Influence of In-sourcing and Outsourcing of Consultants on Construction Project Performance in Nigeria

Authors:

Abstract

Research studies have discovered that outsourcing has several benefits and the practice is fast replacing in-sourcing especially with regard to construction consultants. In the attempt to examine the benefits of the two approaches on project outcome, this study investigates the influence of the use of in-sourced and outsourced consultants on project performance in Nigeria. The objectives are to determine the use of in-sourcing and outsourcing for selected consultants, compare the use of the two approaches in project delivery and their influence on project performance and compare the performance of projects in which in-sourced and outsourced selected consultants were engaged. To achieve these objectives, a questionnaire design approach was adopted. A field survey involving a sample of 164 projects were selected by stratified random sampling. Data were collected using structured questionnaires and analysed using percentage, mean, Spearman and t-tests. The results of the study reveal that clients engage both in-sourced and outsourced consultants in project development and that the practice has significant influence on project performance. It also discovered that the use of the two approaches has differing benefits on project delivery time and cost. The study concludes that in-sourcing and outsourcing are common practices in project development and that clients are facing a challenge in deciding which approach to adopt. The study also discovers that both approaches has benefits associated with project outcome and suggests that clients should consider these benefits in their decision to in-source or outsource consultants.
Influence of In-sourcing and Outsourcing of
Consultants on Construction Project Performance
in Nigeria
Godwin Iroroakpo Idoro, (University of Lagos, Nigeria)
Abstract
Research studies have discovered that outsourcing has several benefits and the practice is fast
replacing in-sourcing especially with regard to construction consultants. In the attempt to
examine the benefits of the two approaches on project outcome, this study investigates the
influence of the use of in-sourced and outsourced consultants on project performance in
Nigeria. The objectives are to determine the use of in-sourcing and outsourcing for selected
consultants, compare the use of the two approaches in project delivery and their influence on
project performance and compare the performance of projects in which in-sourced and
outsourced selected consultants were engaged. To achieve these objectives, a questionnaire
design approach was adopted. A field survey involving a sample of 164 projects were selected
by stratified random sampling. Data were collected using structured questionnaires and
analysed using percentage, mean, Spearman and t-tests. The results of the study reveal that
clients engage both in-sourced and outsourced consultants in project development and that the
practice has significant influence on project performance. It also discovered that the use of the
two approaches has differing benefits on project delivery time and cost. The study concludes
that in-sourcing and outsourcing are common practices in project development and that clients
are facing a challenge in deciding which approach to adopt. The study also discovers that both
approaches has benefits associated with project outcome and suggests that clients should
consider these benefits in their decision to in-source or outsource consultants.
Keywords: Construction projects, In-sourced consultants, Nigeria, Outsourced consultants and Project
performance
Introduction
The importance of consultants in construction project delivery cannot be over-emphasised.
Consultants as Havemann (2007) put it are accountable for the technical risks in a conventional
project. They are responsible for developing the requirements of project clients, setting targets,
deadlines and establishing standards for meeting these requirements, preparing project
documents that describe the targets, deadlines and standards set and sometimes monitoring
the activities of contractors that execute a project to ensure that the targets, deadlines and
standards are achieved. It suffices to say that a project cannot be successfully executed without
the services of consultants.
These consultants are engaged from two sources namely: in-house or external. In-house
consultants can otherwise be described as internal service providers or in-sourced consultants.
These refer to professionals on permanent employment of the client who are engaged to
perform the services of consultants in the procurement of a project. Outsourced consultants can
otherwise be described as external or outsourced service providers. These refer to
professionals who operate consultancy outfits that are engaged by a client to provide
specialised services in the course of procuring a project. Traditionally, organisations used to
engage professionals on permanent employment to perform the services of consultants.
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
46
However, in the past decade, outsourcing has become a prevalent practice in most countries.
Sattineni and University (2008) opined that in developing countries, white collar jobs that were
hitherto considered to be stable are now being outsourced.
The main concern about consultants that prompts this study is that most of the major clients in
particular the public and organised private sector clients have departments where professionals
are employed. These professionals are often responsible for most pre-design services and they
are fully involved in both design and construction activities. In organisations where project
delivery is fully internalised, in-sourced consultants perform all the activities relating to design
and construction of a project. Idoro (2006) described the in-house project delivery process as
direct labour approach. In other projects, clients use in-sourced consultants for some services
while engaging external consultants for others. In projects where outsourced consultants are
involved, client’s professional staff serve as intermediaries between the external consultants
and the client who often seek their advice on every matter relating to a project. Boes and Doree
(2009) opined that the preparatory activities in traditional contract are either carried out in-house
or outsourced to consulting engineering firms and that outsourcing to consulting engineering
firms requires in-house control measures. They maintained that reducing staff by outsourcing
tasks to engineering consultants creates new issues of quality control, risks and staffing. The
main questions raised by this practice are: what is the preference of construction clients on in-
house and outsourced consultants in project delivery? What is the effect of in-house and
outsourced consultants on project performance? The problem of the study therefore is to
determine the influence of in-sourced and outsourced consultants on project performance. The
objectives are to compare the extent of use of in-sourced and outsourced project consultants in
project delivery and the effect of their use on project performance. The achievement of these
objectives will assist stakeholders in the industry in their decision on whether to engage in-
sourced or outsourced consultants in project development.
Hypotheses of the Study
In the attempt to achieve the objectives of the study, three hypotheses were postulated. The first
hypothesis states that the extent of use of in-sourced and outsourced consultants in project
development is not significantly different. This hypothesis is tested to establish the preference of
clients on the two types of consultants. The second hypothesis states that the extent of use of
in-sourced and outsourced consultants has no significant relationship with project performance.
The test of this hypothesis is expected to assist clients to know the influence of the use of in-
sourced and outsourced consultants on project performance. The third hypothesis states that
the outcome of projects in which in-sourced consultants were engaged is not significantly
different from the outcome of projects in which outsourced consultants were engaged. The
results of the hypothesis are expected to assist clients to know the effect of engaging the two
types of consultants and which consultants to source in-house or outside
Conceptual Framework of the Study
Three categories of variables namely: project consultant, consultant source and project
performance were used in the study. Six project consultants namely: project manager, architect,
quantity surveyor, structural, electrical and mechanical engineers were used. Consultant source
was classified into in-source and outsource while twelve variables namely: respondents’
assessment of project cost, duration, quality, variations, fluctuation, risks, conflicts between
client and contractors, conflicts between client and consultants, conflicts between consultants
and contractors, compliance with contract obligations, time-overrun and cost-overrun were used
as parameters of project performance. The last two parameters of project performance were
used as parameters of project outcome because the effects of the other ten parameters are
expected to manifest in them. Project success which is reflected in project performance is the
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
47
purpose of engaging consultants. Hence, the relationship between the two types of consultants
and project performance and the difference in the outcome of projects in which in-sourced and
outsourced consultants were engaged were used to determine the benefits in project
performance of the two types of consultants. This relationship is expressed in Fig.1.
