understanding and
organizing the tasks performed by workers. Through time-motion studies and other analyses, he tried to
convert the jobs performed by individual factory workers into sequences of simplified tasks for which
workers could be trained to execute as quickly as possible. Through this body of work, Taylor established
many of the practices that are still in use today. These include the separation of planning the work from
doing the work, the advent of functional departments, and the application of time-motion studies and
activity sampling, amongst many other innovations.
ERA
-1
PRODUCTIVITY
1900
-1950
ERA
-2
PREDICTABILITY
1950
ERA
-3
PROFITABILITY
2000
SCIENTIFIC MANAGEMENT PROJECT MANAGEMENT PROJECT AS PRODUCTION SYSTEM
How to get more out of workers?
How to predict project outcomes through
measurement and compliance?
How to deliver business objectives with
minimal use of resources?
© 2016 Project Production Institute | Volume 1
In 1918, Daniel J. Hauer translated Taylor’s concepts from the shop floor to the construction site in his
book, Modern Management Applied to Construction. Henry Gantt, another disciple of Taylor, added
planning and control tools, including the ubiquitous Gantt chart, to Taylor’s management system.
Together these men built the foundation upon which projects are delivered today. The use of centralized
planning/project controls, the application of activity sampling to determine “time-on-tools,” and the use
of bar charts are just a few of their concepts that continue to be used in project management, stemming
from Era 1.
Era 1 is best understood as the era focused on getting more out of craft workers through the brute force of
Taylor’s Scientific Management.
ERA 2 – PROJECT MANAGEMENT
If Era 1 management focused on “how to get more out of workers” and on labor productivity, then
Era 2 management focused on “how to get more predictable outcomes through measurement /
compliance / controls.”
By the 1950’s, it was clear that Era 1 practices were not enough to manage the projects of the time.
Projects were increasing in size and complexity, and cost and schedule overruns were becoming
increasingly unpredictable. Frustrated with the outcomes of mission critical defense projects, the U.S.
Department of Defense under Secretary of Defense Donald McNamara launched US DoD 7000.2,
C/SCSC. This initiative, along with the Navy’s development of the Program Review and Evaluation
Technique (PERT) and Remington Rand Univac’s work with DuPont in the development of the critical
path method (CPM) scheduling approach, all set the foundation for modern day project controls.
The development of these tools for forecasting only increased the separation of planning activities from
work execution activities. As a result, during Era 2, project management moved further and further away
from its roots in operations, increasing the intensity of its focus on planning and prediction. In their 1959
paper, “Critical-Path Planning and Scheduling,”3 James E. Kelley and Morgan R. Walker introduced
CPM and listed four tasks of project managers:
1. To form a basis for prediction and planning
2. To evaluate alternative plans for accomplishing the objective
3. To check progress against current plans and objectives, and
4. To form a basis for obtaining the facts so that decisions can be made and the job can be done
3 James E. Kelley, Jr. and Morgan R. Walker, “Critical-Path Planning and Scheduling” 1959 Proceedings of the Eastern Joint
Computer Conference. Retrieved from https://www.computer.org/csdl/proceedings/afips/1959/5055/00/50550160.pdf
© 2016 Project Production Institute | Volume 1
Over time, these advanced forecasting tools became the basis of protecting / seeking claims for schedule
acceleration and delay in planning functions. Arguments ensued over who owned the floatwithin the
schedule duration and how it should be allocated. These arguments manifested into strict specifications
about how project schedules are to be created and updated, especially by governmental entities. To this
day, it is not uncommon to have two or more schedules for a project: “one for the owner” and the other
for managing the project.
ERA 1 + ERA 2 = CURRENT APPROACH
“Conventional project management,” which we define here as the combination of the Era 1 and Era 2
bodies of knowledge, has two fundamental insufficiencies to deliver today’s complex and dynamic
projects. First, the focus on planning and forecasting and the exclusion of operations management from
scope overlooks the need to organize detailed work activities within the project in order to control overall
project performance. Second, there is little to no consideration of the impact of variability and inventory
on overall project delivery. To not recognize variability and inventory is to not recognize the exponential
compounding effect that variability and inventory have upon each other and on total project performance.
