This paper highlights the limitations of the current applications of EVM method in forecasting project durations and introduces a novel concept, embedded in an integrated method, in lieu of those currently in use. The proposed method is designed to improve the accuracy of forecasting, and can be used as an add-on utility to existing software systems that perform forecasting using the earned value method. The proposed method is based on a new formulation for the schedule performance index, which takes into consideration the concurrent nature of project activities in schedules and the manner used to generate cumulative progress. The main concepts behind the developed method are the use of "critical project baseline" and the use the status of critical activities only. A numerical example is presented to highlight the limitations of current forecasting methods and demonstrate the use of the proposed method and to illustrate its improvement of forecasting accuracy over current methods.
Content may be subject to copyright.
THE USE OF EARNED VALUE IN FORCASTING PROJECT DURATIONS
Osama Moselhi*
Department of Building, Civil and Environmental Engineering, Concordia University, Montreal, Canada
* Corresponding author (moselhi@encs.concordia.ca)
ABSTRACT: This paper highlights the limitations of the current applications of EVM method in forecasting project durations
and introduces a novel concept, embedded in an integrated method, in lieu of those currently in use. The proposed method is
designed to improve the accuracy of forecasting, and can be used as an add-on utility to existing software systems that perform
forecasting using the earned value method. The proposed method is based on a new formulation for the schedule performance
index, which takes into consideration the concurrent nature of project activities in schedules and the manner used to generate
cumulative progress. The main concepts behind the developed method are the use of “critical project baseline” and the use the
status of critical activities only. A numerical example is presented to highlight the limitations of current forecasting methods and
demonstrate the use of the proposed method and to illustrate its improvement of forecasting accuracy over current methods.
Keywords: Earned Value, Forecasting, Project Duration, Critical Project Baseline
1. INTRODUCTION
Since the introduction of earned value management (EVM)
back in 1976 by the United States Department of Defense
[3], the use and applications of this method in management
of engineering, procurement and construction projects has
been the subject of numerous publications, most notably
those produced by the U.S.A. Department of Energy [4], and
National Aeronautics and Space Agency [10]. Despite this
sizable body of literature [1 to12], including that dedicated to
forecasting [2, 6, 7, 11 and 12], the current use of EVM in
forecasting project duration is inadequate and calls for further
improvements. While using the current practice and methods
in forecasting project cost at completion, as early as 15%
completion of project scope of work, was reported to be
reasonably accurate of EVM, this is not the case in
forecasting project durations. This paper highlights the
limitations of the current application of EVM method in
forecasting project durations and introduces a novel concepts
and an integrated method in lieu of those currently used. The
proposed method is designed to improve the accuracy of
forecasting, and can be used as an add-on utility to existing
software systems that perform forecasting using the earned
value method. The proposed procedure is based on a new
formulation for the schedule performance index, which takes
into consideration the concurrent nature of project activities
in schedules and the manner used to generate cumulative
progress. A numerical example is presented to demonstrate
the use of the proposed method and to illustrate its improved
forecasting accuracy over current methods.
2. LIMITATIONS OF EVM IN FORCASTING
EVM is designed to provide integrated time and cost
reporting on the status of projects at the end each reporting
period and in forecasting the project status at completion
using a set of cost and schedule variances (CV and SV) and
indices (CPI and SPI). This is carried out making use of 1)
the project baseline (see Figure 1) or budgeted cost of work
scheduled (BCWS), actual cost of work performed
(ACWP) and budgeted cost of work performed (BCWP)
and 2) the following equations:
S21-1
689
Figure 1: EVM Parameters
CV = ACWP – BCWP ……………………………... (1)
SV = BCWP - BCWS………………………….……... (2)
CPI = BCWP/ACWP………………..………………... (3)
SPI = BCWP/BCWS………………….…..…………... (4)
While CV and CPI (Equations 1 and 3) represent
reasonably the cost status of a project, SV and SPI do not
equally represent its schedule status. Consider, for example,
a scenario where at the end of a reporting period it was
found that a number of critical activates are experiencing
considerable delays while non critical activities are way
ahead of planned progress such that the resulting SPI is
equal to1.0. Clearly such SPI erroneously indicates that the
project is on target schedule without any delay while in
actuality the project is behind schedule. In other words,
Equation 4 can mask the actual schedule performance as
the inclusion of noncritical activities could distort and
misrepresent the status of the project schedule.