Figure 1 Framework for evaluating the relationship
between the use of in-sourced and outsourced
consultants and project performance
Previous Studies
The construction industry is one of the most important economic sectors in Nigeria. The industry
is known to account for a major proportion of the Gross Domestic Product (GDP) of Nigeria
(Federal Government of Nigeria, 1986; Idoro, 2004). The industry is also a major contributor to
employment generation by providing employment to millions of people in diverse professions
and skills as well as serving as a vocational training ground. There are several parties that are
involved in the delivery of construction projects. Idoro (2009a) stated that project teams consist
of many parties who have several responsibilities to perform in order to ensure the success of a
project. He identified the notable parties as clients, consultants, contractors, suppliers and
manufacturers. Clients in the Nigerian construction industry are classified into two categories
namely: public clients made up of the federal, state and local governments and their respective
parastatals and private clients made up of individuals and corporate organisations. Idoro and
Okun (2011) opined that in Nigeria, government is the main promoter of construction projects
and that the private sector depends to a considerable on government expenditure. Nigerian
contractors are often categorised as either indigenous that is construction firms that are fully
owned and managed by Nigerians or expatriates that is those firms that are jointly owned by
Nigerians and foreigners but solely managed by expatriates (Idoro, 2009b). Olateju (1991)
reported that indigenous contractors were responsible for only 7% of the total value of contracts
awarded from 1974 to 1994 while their expatriate counterparts were responsible for the
remaining 93%. In a study that investigated the reasons for the poor participation of indigenous
contractors in contracts’ execution, Idoro (2010) discovered that Nigerian clients perceive the
quality performance of expatriate contractors to be better than that of indigenous contractors
and confirmed that clients indeed give preference to expatriate contractors in the award of
contracts.
There are many professionals that are involved in the design and construction of projects in
Nigeria that are regarded as consultants. In a study of quantity surveying practice in Nigeria,
Odusami (1999) stated that in Nigeria as in Britain, the quantity surveyor is one of the key
professionals involved in the design and execution of construction projects. Others include
architects and structural, electrical and mechanical engineers. These consultants can either be
Consultant
source
1. In-source
2. Outsource
Project performance
Consultants’ assessment of
1. Project time
2. Project cost
3. Project quality
4. Variations
5. Fluctuation
6. Project risks
7. Conflict between client & contractors
8. Conflict between client & consultants
9. Conflict between consultants & contractors
10. Compliance with contract obligations
Project outcome
11. Time-overrun
12. Cost-overrun
Project consultant
1. Project manager
2. Architect
3. Structural engineer
4. Quantity surveyor
5. Electrical engineer
6. Mechanical
engineer
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
48
outsourced through direct employment by client, nomination by architect/project manager,
nomination by other consultants or competitive bidding from professionals operating
consultancy outfits outside the client organisation or in-sourced from professionals that are
within the client organisation (Odusami, 1999).
In the attempt to examine the application of outsourcing in different areas of organisations’
activities, researchers describe it in various ways: the significant contribution by external
vendors in the physical and human resources associated with the entire or specific components
of the IT infrastructure in the user organisation (Loh and Venkatraman, 1992); the extent of
components and finished products supplied to a firm by independent suppliers (Kotabe, 1992);
the reliance on external sources for the manufacturing of components and other value-adding
activities (Lei and Hitt,1995). Grover et al. (1996) described outsourcing as the practice of
turning over part or all of an organisation’s internal functions to external service providers. Gilley
and Rasheed (2000) felt that the term outsourcing is so wide that it covers virtually any good or
service that an organisation procures from outside firms. Referring to another way outsourcing
is practised in many organisations, Domberger (1998) believed that outsourcing is synonymous
with contracting and therefore described it as the process of searching for and appointing
contractors for the provision of goods and services and the execution of the contractual relations
needed to support such activities. In another view, Ender and Mooney (1994) described
outsourcing as a form of privatisation that refers to an organisation’s (University) decision to
contract with an external organisation to provide a traditional organisation function or service to
the organisation.
All these descriptions (supply, externalisation, contracting and privatisation) show that
outsourcing is practised in various ways in different organisations. While all of them can be said
to convey the same meaning or practice, two of them mentioned another point to ponder about
in outsourcing. Grover et al., (1996) called it ‘internal functions’ while Ender and Mooney (1994)
regarded it as ‘traditional functions’. The point in these definitions is that the products or
services to be outsourced should be the ones that the organisation is or can currently produce
or render. This view is supported by Gilley and Rasheed (2000) who argued that outsourcing
may arise in two ways namely: 1) substitution of external purchases for internal activities that is
discontinuation of goods or services and an initiation of procurement from outside suppliers and
2) abstention that is purchases of goods or services from outside organisations even when
those goods or services have not been produced in-house in the past. The duo regarded
outsourcing as a decision to reject internalisation that is in-house production of goods or
services outsourced and opined that outsourcing occurs when the internalisation of the good or
service outsourced is within the acquiring firm’s managerial and/or financial capabilities. They
suggested that organisations that have no choice but to acquire a particular good or service
from external source because of lack of capital or expertise are not outsourcing because the
internalisation of the activity in question is not an option. This view tends to indicate that
outsourcing applies when the option of in-sourcing is available and that organisations are
always faced with the decision on whether to adopt in-sourcing or outsourcing for their products
or services.
This problem which clients have to confront when embarking on project development is the
thrust of this study. Kanji and Wong (1998) maintained that the construction industry comprised
of a multitude of occupations, professions and organisations that are involved in different
phases of a construction project and consultants in collaboration with clients, contractors and
sub-contractors all have a role to play in delivering a quality project. Renier and Volker (2009)
maintained that every project is usually assigned a new team, precisely from a client’s own
network in which context social aspects play an important part. If a firm cannot draw from its
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
49
own organisation structural engineers, building consultants, climate advisors, other external
professionals have to be involved in the process as soon as possible. Meiling and Johnson
(2009) opined that during design, manufacturing and erection, the building is thoroughly defined,
manufactured and erected. Most of the activities remain in-house while some are performed by
external consultants. The duo maintained further that in industrialised buildings in Sweden,
drafting of the building envelope is handled by companies themselves while HVAC drafting,
structural design, electrical drafting and life-cycle costing are done by external consultants.
Although Sattineni and University (2008) regarded pre-construction, conception, design and
tendering services as areas that suite outsourcing, however if contracting and privatisation are
forms of outsourcing, it all means that construction activities are equally being outsourced in
project delivery. The point in the above studies is that outsourcing whether full or partial is
inevitable in the development of most construction projects.