We elaborate upon each of these insufficiencies below.
Conventional project management focuses on planning and reporting. The execution of a projectthe
hands-on work of operations management was outside the purview of project management, a move that
occurred during Era 2. Excluding operations management is still the case today. The current edition of the
Project Management Book of Knowledge (5th edition), issued by the Project Management Institute (PMI),
states in Section 1.5.1.1:
“Operations management is a subject area that is outside the scope of formal project management as
described in this standard.
Operations management is an area of management concerned with the ongoing production of goods
and/or services. It involves ensuring that business operations continue efficiently by using the optimum
resources needed and meeting customer demands. It is concerned with managing processes that transform
inputs (e.g. materials, components, energy and labor) into output (e.g. products, goods, and/or services).”
PMI clearly states that operations management is out of the scope of project management, as defined by
PMI and the Project Management Book of Knowledge. PMI recognizes that operations management
exists, but it positions that discipline as an engineering science that comes into play only after a capital
project is complete and ready to begin operations. According to PMI, operations management is not
something that can be effectively applied to the project delivery process. Actually, as we subsequently
describe, the configuration of operations, especially to be robust to control the impact of variability and
inventory, is a distinguishing feature of Project Production Management.
Why are variability and inventory so important? What are their effects on project performance? A few
examples can illustrate how viewing the work to be performed in a project is no different from a
production system.
© 2016 Project Production Institute | Volume 1
First, let’s consider a very simple production system: the assembly of burgers in a fast food restaurant. It
is a production system because burgers are assembled from inventories of ingredients in response to
orders placed by customers. There are various types of variability encountered in the production process,
for instance:
- Variability in the times orders are received
- Variability in the type of order for instance a cheese burger vs. a plain burger
- Variability in the cycle times in performing different steps
- Variability in availability of certain ingredients
- Variability in amount of staff throughout the day
All these variations present challenges for the restaurant in meeting its goal of satisfied
paying customers at a target price. For instance, if the restaurant takes too long to assemble and deliver
burgers because it doesn’t have enough staff to assemble burgers (or shortage of ingredients), customers
stop coming. If one person completes their tasks in the assembly of a burger much faster than the next
person who takes over, then an inventory of unfinished burgers (work-in-process) builds up.
Variability can be beneficial or detrimental. New technology or new techniques for assembly are
examples of beneficial variability, where re-sequencing food preparation tasks can potentially shorten
cycle time without increasing tasks. Other types can be detrimental for instance, having delays because
one runs short of inventory or because equipment breaks down. It is frequently possible to take steps to
reduce detrimental variability in operations. For example, to ensure one doesn’t have unanticipated
delays, implementing automated re-stocking of inventory once it reaches a minimum level, or frequent
inspection and maintenance of equipment, are standard ways of ensuring detrimental variability is kept to
a minimum.
Uncontrolled variability will give rise to uncontrolled inventory / increased cycle time, loss of capacity or
some combination thereof. While it is frequently possible to take steps to reduce detrimental variability, it
is rarely possible to wholly eliminate it. One can manage residual detrimental variability by placing
buffers in the assembly process - having the appropriate combination of inventory (ingredients), capacity
(staff) and time. For instance, in order to have the fastest delivery times, one can have an inventory of pre-
prepared burgers ready to go in response to orders as they are placed. Or one can have plenty of staff, and
plenty of ingredients to ensure burgers are prepared as fast as possible in response to orders not quite as
fast as pre-assembled burgers, but fast nonetheless. Or one can have much longer times to deliver burgers,
by having a minimal staff and minimal stock of ingredients. Different combinations of inventory, capacity
and time have different costs and financial impact on the economics, not to mention the time of delivery.