In addition, while the above variances and indices provide
time and cost status reporting at the end of each reporting
period, forecasting the project status at completion in
current methods are based either on:
a) assuming the performance attained so far will
continue in the future all the way to project
completion, or
b) assuming that the project performance will be as
planned in the future all the way to project
completion
Accordingly, the forecasted project duration (Df) is
calculated respectively, based on its planned original
duration (Do) by:
Df = Do/SPI .....................................................................(5)
or
Df = Do + SVt …………………….……………………(6)
Others may ignore the application of EVM in such
forecasting and resort to updating/revising the project
schedule, focusing primarily on the remaining work to
completion. This, however, is costly and time consuming in
comparison to the direct application of EVM.
.
3. PROPSED METHOD
The proposed method considers:
(1) Critical activities to generate C-BCWS (critical project
baseline) and C-BCWP (earned value of critical activities)
to generate more realistic schedule variance (R-SV) and
schedule performance index (R-SPI) as follows:
R-SV = C-BCWP – C-WCWS ……….……………….. (7)
R-SPI = C-BCWP/ C-BCWS ……..……………………(8)
The time variance in units of time (SVt) is calculated as
depicted diagrammatically in Figure 1.
(2) The impact of performance unrepresentative periods,
which experienced unexpected weather conditions or
accidents, by either revising the performance or by
dropping such periods when generating the cumulative
performance.
(3) Incremental adaptive learning by forecasting C-BCWP
at the end of each remaining periods and comparing it with
actual when reaching that time. As such, adjustment factors
(AFs) at the end of each reporting period are generated:
AF = R-SPI actual/ R-SPI forecasted ……………..… (9)
The AF is then used to calculate adjusted R-SPI (A-R-SPI)
as:
A-R-SPI = AF * R-SPI .............................................. (10)
S21-1
690
The forecasted project duration (Df) is then calculated as:
Df = Do / (A-R-SPI) ..................................................... (11)
or
Df = Do + SVt ……………...……………………. .. (12)
or
Df = De + SVt + (Do- De) / (A-R-SPI)......................... (13)
In which De is the elapsed duration
4. NUMERICAL EXAMPLE
The PDM network of this project example is shown in
Figure 1. The project has duration of 8 month and the latest
progress period is at half way of its planned original
duration. This example is used here to highlight the
limitations of current methods, to demonstrate the use of
the proposed method and to illustrate its improvement in
the accuracy of forecasting project duration at completion.
The data used in the analysis is included in Table 1.
Fig.1 PDM Diagram
Table 1 Activities durations and direct cost
Activity
Duration
ES
EF
LS
LF
TF
To ta l
Direct
Cos
t
Direct
Cost /
Month
A 1 0 1 0 1 0 $1,000 $1,000
B 3 0 3 2 5 2 $12,000 $4,000
C 1 1 2 4 5 3 $4,000 $4,000
D 6 1 7 1 7 0 $6,000 $1,000
E 2 3 5 5 7 2 $16,000 $8,000
F 1 7 8 7 8 0 $1,000 $1,000
The project baseline under three different scenarios was
generated as shown in Table 2 and in Figure 2. The
cumulative progress at the end of month 4 was calculated
as shown in Table 3.