The question that arises from the above review is ‘if outsourcing is a feature of construction
project development, what are the benefits derived from it? Research studies have discovered
that organisations derive numerous benefits when they engage external service providers. It
was discovered that by outsourcing, firms often achieve cost advantages relative to vertically
integrated firms (Quinn 1992; Bettis, et al., 1992; D’Aveni and Ravenscraft, 1994; Lei and Hitt,
1995); manufacturing costs decline and investment in plant and equipment can be reduced
(Bettis et al., 1992); reduced fixed costs that leads to a lower break-even point (Gilley and
Rasheed, 2000); firms have opportunities for flexibility in technology (Harrigan, 1985);
economies of scale by increasing net value and reducing costs, process expertise, access to
capital and expensive technology, greater capacity for flexibility (Carlson, 1989; Harrison, 1994);
enhanced competitiveness (Gilley and Rasheed, 2000); quick response to environmental
changes (Dess et al., 1995); increased management attention and resource allocation to those
tasks that an organisation does best and reliance on management teams in other organisations
to oversee tasks in which the outsourcing firm is at relative advantage (Quinn et al., 1990);
emerging technology without significant investment in the technology (Gilley and Rasheed,
2000); focus on core competencies (Kotabe and Murray, 1990; Quinn, 1992; Dess et al., 1995;
Sang, 2010). While previous studies have covered many benefits in outsourcing, the aspect of
project performance has been virtually neglected. The benefits that a client will derive in terms
of the outcome of projects which is the focus of this study are not in the studies.
Despite these numerous benefits, several problems have been observed on the use of external
consultants. Outsourcing can lead to loss of overall market performance (Bettis et al., 1992;
Kotabe, 1992) or less investment in research and development which may lead to decline in
innovation (Teece, 1987). In a project that involved a change of client, Michell et al., (2007)
discovered problems concerning cooperation between consultants and contractors. As a
solution to the problem of inaccurate proposals submitted by consultants, Tembo and Rwelamila
(2007) suggested that organisations should formulate an evaluation process for the assessment
of project proposals from consultants in a manner that will reflect true costs and schedules.
These problems show that the practice of outsourcing products or services by an organisation is
not without losses.
Research Methods
A questionnaire survey approach was adopted for the study and a field survey involving 164
clients was conducted. A list of 211 organisations made up of 56 government and 155
organised private establishments was prepared through a preliminary survey conducted in the
first quarter of 2010 because a reliable list or statistics of organisations involved in project
development could not be obtained. These organisations were used as the population frame for
the study. The study sample was selected from this population by stratified random sampling. In
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
50
the sampling, the population was classified into public and private organisations thereafter; the
respondents were selected from each sector randomly. One project preferably the one with the
highest contract sum executed by each of the sampled organisations was selected to ensure
that the consultants selected for the study were required in the project.
Data were collected on the characteristics of the projects sampled, the sources of six
consultants discovered to be common to all the projects sampled, respondents’ assessment of
project duration, cost, quality, extent of risks, variations, fluctuation, compliance with contract
obligations and conflicts and disagreement between client and contractors, client and
consultants and contractors and consultants of the projects using five ranks namely: poor, low,
moderate, high and very high. The ranks were assigned scores of 1, 2, 3, 4 and 5 respectively.
Data on the initial and actual duration and cost of the projects were also collected. The data
were collected using structured questionnaires. The instrument was administered to the
respondents by hand through personal visits paid to the organisations sampled in mid 2010 and
completed questionnaires were also collected through the same approach. The extent of use of
the two categories of consultants investigated was defined as the percentage of the six selected
consultants engaged in-house or outsourced to procure the projects sampled. Time-overrun
was defined as the percentage of the difference between actual and initial contract periods
divided by initial contract period while cost-overrun was defined as the percentage of the
difference between actual and initial contract sums divided by initial contract sum. The data
were analysed using percentage, mean, t-test, Chi-square and Spearman correlation tests.
Results of Data Analysis
The results of the analysis of the data collected for the study are presented as follows.
Characteristics of Projects used for the Study
The characteristics of the projects used for the study were investigated for the purpose of
understanding the projects which the results of the study apply to. Five project characteristics
and their sub-types stated Table 1 were investigated. The percentages of each sub-type of
project characteristics were analyzed. The results are presented in Table 1.
Table 1 shows that the projects sampled were procured by four notable methods namely: direct
labour, traditional contract, design-build and labour-only however the percentage of projects
procured by direct labour method was the highest. On the owners of the projects used for the
study, Table 1 shows that both government and private sector projects procured were covered
in the sample but private sector projects constituted the majority. On the type of construction,
Table 1 shows that both new construction and renovation/maintenance works were sampled but
the majority of the projects were new projects. Table 1 shows that projects were procured by the
construction management method in which the construction manager is the coordinator, the
project management system in which the project manager was the project leader and the
traditional management method in which the architect was the project leader were sampled.
The analysis of the rise of the buildings sampled shows that low-rise (1-3 floors), medium-rise
(4-7 floors) and high-rise (above 7 floors) buildings were covered but the majority of the projects
were low-rise buildings. The analysis of the value of the projects shows that the five value
intervals selected were covered in the projects sampled which indicates that the projects
sampled were both small and large. On the duration of the projects sampled, Table 1 shows that
the percentage of long duration (above 52 weeks) projects is the highest while the percentage
of medium duration (26-52 weeks) projects is the lowest. On the contractor type that executed
the projects sampled, Table 1 shows that projects executed by both indigenous and expatriate
contractors in Nigeria were covered however, majority were executed by indigenous
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
51
contractors. The analysis of the use of the buildings sampled shows that the projects covered by
the study have several uses.
Characteristic
Sub-type
N
Characteristic
Sub-type
N
%
Procurement
method
Design-Bid-Build
Direct labour
Design-build
Labour-only
Total
42
64
42
16
164
Project value
N 1- 25 million
N26-50 million
N51-75 million
N76-100million
Above N100 million
Total
32
22
26
8
28
116
27.6
19.0
22.4
6.9
24.1
100
Client type
Public
Private
Total
28
136
164
Project
duration
1-26 weeks
27-52 weeks
Above 52 weeks
Total
48
40
74
162
29.6
24.7
45.7
100
Construction
type
New construction
Renovation
Total
122
42
164
Contractor
type
Expatriate
Indigenous
Total
42
122
164
25.6
74.6
100
Management
method
Traditional
Project mgt
Construction mgt
Total
42
58
64
164
Project use
Residential
Commercial
Industrial
Social
Total
88
62
2
12
164
53.7
37.8
1.2
7.3
100
Building rise
1-3 floors
4-7 floors
Above 7 floors
Total
96
6
22
124
Table 1 Descriptive result of characteristics of projects used for the study
N=Number of respondents. N=Naira (Nigerian official currency; 1US$=158N), mgt=management
Priority Accorded the Use of In-sourced and Outsourced Consultants
To investigate the priority accorded the use of in-sourced and out-sourced consultants in project
development, the percentages of the consultants in-sourced and outsourced were analysed and
ranked separately. The results are presented in Table 2.
Consultant
Total
N
In-source
N % Rank
Outsource
N % Rank
Electrical engineer
Mechanical engineer
Architect
Structural engineer
Quantity surveyor
Project manager
94
90
98
112
108
102
43 45.7 6
46 51.1 5
55 56.1 4
63 56.3 3
68 63.0 2
77 75.5 1
51 54.3 1
44 48.9 2
43 43.9 3
49 43.7 4
40 37.0 5
25 24.5 6
Table 2 Ranks of the sources of selected project consultants
N=Number of respondents
Table 2 shows that the percentage of in-sourced project managers (75.5) ranked first while that
of quantity surveyors (63) ranked second. The percentage of in-sourced structural engineers
(56.3) ranked third while those of architects (56.1), mechanical engineers (51.1) and electrical
engineers (45.7) ranked fourth, fifth and sixth respectively.