A second example to show how variability can be managed through an appropriate combination of
inventory, capacity and time is by comparing oil changes done for Formula 1 with a retail automotive tire
repair chain. In Formula 1, the extreme variability of arrival times the uncertainty of when a car comes
© 2016 Project Production Institute | Volume 1
in within a 4-hour period for a tire change is handled by having a massive capacity of technicians,
equipment and an inventory of supplies to ensure the shortest possible time spent in executing a tire
change. The utilization of capacity is extremely low, however, the execution cycle time is extremely fast.
In contrast, a retail tire repair chain targets an acceptable waiting time to manage the economics of having
capacity that’s working at close to full utilization. As a result, execution cycle time goes up in response to
working at close to full capacity.
The same principles of variability and inventory compounding each other’s effects in project performance
are at play in construction projects and oil & gas capital projects, just on a much bigger scale. In a
construction project, there is variability in execution times of the individual work steps to be performed.
There will be variation in arrival times of supplies to the construction site. There may be variation in the
availability of trades and construction equipment required to execute work. This, and myriad other types
of variability, can give rise to unwanted or unplanned inventory work-in-process as individual work
stages are completed, but then must wait for the next stage of work to start.
As with the two examples cited earlier, variability can be managed by a judicious combination of inventory,
capacity and time to place buffers along appropriate places in the project’s execution workflow in order to
optimize the throughput through the project.
While our discussion has been qualitative, there are systematic and scientific ways of analyzing the
behavior of processes in the presence of variability, and a science to design actions to mitigate detrimental
variability, as well as a science to design the optimal allocation of buffers to manage residual detrimental
variability. This is part of the foundation of Project Production Management and is further elaborated in
articles by Spearman & Pound and by Choo later in this journal. The systematic accounting for variability
with actions to reduce and to buffer is one way in which PPM is distinguished from conventional
project management.
The absence of scientific design in project execution has had a profoundly negative impact on capital
project performance in the construction and oil & gas industries. A classic practice in oil & gas is to
amass a lot of inventory in the belief that having plenty of inventory on hand will assure continuous
smooth execution with minimal delays. But inventory, besides being very expensive to have extra on
hand, is subject to its own variability (spoilage, obsolescence), and is not always the most effective buffer
against the types of variability that are actually encountered in oil & gas projects. Because variability in
the project work continues to cause unplanned outcomes, the results are large costs from setting up the
wrong type of buffer, project delays, poor quality and excess work-in-process. The financial and schedule
overruns in recent years have been spectacularly bad, as exemplified by the exhibit in Figure 1, and cited
in the oil & gas megaproject study by Ernst & Young.
While capital projects are failing to hit their targets, the connection between project misses and the two
insufficiencies of conventional project management is not obvious to many. This may be a function of the
power of the conventional project management paradigm and its supporting infrastructure. Regardless of
why the connection is not being made, it has given rise to a number of ineffective responses that require
greater investment by oil and gas executives without eliminating cost overruns and scheduling delays.
© 2016 Project Production Institute | Volume 1
These widely-adopted responses include:
- Project controls: Project controls are project management practices on steroids. They attempt to solve
the capital project problem by driving project management down to lower levels of a project’s
organizational chart. This means more reporting on what work has gotten done and how much it has
cost, and more forecasting of the work that needs to get done and how much will it cost. More reporting
and forecasting of time and costbut, as in project management, the execution of the project remains
outside the realm of project controls.
- Contracts: Contracts are an attempt to offload the risk of capital project misses. They encompass a
variety of models, all of which attempt to reduce or transfer risk and achieve project targets by using
incentives and/or penalties to modify behavior. Contracts cannot, of course, address the execution of
work in and of themselves. At best, they are legal constructs that shift costs, without addressing the root
causes. At worse, as research on using money to change behavior has shown, a contract approach to
capital project success is both expensive and ineffectiveoften encouraging people to focus on the ends
instead of the means, and to try to game the system.