Table 2: Project baseline (BCWS)
Early start Late start Critical Activities
Time (month)
Period
BCWS (ES)*
Period
BCWS (LS)*
Period
BCWS (Cri.)*
1 5 5 1 1 1 1
2 11 16 3 4 3 4
3 7 23 7 11 3 7
4 11 34 7 18 3 1
5 11 45 11 29 3 13
6 3 48 11 4 3 16
7 3 51 11 51 3 19
8 1 52 1 52 1 20
*Cost is in thousands of dollars
Fig. 2 Project baseline (BCWS)
The earned value analyses were performed using current
methods, i.e. Equations 1 to 6, and the proposed method as
described in Section 3 above. Three scenarios were
considered; 1) current EVM methods based on early start
S21-1
691
schedule, 2) as in 1) but based on late start schedule and 3)
using only critical activities. The analysis was carried to
determine project schedule status at the end of month 4 and
to forecast the project duration at completion as follows:
Scenario-1: Based on early start
Schedule Variance (SV) = BCWP BCWS= -$6,000.0
Schedule Performance Index (SPI) = BCWP / BCWS =
0.82352
Original Duration Do = 8 month
Forecasted Project Duration-I = Do/SPI = 9.7142 month
Schedule Variance (SVt) = 0.55 month
Forecasted Project Duration-II = Do + SVt = 8.55 month
Senario-2: Based on late start
Schedule Variance (SV) = BCWP BCWS= $10,000.0
Schedule Performance Index (SPI) = BCWP / BCWS =
1.5556
Original Duration Do = 8 month
Forecasted Project Duration-I = Do / SPI = 5.1428month
Schedule Variance (SVt) = -0.9 month
Forecasted Project Duration-II = Do + SVt = 7.1 month
Table 3 Earned value analysis
Activity
% Complete
BCWS(ES)*
BCWS(LS)*
BCWS (Cri.)*
BCWP*
BCWP (cri.)*
ACWP*
A** 100% 1 1 1 1 1 1.1
B 100% 1.2 8 12 11
C 100% 4 0 4 3.5
D** 30% 9 9 9 5.4 5.4 6.5
E 35% 8 0 5.6 8
F** 0% 0 0 0 0 0 0
Total 34 18 10 28 6.4 30.1
*Cost in thousands of dollars, **Critical activities
Fig.3 Earned value analysis at the end of month 4
Scenario-3: Based on critical activities only
The proposed method is applied in this scenario (i.e.
Equations 7 to 13). For simplicity it is assumed that no
unusual incidents have impacted the performance in the 4
periods and therefore AF is set equals to 1.0.
R-SV = C-BCWP C-BCWS= -$3,600.0
R-SPI = C-BCWP / C-BCWS = 0.64
A-R-SPI = 0.64 x 1.0 = 0.64
Original Duration Do = 8 month
Forecasted Project Duration-I = Do / (A-R-SPI) = 12.5
month
Schedule Variance (SVt) = 1.25 month
Forecasted Project Duration-II = Do + SVt = 9.25 month
Elapsed Duration De = 4 month
Forecasted Project Duration-III = De + SVt + (Do- De)/
(A-R-SPI) = 11.50 month
5. DISCUSSION OF RESULTS
The results obtained in the numerical example exhibit
considerable differences (see Table 4) and clearly
demonstrate the limitations of current methods used in the
application of EVM for reporting the status of project
schedules and for forecasting their duration at completion.
S21-1
692
Table 4 Forecasted project durations (month)
Duration
Scenario 1
Scenario 2
Average 1&2
Scenario 3
I 9.71 5.14 7.42 12.50
II 8.55 7.10 7.82 9.25
III --- --- 11.50
Clearly the differences between scenarios 1 and 2 may not
be encountered in practice as the schedule will be that
approved by the owner and/or its agent and it commonly
leans toward early start schedule. It is included in this
example to demonstrate its impact on earned value analysis.
It is important here to compare scenario 1, or the average
of scenarios 1 and 2, to scenario 3. We see in this example
how current methods (used in scenarios 1 and 2)
underestimate the forecasted project duration at completion.
6. SUMMARY AND CONCLUDING REMARKS
The use the two the widely used two methods, described
above in Section 2, for forecasting may produce to
inaccurate results, which leads to unrealistic forecasting of
the project status at completion. This is of considerable
importance, particularly in forecasting project durations. In
this case it is recommended to use only critical activities in
generating project baseline and subsequently in generating
schedule variances and indices as outlined in the proposed
method. The results obtained from the numerical example
demonstrate how erroneous forecasting project duration
can be when applying the current EVM methods.
ACKNOWLEDGMENTS
The author would like to thanks Mr. Ali Montaser for his
assistance in generating the results of the numerical
example and the preparation of its related tables and
figures.
REFERENCES
[1] Alshibani, A., “A computerized cost and schedule
control system for construction projects”, Master’s thesis,
Civil, Building, and Environmental Engineering,
Concordia University, Montreal, Canada, 1999.
[2] Christensen, D.S, Antolini, R.C. and Mckinney, J.W.,
“A review of EAC Research”, Journal of Cost Analysis and
Management, Spring Issue, pp. 41-62, 1995.
[3] Department of Defense, 1967. Performance
Measurement for Selected Acquisitions, DODI 7000.2.