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
52
Test of Difference between the Use of In-sourced and Outsourced Consultants
To test whether or not there is difference in the preference of the respondents for in-sourced
and outsourced consultants, the first hypothesis was postulated. The hypothesis states that the
extents of use of in-sourced and outsourced consultants in project development are not
significantly different. The hypothesis was tested using the t-test with p≤0.05. The rule for the
acceptance or rejection of the hypothesis is that when p-value>0.05, the hypothesis is accepted
but when p-value≤0.05, the hypothesis is rejected. The results are presented in Table 3.
Variables compared
Mean
t-value
Df
p-value
Decision
Diff
% of in-sourced consultants
% of outsourced consultants
50.27
49.73
0.158
158
0.874
Accept
NS
Table 3 Results of t-test for difference between the use of in and out sourced consultants
N=Number of respondents, Df=Degrees of freedom. Diff=Difference, NS=Not significant
Table 4 shows that the p-value (0.874) for the test of difference in the extent of use of in-
sourced and outsourced consultants is greater than the critical p-value (0.05) therefore the
hypothesis is accepted. This result implies that the extent of use of in-sourced consultants is not
significantly different from the extent of use of outsourced consultants. The result implies that
clients have no preference for in-sourced or outsourced consultants in project development.
Relationship between the Use of In-sourced and Outsourced Consultants and
Project Performance
To determine the influence of the use of the two types of consultants on project performance,
the second hypothesis of the study was postulated. The hypothesis states that the extent of use
of in-sourced and outsourced consultants and project performance are not significantly related
that is the extent of use of either in-sourced or outsourced consultants does not have significant
influence on project performance. For the test of the hypothesis, data collected on the use of the
two variables of project consultants and the respondents’ assessment of the twelve variables of
project performance as stated in the research methods were used. The hypothesis was tested
using the Chi-square and Spearman correlation tests with p≤0.05. The rule for the acceptance
or rejection of the hypothesis is that when p-value>0.05, the hypothesis is accepted but when p-
value≤0.05, the hypothesis is rejected. The results are presented in Table 4.
On the relationship between the use of in-sourced consultants and project performance, Table 4
shows that the p-values for the test of relationship between the percentage of in-sourced
consultants and the respondents assessment of project duration (0.758), variations (0.663),
fluctuation (0.229), project risks (0.097), conflicts/disagreement between consultants and
contractors (0.356) and percentage of time-overrun to initial contract period (0.080) are greater
than the critical p-value (0.05) therefore the hypothesis is accepted. This result implies that the
number of in-sourced project consultants has no significant relationship with the perception of
clients on project duration, variations, fluctuation, project risks, conflicts or disagreements
between consultants and contractors and the percentage of time-overrun to initial contract
period of projects. However, the p-values for the test of correlation between the percentage of
in-sourced consultants and the respondents assessment of project cost (0.033), project quality
(0.017), conflicts between clients and contractors (0.015), conflicts between clients and
consultants (0.038), compliance with contract obligations (0.001) and percentage of cost-
overrun to initial contract period (0.002) are lower than the critical p-value (0.05) therefore the
hypothesis is rejected. The result indicates that the number of project consultants sourced from
among clients’ staff has significant correlation with the perception of the clients on project cost
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
53
and quality, conflicts between clients and contractors and between client and consultants,
compliance with contract obligations and overrun in the cost of projects.
Variables correlated
N
p
Decision
Rel
% of in-sourced consultants
Res asmt of project cost
Res asmt of project duration
Res asmt of project quality
Res asmt of variations
Res asmt of fluctuation
Res asmt of project risk
Res asmt of client & contractors’ conflicts
Res asmt of client & consultants’ conflicts
Res asmt of consultants & contractors’ conflicts
Res asmt of compliance with contract obligations
% time-overrun to initial contract period
% cost-overrun to initial contract sum
164
164
164
164
164
164
164
164
164
164
80
54
2
x
0.166
-0.024
-0.186
-0.034
0.095
0.130
0.189
-0.162
0.072
0.299
R
0.197
-0.409
0.033
0.758
0.017
0.663
0.229
0.097
0.015
0.038
0.356
0.001
0.80
0.002
Reject
Accept
Reject
Accept
Accept
Accept
Reject
Reject
Accept
Reject
Accept
Reject
S
NS
S
NS
NS
NS
S
S
NS
S
NS
S
Table 4 Results of Spearman test of correlation between the use of in-sourced and outsourced
consultants and project performance
N=Number of respondents, x
2
= Chi-square value, R=Correlation coefficient, p=p-value, Res=respondent,
Asmt=assessment, Rel=relationship, S=significant, NS=not significant
Difference between Performance of Projects based on the Use of In-sourced and
Outsourced Consultants
The argument in favour of the use of outsourced consultants has been that the cost is less than
that of engaging in-sourced consultants. The attempt to justify the engagement of in-sourced
consultants prompts the comparison between the performance of projects in which in-sourced
consultants were engaged with that of projects in which outsourced consultants were engaged.
For the purpose of this comparison, the percentages of time-overrun to initial contract period
and cost-overrun to initial contract sum of projects in which in-sourced project managers,
architects, quantity surveyors and structural, electrical and mechanical engineers were engaged
were compared with those of projects in which outsourced consultants were engaged. The third
hypothesis of the study was postulated for purpose of the comparison. The hypothesis states
that the performance of projects in which in-sourced consultants were engaged is not
significantly different from the performance of projects in which outsourced consultants were
engaged. The hypothesis was tested using the t-test with p≤0.05. The rule for the acceptance or
rejection of the hypothesis is that when p-value>0.05, the hypothesis is accepted but when p-
value≤0.05, the hypothesis is rejected. The results are presented in Table 5.
Table 5 shows that the p-values for the test of difference between the percentages of time-
overrun to initial contract period of projects in which in-sourced and outsourced project
managers (0.847), architects (0.563), quantity surveyors (0.649), mechanical engineers (0.360)
and structural engineers (0.209) were engaged are higher than the critical p-value (0.05)
therefore the hypothesis is accepted. These results imply that the time-overruns of projects in
which in-sourced project managers, architects, quantity surveyors, mechanical and structural
engineers were engaged are not significantly different from those of projects in which
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
54
outsourced project managers, architects, quantity surveyors, mechanical and structural
engineers were engaged. Similarly, the p-values for the test of difference between the
percentages of cost-overrun to initial contract sum of projects in which in-sourced and
outsourced project managers (0.937), electrical engineers (0.112) and structural engineers
(0.733) were engaged are higher than the critical p-value (0.05). These results signify that the
hypothesis is accepted that is the cost-overruns of projects in which in-sourced project
managers, electrical and structural engineers were engaged are not significantly different from
projects in which outsourced project managers, electrical and structural engineers were
engaged.