- Modularization and offsite assembly: Modularization and offsite assembly respond to the capital
project problem by shifting the workideally, to somewhere where assembly costs are lower and
conditions are easier to control than the often remote and dangerous project locations. Unfortunately,
these responses introduce new problems. First, they add complexity to the project’s supply chain, which
makes it increasingly difficult to plan and execute the project. Second, although assembly costs may be
lower offsite than onsite, the cost savings tend to be illusionary because modularization and offsite
assembly come with less-recognized WIP costssuch as those associated with longer lead times,
transport, handling, and storage. Beyond these issues, the need for these components to be integrated at
the site also brings a host of challenges.
- Workface planning: Workface planning attempts to reduce the capital project problem to a labor
problem. To boost time on tools, its adherents break down tasks into work packages. Multiple packages,
which might encompass 500 to 2000 hours of work and involve several trades, are delivered at the
workface to enhance productivity by helping workers ensure that they have the information, materials,
and tools needed to complete a specified task before they try to execute it. In essence, workface
planning is a hybrid extension of project management and modularization, with work being planned and
assembled weeks in advance that may or may not be possible to execute at its scheduled time.
However, the four responses described above share the same flaws found in conventional project
management itself, being that:
1. None of them attempt to directly manage the execution of work
2. None of them recognize, account for, or attempt to manage variability and WIP
As a result, they ultimately add cost and complexity to the project, without solving the core problem that
is endemic throughout the engineering and construction industry.
© 2016 Project Production Institute | Volume 1
The Construction Industry Institute (CII) and Construction Owners Association of America (COAA)’s
Advanced Work Packaging (AWP) approach is a good example of the Era 1 combined with Era 2
construct. AWP endeavors to increase time-on-toolsby ensuring all necessary information, materials
and construction equipment are available for the craft person when needed. However, it ignores the more
important task at hand, which is effectively completing work in the right quantity, at the preferred
quality and the desired time.
The implications of variability and excessive work-in-process should not be overlooked. Since
conventional Project Management does not recognize variability and WIP, inventory is often used to
shield downstream work enabling increased capacity utilization.
At the root of the issue is the cost and time required to amass, handle, hold and preserve inventory, not to
mention the risk of obsolescence, theft and damage. This cost is not only related to the financial
investment but also to the unnecessary use of cash. Often called pre-productive capital, WIP is the
equivalent of cash that is not earning a return on investment because the project is not complete and/or
due to lost opportunity cost.
Project managers and business leaders are often called upon to develop cost and schedule recovery plans.
These efforts have limited impact due to the amount of WIP in the system. Frederick Gluck and Richard
Foster pointed out that the ability to influence decreases with time.4 We propose that this decrease is
directly related to the amount of WIP in the system, as illustrated in Figure 3.
4 Managing Technological Change: A Box of Cigars for Brad. Gluck, Frederick W. and Foster, Richard N. Harvard Business
Review, 1975.
© 2016 Project Production Institute | Volume 1
Figure 3: WIP reduces ability to influence
ERA 3 – PROJECT AS PRODUCTION SYSTEM
Beginning in the early 1990’s at the Stanford Center for Integrated Facility Engineering (CIFE), Lauri
Koskela, PhD, a visiting researcher from Finland, asked, “can and how does the new production paradigm
apply to the delivery of projects?”
Guided by reports coming from the automotive and other manufacturing sectors, researchers at Stanford
and U.C. Berkeley, including Glenn Ballard PhD, Martin Fischer PhD, Greg Howell P.E, Iris Tommelein
PhD and later James Choo PhD, began developing a production-focused approach to project delivery.
These efforts identified key factors missing in the constructs of Era 1 and Era 2, including sizing and
locating of buffers, sources and implications of variability as well as the lack of effective production
control. At the same time, Pacific Contracting of San Francisco and later BAA and its supplier network,
began experimenting with the application of this new paradigm. One such example was the successful
delivery of the construction phase of Heathrow Terminal 5.