[4] Department of Energy, 1980. Cost/Schedule Control
Systems Criteria for Contract Performance Measurement:
Implementation Guide, DOE/CR-0015, Office of the
Controller.
[5] Fleming, Q. W. and Koppelman, J.M., Earned Value
Project Management, 3rd Ed., Newton Square, Pa., USA:
Project Management Institute, 2005.
[6] Hassanein A., and Moselhi O., “Tracking and Control
of Linear Infrastructure Projects”, 5th Construction
Specialty Conference of the Canadian Society for Civil
Engineering, Moncton, Nouveau-Brunswick, Canada, 2003.
[7] Ji, Li. “Web-based integrated project control”, PhD’s
thesis, Civil, Building, and Environmental Engineering,
Concordia University, Montreal, Canada, 2004.
[8] Moselhi, O.,. Applied Earned Value for Project Control,
proc. of the CIB W-65 7th International Symposium on
Organization and Management of Construction, Port of Spain,
Trinidad. 1993
[9] Moselhi, O., Ji,li, and Alkass, Sabah,“Web-based
integrated project control System.” Construction
Management and Economics. Vol. 1, pp. 35-46, 2004.
[10] NASA, “Integrated Baseline Review (IBR) Handbook,
SP-2010-3406.
[11] Paul Teicholz, “Forecasting final cost and budget of
construction projects”, Journal of Computing in Civil
Engineering, Vol. 7, No. 4, October, 1993.
[12] Xiao hui, Xiao, “Trending and forecasting in
construction operations”, Master’s thesis, Civil, Building,
and Environmental Engineering, Concordia University,
Montreal, Canada. 2009.
S21-1
693
... Concurrently, this issue has negative impact on forecasting the status of project at completion too (Forecast project Duration= (Planned original Duration/SPI)). Moselhi (2011) developed a model which is based on the Critical C-BCWS and C-BCWP and their Adjustment Factors (AF). It was recommended "to use only critical activities in generating project baseline and subsequently in generating Schedule variances and indices in order to forecast project duration" (Moselhi, 2011). ...
... Moselhi (2011) developed a model which is based on the Critical C-BCWS and C-BCWP and their Adjustment Factors (AF). It was recommended "to use only critical activities in generating project baseline and subsequently in generating Schedule variances and indices in order to forecast project duration" (Moselhi, 2011). ...
Conference Paper
The Earned Value Management (EVM) is the most commonly used system in construction projects allover the world to integrate both time and cost controls of a project. However, numerous researchers have identified gaps and limitations to using this method. The most agreed-upon limitation in using the EVM, is that it does not incorporate the quality aspect of a project, although it is one of the main drivers of success in any project. As a result, this study was conducted as a contribution to efforts in this field with the aim of identifying a proper way to integrate quality, time and cost using the EVM. A framework was developed to assess the quality of a project by the means of proposed equations and formulae that hopefully will aid project managers and responsible parties in a project in having a broader vision of the project's performance in terms of time, cost and quality. Furthermore, a case study from an actual construction project was analysed to verify and validate the framework, and the results were in favor of using the framework rather than the conventional EVM calculations.
Conference Paper
This paper presents a new method for forecasting time and cost of construction projects at completion and/or at any intermediate time horizon. The method is designed to overcome limitations of current applications of earned value method in forecasting project cost and durations. The method adopts recently introduced extensions to EVM and the project ratios technique for progress reporting. It introduces modifications and developments that allow more accurate and practical results. Unlike the current applications of EVM method, the proposed method uses simulation to generate stochastic S-curves based on past performance achieved by contractors. The method enables the user to assess the uncertainty associated with forecasted project cost and duration at completion so that appropriate corrective actions can be taken, when needed. A numerical example is presented to demonstrate the use of the proposed method and to illustrate its improved forecasting accuracy over current methods. The results obtained by the developed method demonstrate the effectiveness of (1) using project ratios technique in forecasting project time and cost comparing to that obtained by traditional EVM method; (2) measuring the status of critical activities only, is particularly useful in forecasting project durations; and (3) accounting for uncertainties involved in the forecasting process provides flexibility in modelling forecasted project time and cost.