Parameter
Consultant
N
Mean
t-value
Df
p-value
Decision
Diff
Project manager
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
66
14
50
14
16.29
17.01
12.81
13.35
-0.194
-0.080
78
62
0.847
0.937
Accept
Accept
NS
NS
Architect
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
30
48
24
28
16.52
14.95
7.87
16.00
0.581
-2.396
76
50
0.563
0.020
Accept
Reject
NS
S
Quantity surveyor
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
38
42
32
22
15.74
17.03
8.09
19.78
-0.457
-3.631
78
52
0.649
0.001
Accept
Reject
NS
S
Mechanical engr
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
28
52
24
30
18.19
15.47
8.52
16.32
0.920
-2.297
78
52
0.360
0.026
Accept
Reject
NS
S
Electrical engr
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
32
48
28
26
19.84
14.13
10.16
15.75
2.025
-1.618
78
52
0.046
0.112
Reject
Accept
S
NS
Structural engr
Time-overrun
Cost-overrun
In-source
Outsource
In-source
Outsource
44
34
38
14
18.07
14.40
13.67
12.27
1.266
0.344
76
50
0.209
0.733
Accept
Accept
NS
NS
Table 5 Results of t-test of difference in project performance based on the use of in-sourced and
outsourced consultants
N=Number of respondents, Diff=Difference, engr=engineer
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
55
Table 5 however shows that the p-value for the test of difference between the percentages of
time-overrun to initial contract period of projects in which in-sourced and outsourced electrical
engineers (0.046) were engaged is less than the critical p-value (0.05) therefore the hypothesis
is rejected. This result implies that the time-overrun of projects in which in-sourced electrical
engineers were engaged are significantly different from that of projects in which outsourced
electrical engineers were engaged. Similarly, the p-values for the test of difference between the
percentages of cost-overrun to initial contract sum of projects in which in-sourced and
outsourced architects (0.020), quantity surveyors (0.001) and mechanical engineers (0.026)
were engaged are less than the critical p-value (0.05) therefore the hypothesis is rejected.
These results indicate that the cost-overruns of projects in which outsourced architects, quantity
surveyors and mechanical engineers were engaged are significantly different from projects in
which in-sourced architects, quantity surveyors and mechanical engineers were engaged. The
results in Table 5 reveal that the mean time-overrun of projects in which in-sourced electrical
engineers were engaged (19.84 weeks) is higher than the mean time-overrun of projects in
which outsourced electrical engineers were engaged (14.13 weeks). This result tends to
indicate that less time-overrun was recorded in projects in which outsourced electrical engineers
were engaged compared to projects in which their in-sourced counterparts were engaged.
However, the mean cost-overrun of projects in which outsourced architects (N16 million),
quantity surveyors (N19.78 million) and mechanical engineers (N16.32 million) were engaged
are higher than the mean cost-overruns of projects in which in-sourced architects (N7.87
million), quantity surveyors (N8.09 million) and mechanical engineers (N8.52 million) were
engaged. These results indicate that less cost-overrun was recorded in projects in which in-
sourced architects, quantity surveyors and mechanical engineers were engaged compared to
projects in which their outsourced counterparts were engaged.
Discussion of Findings
The analysis of the percentages of use of the two sources of consultants in Table 2 has shown
that the extent of use of in-sourced project managers is the highest, followed by in-sourced
quantity surveyors while the extent of use in-sourced electrical engineers is the least. The
reverse is the case of the extent of use of outsourced consultants in project development. These
results indicate that clients’ preference for in-sourced and outsourced consultants in project
development varies from one consultant to another, and that clients do not rely on one of the
two sources of consultants in project development; rather they use their staff as some
consultants and source the others from outside.
The results in Table 4 that there is no significant difference between the extent of use of in-
sourced and outsourced consultants also support the finding that clients use the two types of
consultants for the development of projects. This finding shows that the two types of consultants
are important features of project development in Nigeria. It also goes to show that clients are
found of employing professionals who serve as consultants in their organizations. The results of
the influence of the use of the two types of consultants in Table 4 shows that the use of either
in-sourced or outsourced consultants has significant influence on clients’ assessment of project
cost, quality, conflicts between project team members and cost-overruns.
The results of the test of difference in the performance of projects in which the two types of
consultants were engaged tend to indicate that the engagement of in-sourced or outsourced
project managers and structural engineers does not make any difference on project
performance. This tends to imply that clients can engage their staff or external consultants as
project managers and structural engineers without any increase or decrease in both time and
cost overruns. However, the results of the study show that the engagement of outsourced
electrical engineers could help to achieve savings in the delivery time of projects compared to
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
56
when in-sourced electrical engineers are engaged but such will not make any difference in the
overrun in the delivery cost of projects.
This result may suggest that an outsourced electrical engineer is unlikely to prolong his
involvement in a project but more willing to perform his service and disengage from a project on
time than his counterpart in the employment of the client. This interest can be attributed to the
fact that his service fee is fixed and may not vary with the duration of his involvement in a
project. The implication of this result is that considerable time can be saved in projects that have
long duration when electrical engineers are outsourced. On the other hand, the engagement of
in-sourced architects, quantity surveyors and mechanical engineers could help to achieve
savings in the delivery cost of projects compared to when outsourced consultants are engaged
but this will not make any difference in the delivery time of projects. This result may indicate that
in-sourced architects, quantity surveyors and mechanical engineers have better knowledge of
both the client and project requirements than their outsourced counterparts and this knowledge
helps to minimise incidences of variations and the likes that are responsible for cost-overrun.
The implication of this result is that cost can be saved when project design, in particular
architectural and mechanical drawings and bills of quantities are carried out in-house, that is
direct labour instead of contract.
Conclusion
The study has established that in-sourcing and outsourcing of consultants is a feature of the
project delivery process. This finding shows that clients are often faced with the challenge of
deciding which of the two types of consultants to engage when they embark on project
development. Organisations all over the world are abandoning the practice of keeping many
construction professionals as staff because construction is a service activity and they need to
concentrate on their core business activities and reduce overhead costs. This study has
contributed to existing studies on the benefits of in-sourcing and outsourcing by revealing the
benefits derived from project outcome when they are adopted. It has revealed that organisations
do not have anything to lose on project outcome by engaging external project managers and
structural engineers as project consultants. Specifically, it has discovered that outsourcing
electrical engineers in project development not only provide the clients with the numerous
benefits of outsourcing discovered in previous studies, it will equally assist organisations to
reduce the delay to be experienced in project delivery. On the other hand, the study has
discovered that by engaging in-house architects, quantity surveyors and mechanical engineers
as consultants, organisations are likely to derive the benefit of reduced cost-overrun. These
results suggest the need for organisations to engage a mixture of in-sourced and outsourced
consultants in project development. In adopting this, it is suggested that such organisations
should give consideration to electrical engineers in outsourcing and architects, quantity
surveyors and mechanical engineers in in-sourcing.
Suggestion for Further Studies
Time and cost overruns are not the only parameters of project outcome. The study could not
investigate the benefits associated with other important parameters of project outcome such as
project quality when the two consultants are engaged in project development. It therefore
suggests further studies on the influence of the use of the two consultants on other parameters
of project outcome such as project quality in order to complement the results of the study.