Looking back at Henry Ford’s system of Mass Production and Frank Woollard’s Flow Production
followed by Toyota’s Production System, the key strategies of all these manufacturing systems include
maintaining a flow of production from the beginning to the end of the process or the value stream by
reducing variability and effectively controlling the amount of work-in-process.
© 2016 Project Production Institute | Volume 1
Figure 4: Contrasting Era 1 + Era 2 Conventional Project Management
with Era 3 Project as Production System
The figure above illustrates the contrast between conventional project management Era 1 + Era 2 with
Era 3 - Project Production Management.
Conventional project management is a tradeoff between cost, time and scope, using the levers of scope or
quality, process design and capacity. Those using the forecasting/planning tools of conventional project
management typically make statistical assumptions about how long project work execution should take,
and what it should cost, without a detailed analysis of how the work should be configured or executed.
This typically happens because they are not directly responsible for it, or lack the subject matter expertise
to organize the work, even if they bear responsibility for it. Process design is performed by the planning
functions using tools such as work-breakdown-structures, rather than by those doing the work.
As for setting capacity, project managers trained in conventional project management set capacity within
the overall constraints of cost, and by comparing what past projects have used for capacity. There is
generally little to no consideration of the strategic allocation of capacity across different parts of the
project as a buffer to optimize execution of work. Conventional project management generally seeks to
maximize the utilization of the most expensive capacity within the project, in a belief that maximizing
capacity utilization optimizes overall project execution performance in terms of cost and time to execute
Taylor’s construct for Scientific Management.
Project Production Management seeks to optimize cost, time and scope with the levers of process design,
capacity, inventory and variability.
PPM approaches process design very differently from conventional project management because it seeks
to design processes accounting for the impact of variability through the strategic placement of buffers
PROJECT MANAGEMENT
PRODUCTION MANAGEMENT
Cost,
Time
&
Cash
Process Design Resource Use
Cost,
Time
&
Cash
Capacity Inventory Variability
Scope & Quality
Process DesignScope & Quality
© 2016 Project Production Institute | Volume 1
within the process. Moreover, the science of operations management dictates that buffers can be some
combination of inventory, capacity and time not simply capacity. PPM systematically takes into account
all these considerations to optimize project delivery.
Four theoretical operations management results, outlined in the basic text by Philip M. Morse5 and
recapped by Wallace J. Hopp and Mark L. Spearman,6 form the basis of the systematic analysis of a
project to understand the limits on performance at any point in the project and the overall limits:
1. In 1954, Morse proposed and in 1961 Little validated the queuing equation, relating work-in-process
(WIP, or inventory) that arises from the execution of a task to the cycle time to execute the task, and
the throughput (number of times per unit time) of completing the task.
That equation is: WIP = Throughput x Cycle Time
2. The cycle time formula denotes all the component times that contribute to the overall cycle time in
executing a work task within a project.
3. As work tasks accumulate or queue to be completed at a point in a project, Sir John Kingman, a
British mathematician, set forth an equation, known as the VUT equation. This equation
approximates the mean waiting time in a queue using variability, capacity utilization and service rate.
4. Variability at any point in a project will be buffered by a combination of inventory (WIP), capacity
and cycle time.
These results are instrumental in incorporating knowledge about capacity and variability in a project to
design both the project work (process design) and set limits on capacity and inventory to optimize project
execution throughput. This is a fundamental difference from conventional project management.
CONCLUSION
Viewing project management through the lens of the 3 Eras provides a foundation upon which to
understand its evolution and where we are today. Conventional project management can be viewed as the
culmination of Era 1 and Era 2. Project Production Management (PPM) overcomes two fundamental
limitations of the conventional project management approach and ushers in a third Era of project
management necessary to address the challenges of today’s complex and dynamic capital projects. Now
that the underlying physics of project delivery can be understood through the application of operations
management / science, it is time to apply the necessary principles to today’s large capital projects.