Article
Full-text available
This paper presents a study conducted in collaboration with large Canadian engineering, procurement and construction management (EPCM) firm to identify areas of improvement in the current process of progress reporting and forecasting project status at different targeted future dates. The study focused mainly on trending and time/Cost control of engineering, procurement and construction (EPC) projects. It encompassed a field study of the practices of the industrial collaborator, study of related materials from the literature, and development of standalone computer applications, which serves as add-on utilities to the propriety project management software of the industrial partner. The paper presents a model for improving trending and forecasting of time and cost in construction operations. The proposed model has 3 main functions: 1) trending of estimate accuracy, 2) integrated control and forecasting, and 3) progress visualization. @Risk 5.0 for excel, Windows SharePoint Server and visual basic for application (VBA) are used to develop 3 add-on tools to implement the developments made in the above 3 functions. Numerical examples based on a set of data from a pilot training project, developed by the industrial partner, are presented to illustrate the essential features of the developed model.
Article
Full-text available
This paper describes a computational approach to calculating the final cost and budget of a construction project, which is based on the data normally developed by a cost system during the life of the project. While most cost systems are able to collect total budget and to-date cost, budget, and quantity data, there is often less capability to use this data to forecast the final cost of a project. In many cases, the cost forecast for unstarted work does not reflect the overruns or underruns that are recorded early in the life of a project. This paper presents an algorithmic approach that has been tested using the data from 121 completed construction projects, which calculates reasonably good cost and budget forecasts over a wide range of project types and changed conditions. The proposed method is compared to two other methods and is found to be superior in accuracy, timing, and stability. The forecasting method, sliding moving average, is general in its approach and may be useful for other situations in which predictions of limited duration time-series data are desired.
Conference Paper
Factors to be considered in the implementation of an earned value project management are described. First, management and owner must commit to using earned value metrics to monitor the cost and schedule performance of their projects. Second, some method must be used to define all project work in order to both understand the requirements and to set the project's outer limits. Third, all work defined within the WBS must be planned and then logically sequenced into a specific time frame for performance. Fourth, resources will need to be estimated and budgeted for all defined scope. Fifth, the summation of all authorized CAPS will need to form a project performance baseline. The last necessary step is for the project to monitor performance against the unauthorized baseline for the duration of the project.
Article
This paper presents a system that supports project time and cost control in an integrated manner. The system utilizes object-oriented modelling to represent the process of project delivery. A set of control objects is designed to map the process of project control. Eighteen key indicators are considered to represent the resources utilized in each control object and serve as sensors to highlight problematic areas associated with unfavourable performance. A Three-Tier Client/Sever computer system is designed to implement the developed system. Daily, weekly, monthly and/or yearly, period-by-period, and cumulative to-date project performance reports are generated to provide the status at project, control object and resource levels. An example drawn from the literature is analysed to allow for comparison with the results obtained using the proposed methodology. The example also serves the purpose of demonstrating the use of the proposed system and illustrating its essential features.
A review of EAC Research
  • D S Christensen
  • R C Antolini
  • J W Mckinney
Christensen, D.S, Antolini, R.C. and Mckinney, J.W., "A review of EAC Research", Journal of Cost Analysis and Management, Spring Issue, pp. 41-62, 1995.
Tracking and Control of Linear Infrastructure Projects " , 5 th Construction Specialty Conference of the Canadian Society for Civil Engineering
  • A Hassanein
  • O Moselhi
Hassanein A., and Moselhi O., " Tracking and Control of Linear Infrastructure Projects ", 5 th Construction Specialty Conference of the Canadian Society for Civil Engineering, Moncton, Nouveau-Brunswick, Canada, 2003.
Applied Earned Value for Project Control, proc. of the CIB W-65 7 th International Symposium on Organization and Management of Construction
  • O Moselhi
Moselhi, O.,. Applied Earned Value for Project Control, proc. of the CIB W-65 7 th International Symposium on Organization and Management of Construction, Port of Spain, Trinidad. 1993
A computerized cost and schedule control system for construction projects
  • A Alshibani
Alshibani, A., "A computerized cost and schedule control system for construction projects", Master's thesis, Civil, Building, and Environmental Engineering, Concordia University, Montreal, Canada, 1999.
Tracking and Control of Linear Infrastructure Projects
  • A Hassanein
Hassanein A., and Moselhi O., "Tracking and Control of Linear Infrastructure Projects", 5 th Construction Specialty Conference of the Canadian Society for Civil Engineering, Moncton, Nouveau-Brunswick, Canada, 2003.