References
Bettis, R., Bradley, S. and Hamel, G. (1992) Outsourcing and industrial decline, Academy of
Management Executive, 6 (1), 7-22
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
57
Boes, H. and Doree, A. (2009) ‘Public procurement of local authorities in the Netherlands: a
case of breaking tradition for a more strategic approach, Proceedings of RICS COBRA
Research Conference, University of Cape Town, 10-11th September
Carlson, B. (1989) ‘Flexibility and theory of the organisation’, International Journal of Industrial
Organisation, 7 (1), 189-203
D’Aveni, R. and Ravenscraft, D. (1994) ‘Economies of integration versus bureaucracy costs:
Does vertical integration improve performance?’, Academy of Management Journal, 37 (5),
1167-1206
Dess, G. G., Rasheed, A., McLaughlin, K. and Priem, R. (1995) ‘The new corporate
architecture, Academy of Management Executive, 9 (3), 7-20
Domberger, S. (1998) The contracting organisation: a strategic guide to outsourcing, 1
st
edition,
Oxford University Press, Oxford
Ender, K. L. and Mooney, K. A. (1994) ‘From outsourcing to alliances: Strategies for sharing
leadership and exploiting resources in metropolitan universities’, Metropolitan Universities: An
International Forum, 5 (3), 51-60
Federal Government of Nigeria (1986) Budget, Federal Government Press, Lagos
Gilley, K. T. and Rasheed, A. (2000) ‘Making more by doing less: an analysis of outsourcing and
its effect on firm performance’, Journal of Management, 26 (4), 763-790
Grover, V, Cheon, M. J. and Teng, J. T. C. (1996) The effect of service quality and partnership
on the outsourcing of information systems functions’, Journal of Management Information
Systems, 12 (4), 89-116
Harigan, K. R. (1985) ‘Formulating vertical integration strategies’, Academy of Management
Review, 9 (4), 638-652
Harrigan, K. R. (1985) Exit barriers and vertical integration’, Academy of Management Journal,
28 (3), 686-697
Harrison, B. T. (1994) Lean and Mean: The Changing Landscape of Corporate Power in the
Age of Flexibility, Basic Books, New York
Havemann, G. (2007) The challenge of engaging South Africa’s unemployed in construction
sector delivery’, Proceeding of the CIB World Building Conference on Construction for
Development, Cape Town, South Africa, 14-18 May 2007
Idoro, G. I. (2004) ‘The effect of globalisation on safety in the construction industry in Nigeria’,
Proceedings of International Symposium on Globalisation and Construction, 17-18 November,
Asian Institute of Technology, Thailand, 817-826
Idoro, G. I. (2006) ‘An evaluation of the use of direct labour system in the Nigerian construction
Industry’, Urban and Planning Review, 1 (1), 75-88
Idoro, G. I. (2009a) ‘Clients’ perception of construction project leaders in the Nigerian
construction Industry’, Journal of Engineering, Design and Technology, 7 (3), 264-271
Idoro, G. I. (2009b) ‘Correlation between managerial and technical capacities and quality
performance of indigenous and expatriate contractors in Nigeria’, International Journal of
Construction Project Management, 1 (2), 173-187
Idoro, G. I. (2010) ‘Influence of quality performance on clients’ patronage of indigenous and
expatriate construction contractors in Nigeria’, Journal of Civil Engineering and Management, 16
(1), 65-73
Australasian Journal of Construction Economics and Building
Idoro, G I (2011) ‘Influence in-sourcing and outsourcing of consultants on construction project performance in Nigeria,
Australasian Journal of Construction Economics and Building, 11 (4) 45-58
58
Idoro, G. I. and Okun, B. O. (2011) ‘Project leaders’ assessment of the contribution of
contractors to delay in the delivery of federal government projects in Nigeria’, Proceedings of
RICS COBRA 2011 International Built and Human Environment Conference, 12-13 September,
University of Salford, Manchester, UK
Kanji, G. K. and Wong, A. (1998) ‘Total quality culture in the construction industry’, Total Quality
Management, 9 (4/5), 133-140
Kotabe, M. (1992) Global Sourcing Strategy: R&D, Manufacturing and Marketing Interfaces, 1
st
edition, Quorum Publications, New York
Kotabe, M. and Murray, J. (1990) Linking product and process innovations and modes of
international sourcing in global competition: a case of foreign multinational firms’, Journal of
International Business Studies, 3, 383-408
Lei, D. and Hitt, M. (1995) Strategies restructuring and outsourcing: The effect of mergers and
acquisition and LBOs on building firm skills and capabilities’, Journal of Management, 21 (5),
835-859
Loh, L. and Venkatraman, N. (1992) Determinants of information technology outsourcing: a
cross-sectional analysis’, Journal of Management Information Systems, 9 (1), 7-24
Meiling, J. and Johnsson, H. (2009) Feedback in industrialised housing: why does it not
happen?’, Proceedings of RICS COBRA Research Conference, University of Cape Town, 10-
11th September
Michell, K., Brown, P., Catell, K., Edwards, P. and Pearl, R. (2007) ‘Stakeholder perception of
construction time, cost and quality management of building projects’, Proceeding of the CIB
World Building Congress on Construction for Development, Cape Town, South Africa, 14-18
May 2007
Odusami, K. T. (1999) ‘A survey of current trends in quantity surveying consultancy practice in
Nigeria’, The Quantity Surveyor, Journal of the Nigerian Quantity Surveyor, Jan/March, 57-62
Quinn, J. B. (1992) Intelligent Enterprise: A Knowledge and Service Based Paradigm for
Industry. Free Press, New York
Quinn, J. B., Doorley, T. L. and Paquette, P. C. (1990) ‘Technology in services: rethinking
strategic focus’, Sloan Management Review, 31 (2), 79-87
Renier, B. and Volker, L. (2009) ‘The architect as a system integrator’, Proceedings of RICS
COBRA Research Conference, University of Cape Town, 10-11th September, 103-113
Sang, J. K. (2010) ‘Outsourcing in Kenyan universities: an examination of challenges and
opportunities’, International Journal of Business and Social Science, 1 (2), 204-212
Sattineni, A. and University, A. (2008) ‘Outsourcing and off-shoring: options for the US
construction industry’, International Business and Economics Research Journal, 7 (5), 59-66
Teece, D (1987) ‘Capturing value from technological innovation, strategic partnering and
licensing decisions in Guile, B. and Brooks, H. (Eds), Technology and Global Industry, National
Academy Press, Washington
Tembo, E. and Rwelamila, P. M. D. (2007) Project management maturity in public sector
organisations: the case of Botswana’, Proceedings of CIB Conference W065/055: Commissions
Transformation through Construction organised by Herriot-Watt, University, Edinburg, Dubai,
November
... Despite the results of these studies and an increasing shift towards total outsourcing of consultancy services by many public-sector organisations, limited studies have been undertaken to evaluate the effectiveness of outsourcing and insourcing of consultancy services during the design, procurement and delivery of public-sector construction projects (Idoro, 2011;Khan et al., 2019). Also, a plethora of studies have been focussed on the impact of outsourced services on organisational performance (Abdul-Aziz and Ali, 2004;Ikediashi and Mbamali, 2014;Nyameboame and Haddud, 2017). ...