5 Queues, Inventories and Maintenance: The Analysis of Operational Systems with Variable Demand and Supply, P. M. Morse,
John Wiley & Sons, 1962.
6 Factory Physics, W. J. Hopp and M. L Spearman, 3rd Edition, Waveland Pr. 2011.
... A common practice in delivering construction projects (or simply 'projects') is to use "conventional project management" (simply 'PM') as a body of management knowledge [1]. However, this body of knowledge lacks two fundamental concepts that are useful in delivering projects, as Shenoy & Zabelle [2] pointed out. First, conventional project management practices focus on planning and forecasting, but ignore that production occurs throughout the project thus overlooking the need to organize detailed work activities, resources that perform the work, and inventories that determine the actual duration of the work and thus affects overall project performance. ...
... When applied to projects, it is called Project Production Management (PPM). PPM is viewed as the delivery model for the 3rd era of project delivery [2]. ...
Article
Full-text available
Managers of construction projects have been focusing on cost, schedule, quality and safety to measure project performance using conventional metrics from administration management. These conventional metrics have led them to underestimate or overlook how variability, prerequisites for starting work, and work-in-process (WIP) affect project performance, which is a problem. To tackle this problem, concepts from Operations Science (OS) can be applied to construction production system design (PSD), focusing on metrics pertaining to throughput, work-in-process, cycle time, and capacity utilization. While the application of these concepts in building construction is still uncommon, this paper demonstrates by means of an example case study (a healthcare building in Northern California) how this may be done. Since OS has its foundation in a manufacturing industry context, this paper will comment on the assumptions necessary to apply it in a construction industry context and the implications of these assumptions. The methodology used in the case study leverages the use of an OS-based production analytical model. This case study illustrates the use of OS metrics at the project level, given certain assumptions (i.e., steady-state production system, no matching problem). As a conclusion, the use of OS for PSD provides a basis for understanding the “behavior” of a construction project and its performance regarding interrelated OS metrics.
... In other words, the Product-Process matrix provides a unifying framework to understand production systems, with the same theoretical principles applying to any of them. Making this observation allows us to apply the tools of operations management to model any of these production systems and optimize them, as we at the Institute have advocated for [10], using the PPM framework illustrated in Figure 2. The ability to model project execution, to predict the limits of performance, to model how variability propagates across the different dimensions of a project, and to identify where best to implement control mechanisms to mitigate and manage variability is what distinguishes PPM from other methods and practices that are advocated for improving project execution and delivery. No other discipline for project management has a theoretical framework that uses actual data from outcomes on project activities to predict limits on project execution performance and identify what is genuinely achievable. ...
Article
Full-text available
Project Production Management (PPM) is sometimes described as “applying manufacturing techniques to projects,” implying that PPM only applies to scenarios with highly repeatable and predictable conditions. Consequently, many experienced project professionals mistakenly believe that PPM denotes a “manufacturing approach” to capital projects. To the contrary, evidence shows that PPM applies to the execution and delivery of all projects, large or small, customized or standardized, and improves upon prior conventional project management practices. We further demonstrate that, depending upon the complexity of scope, implementation of PPM on “one-off” projects is even more critical to achieving stated objectives. PPM is based on operations sciences, a well-established field of engineering, as the foundation of production systems. All manufacturing systems are production systems; however, not all production systems are manufacturing systems. A deeper analysis of the work activities in projects shows different types of production systems embedded within a single project. Describing project work activities as a set of interconnected production systems makes them amenable to the modeling and analysis tools of PPM. These tools can be used to predict the limits of project execution and where best to manage variability through the strategic allocation of buffers such as capacity, inventory and time. Select case examples are included to illustrate these concepts.
... Inventory word uses in American English or stock in British English, means the goods and materials holds by a business for the ultimate goal of sale, resale and repair (Chase, Aquiline & Jacobs, 1998). The concept of inventory, stock and work-in-process has been extended from manufacturing systems to service businesses (Chase, Aquiline & Jacobs, 1998;Jacobs & Chase, 2010;Pound, Bell & Spearman, 2014) and projects (Zandin, 2001;Shenoy & Zabelle, 2016) by generalizing its definition. Its definition extends from all work within the process of production to all work done towards the completion of production. ...
Article
Full-text available
This study is the second paper of the series of the diagonal model of job satisfaction and motivation: Extracted from the logical comparison of content and process theories that was published in the international journal of Higher Educations. It focuses on the designing of inventory of job satisfaction and motivation of teacher educators to know their level of satisfaction and motivation through explored criteria by diagonal model consists of four levels i.e. extremely satisfied and motivated; highly satisfied and motivated; moderately or normally satisfied and motivated; and dissatisfied and demotivated. It emphasizes the sixteen factors of job satisfaction and motivation each means a total of thirty-two factors with their sub-factors and further statements. The findings are finalized in the shape of inventory, which would be a reliable resource and a good addition to the existing literature of satisfaction and motivation to understand the phenomenon deeply in teacher education institutions of Sindh, Pakistan.
... On the one hand, this is unnecessary production and increases costs for resources such as raw materials, workforce, or storage space. Balancing these competing requirements leads to optimal inventory levels, which is an ongoing process as the business needs shift and react to the wider environment (Shenoy & Zabelle, 2016). Inventory management concerns the balance between replenishment lead time, carrying costs of inventory, asset management, inventory forecasting, inventory valuation, inventory visibility, future inventory price forecasting, physical inventory, available physical space, quality management, replenishment, returns and defective goods, and demand forecasting. ...
Article
Full-text available
Looking at the perspective of investment theory, financing research and development (R&D) is the starting point in developing and accumulating needed resources in sustaining the survival of an organization. This work seeks out on the effect of Research and Development (R&D) funds on managing sales leads with the commercialization of completed research project in Enugu State as case study. A sample size of 355 staff was drawn from a population of 4680 using Freund and William formula. The study used the survey approach. The primary sources were personal interview and the administration of questionnaire to staff of University of Nigeria Nsukka, Enugu State University of Science and Technology, Enugu, Enugu State Government, 7UP Bottling company, and Coco-cola bottling companies, 9 th Mile corner. The reliability was tested using the Pearson Solid State Technology Volume: 65 Issue: 1 Publication Year: 2022 186 Archives Available @ www.solidstatetechnology.us correlation coefficient (r). It gave a reliability coefficient of 0.82 which was also good. The hypotheses were analyzed using Z-test statistic tool. Findings revealed that funds intended for research and development have positive effect on managing sales leads of the industry. This study concludes that funds intended for research and development and innovation activity of the personnel had positive effect on curbing industrial challenges in south east, Nigeria. The study therefore recommends that universities and higher educational centers should try to attract aptitudes to encourage scientific elites to form both a research team as well as development team; and that room should be created for other required circumstances to conduct applied research designs and to tackle social and economic problems.
Article
Full-text available
What is a Production System? Different disciplines, ranging from manufacturing to civil engineering and construction to project management and Lean, refer to the term, but few define it. One can only assume its meaning is generally taken to be self-evident from the constituent words. However, for purposes of Project Production Management, as with other scientific fields, a more precise definition, distinct from colloquial usage or usage in other subjects, is an essential part of a theoretical framework for making predictions about project execution performance and to identify how to control project execution. Starting from the etymology of terms and key requirements drawn from operations science [1 – 2], we provide a precise definition of Production System. We explain the contrast between our definition taken from operations science literature and terminology used elsewhere, such as by the Toyota Production System [3 – 4], Era 2 Project Scheduling [5] e.g., Critical Path Method and the Last Planner System© [6]. The most important distinction is that the precise definition of Production System provided here enables Project Production Management to be a quantitative theoretical framework, capable of modeling and predicting limits on project execution for a given Production System, and of identifying precisely where buffers can be allocated to optimize key parameters of a Production System: system throughput, system cycle time and system WIP.