... The services provided by these professionals include the development of client requirements, preparation of project documents, establishing and monitoring milestones to ensure that they are attained timeously, to the specified quality and within budget (Idoro, 2011) and are critical for achieving successful project performance. Furthermore, from a methodological perspective, a cursory scan of relevant literature about this phenomenon revealed an overt focus on mixed-method and survey research designs (Abdul-Aziz and Ali, 2004;Idoro, 2011;Verroiopoulos and Sfakianaki, 2015;Khan et al., 2019;Ranasighe et al., 2019). Deviating from this supposed norm, the grounded theory methodology (GTM) was applied to achieve the objectives of objective this study. ...
... Whereas outsourcing was previously limited to activities such as cleaning, catering and security services, Agburu et al. (2017) and Dominguez (2006) asserted that it has expanded to critical areas in several industries, including design, manufacturing information systems and project and facilities management. In other instances, public-sector organisations have adopted a hybridised option whereby a mix of in-house, professional personnel and external consultants are engaged during the delivery of infrastructure projects (Idoro, 2011). These consultants might be situated either within the public-sector organisation where they are referred to as in-house or insourced consultants or external to the organisation and are referred to as outsourced consultants. ...
Article
Full-text available
Purpose An increase in outsourcing of consultancy services has been observed during procurement and delivery of public-sector infrastructure projects. However, the incidence of project failure has continued unabated despite this shift by public-sector entities. Also, there appears to be limited literature focussed on seeking to provide the rationale governing the decision to outsource or insource consultancy services by public-sector organisations. The purpose of this study was to appraise the performance of public-sector projects in which consultancy services have been outsourced or insourced. These are the gaps which this study was undertaken to fill. Design/methodology/approach A grounded theory methodology (GTM) research design was adopted based on the nature of evidence sought and gathered from a Provincial Department of Public Works and Infrastructure (PDPWI) in South Africa. Data was obtained from a mixture of semi-structured interviews and project-specific documents spanning a five-year period and was analysed according to the procedures associated with GTM. Accordingly, open coding, axial coding and pattern matching were carried out at several intervals to develop categories and themes. Findings The findings of the study showed the absence of a structured approach within the PDPWI for facilitating decisions pertaining to outsourcing or insourcing consultancy services within construction projects. Furthermore, the study established that both approaches yielded similar results across all performance facets of cost, time and quality. In addition, a detailed insight into the steps required for the successful application of GTM in built environment research has been provided in the study. Originality/value Limited studies have been undertaken to compare the impact of either outsourced or insourced services on the organisational and project performance. This was the gap to which the study reported in this paper was undertaken to contribute.
... Since building construction project's major goals and focus are on the needs of the client, meeting those needs and getting the client's satisfied will increase the likelihood that the project will be successful. There are many ways to assess client satisfaction with building construction projects but majority of studies employed the three criteria of cost, time, and quality (Idoro, 2010;Idoro 2011). Idoro (2011) stated that project objectives that take client goals into account are evaluated from a variety of angles, but the primary purpose is to enable customers to clearly identify and convey their goals and allow construction managers to accomplish these goals via the project participants. ...
... There are many ways to assess client satisfaction with building construction projects but majority of studies employed the three criteria of cost, time, and quality (Idoro, 2010;Idoro 2011). Idoro (2011) stated that project objectives that take client goals into account are evaluated from a variety of angles, but the primary purpose is to enable customers to clearly identify and convey their goals and allow construction managers to accomplish these goals via the project participants. ...
Article
Full-text available
Performance of construction projects is a crucial driver of economic growth and infrastructural development in Nigeria, but there is still a need for a tool that can accurately analyze construction project performance from the design stage through construction and completion. This study developed a performance model for building construction projects in higher institutions, Southwest Nigeria. Literature was reviewed to identify the previous performance measurement parameters and were classified into sixteen by pilot survey. Qualitative research approach was adopted and a structured questionnaire was administered to 394 project stakeholders and 297 (75.38%) were retrieved from respondents. Mean Score, Kuskal wallis test, analysis of variance and least significant difference post hoc test was used to determine the convergence and divergent views of the stakeholders. Factor analysis as data reduction method via principal component extraction was used to classify project performance into five categories. The study’s findings indicate that client satisfaction with the project (MS = 3.833), Construction time predictability (MS = 3.845) and construction cost predictability (MS = 3.832) were ranked as the top three performance index. From the result of the reliability analysis, project performance was loaded into five (5) integrated factors; construction management, stakeholder management, quality, cost and time performance indicators. It is hereby recommended that client satisfaction, accurate time estimate and good cost forecast should be considered when executing building construction projects to enhance performance. It is also recommended that attention should be given to the five integrated performance indices during construction of building projects to improve performance..
... Consultants typical clarify clients' needs, develop designs meeting those needs, establish modalities for contractor engagement and manage the overall procurement process on behalf of the client (Dosumu and Aigbavboa, 2019). In major construction projects, the services of consultants are thought to be indispensable (Idoro, 2011). Particularly in design-bid-build procurements, the contractors' main role is to place the structure physically on ground to the consultants' approval. ...
... Despite the huge construction procurement involvement of the Nigerian Government, there are few Nigerian studies on the selection of construction consultants, none of which provides a clear insight into the relationship between consultant selection criteria and client satisfaction. Idoro (2011) studied the influence of insourcing and outsourcing of consultants on construction project performance in Nigeria without focusing on the criteria used in the selection of the outsourced consultants. Adedapo's (2014) interest was limited to the criteria for selection of architects by first-time clients. ...
Article
Purpose To receive a satisfactory consultancy service, a construction client must first select suitable consultants. While numerous criteria for the selection of construction consultants have been suggested in the literature, their influence on client satisfaction has hardly been statistically established. This study aimed to reduce the criteria for the selection of construction consultants into a more manageable set of fewer factors and ascertain the influence of the factors on client satisfaction. Design/methodology/approach Data were gathered through a purposively administered cross-sectional survey of public sector clients in Nigeria. Analyzes were done using relative importance index, factor analysis and multiple regression analysis. Findings The results proved that the criteria for the selection of consultants can, in the order of decreasing influence on client satisfaction, be grouped into service delivery approach (SDA), relationship with the client, the caliber of personnel, firm reputation and firm certification. However, SDA is more influential on client satisfaction. All the factors were found to have significant statistical effects on clients’ overall satisfaction with consultancy services. Originality/value The study demonstrates the extent to which construction consultant selection criteria are relevant to client satisfaction. It shows that SDA is the most important predictor of clients’ satisfaction with consultancy services. The results are helpful for grouping consultant selection criteria in future studies, and in guiding clients on the weights to assign to consultant selection criteria during tender evaluation.
... Complete and accurate as-built drawings are more than documents developed when a construction project is completed. They are key tools that provide essential information needed in the operation and maintenance stages [27]. ...