Article
Full-text available
Project Management aims to address the myriad technical, human, organizational and managerial issues encountered during project execution [1]. Over the past two decades, different variants have emerged, including Lean Project Management, Agile Project Management, Scrum, Theory of Constraints and Extreme Project Management, to name a few. Lean Construction [2,36,54] utilizes concepts originally from Lean manufacturing and applies them specifically to the delivery of projects in the construction sector. Despite the proliferation of different “flavors” of project management, major capital project outcomes in construction and in other industries remain poor [3 – 5]. Industry practitioners face a confusing array of differing methodologies, each claiming to address poor project performance. The Institute’s mission is to explain how Project Production Management (PPM) addresses the gap between today’s poor project performance and what is possible, thereby differentiating PPM from other methodologies. Here, we focus on a comparison between PPM and Lean Construction. We trace the historical evolution of Lean Construction from its roots in Lean manufacturing, highlighting the operations science foundation underlying Lean and PPM. Lean Construction covers aspects of project governance, organization of project stakeholders and the work activities of the organization. In contrast, PPM focuses on the organization and control of project work activities. PPM’s deeper focus on the execution of work activities results in quantitative, predictive outcomes, validated by practice, that address poor project execution performance.
Article
Full-text available
The basic relationship, WIP = CT x TH known as Little’s Law has wide application in both production systems as well as projects [1]. However, when some parts/tasks are never completed because they are either scrapped (yield loss) or have become obsolete (as in a project), the application becomes a bit more complex. This study presents an analysis of these situations and concludes with a more general set of Little’s Law equations, as referenced in Factory Physics [2].
Article
Full-text available
Herein we describe a refinement of the well-known Cycle Time Formula, introducing two new components into the formula. One component describes the “wait-to-match” time of different routings in a production system converging at a single point, such as in an assembly operation. The second component accounts for “planned time buffers” – the time that parts or tasks are waiting, whether or not they can be worked on because of policies governing whether work can be done or not. Including these new components leads to a deeper understanding of the key contributors to cycle time, allowing us to make better decisions to optimize production system performance for considerations such as time-to-market or minimizing cash tied-up in Work in Process (WIP).
Article
Full-text available
The effective implementation of Project Production Management (PPM) requires a clear understanding of production processes within a given project production system – how they transform information and materials into outputs using capacity contributors (labor, equipment, space) and based on specific objectives, policies and requirements. This brings not only a necessary process perspective to production, but also forms the basis for production system optimization, control and ongoing performance improvement. However, experience tells us that those adopting PPM are often influenced by Era 1 and Era 2 thinking and associated frameworks, which gravitate towards functional and administration processes rather than actual production processes. The functional / administration perspective gives a myopic view of how work is executed compared with the production perspective, which emphasizes effective engineering, fabrication, assembly, delivery and installation. Therefore, the purpose of this paper is to provide a clear definition of production processes and their components, how best to represent them for design, technical analysis, control and improvement, and in so doing, enable differentiation from functional and administration processes used in traditional Project Management.
Conference Paper
Full-text available
The construction industry is an engine of economic and social development; however, it has grown the least in terms of productivity in comparison with other industries. Furthermore, it is characterized by inefficiencies that lead to time and cost overruns. This research seeks to optimize the execution time of a multipurpose building's concrete columns, beams, and slabs by applying the Virtual Design and Construction (VDC) methodology. The VDC framework was developed to establish the client's objectives, the project's objectives, production metrics, and controllable factors. As a result, 60 possible clashes among 2 disciplines (structure & MEP) were identified before construction and solved in a collaborative environment. In addition, the execution time of the structure's concrete beams, slabs, and columns was shortened by 37% compared to the baseline from the execution of the first work lot.