... Self-administered questionnaire was used because of its ability to obtain both secondary and primary data. A structured questionnaire was selected for consistency since a cross-sectional design requires use of quantitative analysis (Afolabi et al., 2017;Alashwal et al., 2017;Idoro, 2011;Gupta, 2003). The questionnaire was prepared to reflect the research objectives and variables with structured questions (Taofeeq et al., 2020;Durdyev et al., 2017). ...
... Smart technology, which is in the spotlight for technological innovation, is also usually being used in construction projects via this contractual relationship. It is common for contractors to improve their technical capabilities through in-house or outsourced management strategies, especially for construction firms that carry out projects by utilizing resources such as equipment, manpower, and building technology [57][58][59][60][61][62]. These strategies are traditional methods to ameliorate the organizational and technological capabilities of an enterprise [62][63][64]. ...
Article
Full-text available
The fourth industrial revolution (4IR) is bringing about enormous changes in various aspects of the construction industry. This influence is emerging as a smart technology and is regarded as a productivity innovation in the construction industry. In addition, several countries are attempting policies to diffuse technological innovation into various industries, such as those related to legal systems, investments, and additional markets. These policies commonly have the intention to encourage various industrial factors that are related to smart-construction competitiveness. Therefore, this study analyzed the competitiveness from an industrial perspective to revitalize smart technologies in the construction industry. For this purpose, the acceptance of innovation within the Korean construction industry (KCI) was reviewed through diffusion-innovation theory, and then competitiveness factors were driven by the literature, based on Porter’s diamond model. Factors are measured by the contractors who utilize smart technologies, analyzing the competitiveness priority and differences between them. The main finding is that the “Demand Condition” is the most important industrial competitiveness for embedding smart technology in the early stage of construction industry. Moreover, to reduce the risks related to developing technologies, it suggested that distinct policies are required in accordance with the contractors. These findings are going to be helpful for policy makers as references for developing policies to embed smart technology in the construction industry.
... Perhaps inventions and good technology do not exist to test their success against the existing norm. Idoro (2011) and Idoro and Okun (2011), claimed that on the one hand, with growing higher consumer requirements, environmental knowledge and limited resources, and high completion for construction company, on the other hand, contractors must be able to enhance their performance continuously. A variety of studies have been carried out to analyze the effect of variables on the success of projects in developing countries. ...
Article
Full-text available
Nigeria's indigenous construction companies face the problem of poor performance on construction projects in different areas in terms of quality, cost and time. This may be due to the fact that companies do not have good creativity and technology to improve their construction activities and evaluate them. One of the innovations is the outsourcing in construction projects. To this end, this study was carried out to examine the perception of some professionals in Ondo State, Nigeria, of how outsourcing has been used in the construction of projects. A Survey design methodology was used. One hundred and two (102) questionnaires were sent to the respondents (Engineers-41, Builders-17, Quantity Surveyors-18, and Architects-26). The data gathered was statistically analyzed. The results showed that 30 % and 70 % were female and male respectively and they are all qualified in terms of their academic qualifications. The findings showed that the areas of company outsourcing include substructure, superstructure (18.6%), finishing (27.1%), and materials (34.3%) which were outsourced by 20 percent of respondents. Over forty-two percent (42.9%) of the respondents suggested that their level of outsourcing for companies is exceptionally high. The professionals observed that outsourcing has improved their company efficiency on project construction; cost reduction, delivery time, cost control, quality of project. The independent Kruskal-wallis sample test established the relationship between project success and the level of company outsourcing. Finally, to improve the use of outsourcing, the respondents indicated that organizing seminar; doing your homework; keeping a good clear record; issuing proposal requests; ensuring quality work; buying into management; involving key parties; ensuring a competitive environment are important criteria for improving the performance of contractors on construction projects.
... All major infrastructural projects in public institutions have consultants because the institutions are statutorily required to engage them. Idoro (2011) noted that it would be very difficult to procure/execute public projects without the services of consultants. A consultant's role is not only to design and supervise construction as already pointed out by Ling, Ofori and Low (2003). ...
Article
Full-text available
Almost all tertiary institutions' new construction projects in Nigeria have consultants. In spite of this, majority of projects in these institutions underperform due to poor management as a result of flaws in the selection of consultants. This study determined the order of priority of the criteria for the selection of consultants for public tertiary institution construction projects in Edo and Delta States. First, a survey of relevant staff of the institutions and their consultants (n=58) was made and analyzed using the RII technique. Secondly, 16 randomly selected respondents to the first survey were surveyed again based on a reduced number of consultant selection criteria, and the data was analyzed using the analytical hierarchy process (AHP). In their order of decreasing importance, the criteria for selection of the consultants were grouped into four, namely: firm and firm owners characteristics, project approach, capacity to accomplish the work, and past performance. Respectively, under each of these groups, the most important sub-criteria are: public policy requirements, confidentiality and trust, perceived professional competence and experience with similar projects. This study offers tertiary institutions the priority that should be accorded construction consultant selection criteria for their projects. It also reveals to their consultants the key qualifying criteria to possess for successful bidding in the institutions. It is recommended that use of ICT and location of firm/proximity to the site should be among the criteria for the selection of construction consultants for tertiary institution projects.
Article
Purpose The purpose of this study is to investigate the influences of the characteristics of procurement strategies, in this instance labour-only, on project performance concerning health and safety (H&S), a project performance indicator. Design/methodology/approach Using non-probability purposeful and snowballing sampling methods, questionnaires were used to collect data from construction professionals in Nigeria. This was then analysed using descriptive (frequency and mean scores) and inferential statistics (Mann–Whitney-U and Kendall's Tau_b tests). Findings The findings indicate a statistically significant negative correlation between ‘the level of client involvement and ‘fatalities' and a positive one with ‘conducting of health and safety risk assessment' and ‘conducting employee surveys on health and safety attitude’. Poor hygiene is found to be the worst lagging indicator, while conducting of inspection is the most adopted leading indicator of project health and safety performance. It also emerged that there is no significant difference in the health and safety performance of projects procured through the procurement strategy in urban and rural areas. Practical implications The study provides valuable insight into the complexities in H&S management due to the high level of client involvement in labour-only procurement system (LoPS) projects and the level of diversity in their responsibilities therein. It creates a fundamental direction for developing a detailed framework or guidance notes for client involvement in the integration of H&S into LoPS projects. Originality/value This is the first study that examines the influence of the characteristics of procurement strategy on project health and safety performance. Evidence in the literature shows that project delivery outcomes significantly improve if procurement is strategically used, including when it is considered early in projects. However, integrating H&S into procurement strategies has received little attention.
Article
Full-text available
Firmaların işlevsel yeteneklerinden olan lojistik yetenekler, günümüz iş düyasında firmaların gelişim göstermelerine katkıda bulunmaktadır. Bu çalışmanın amacı, lojistik yeteneklerin mali performans üzerinde yarattığı etkileri araştırmaktır. Ayrıca firmaların yaşı ve büyüklüğünün performans üzerinde bir etkide bulunup bulunmadığı araştırılmıştır. Araştırma kapsamında, Tekirdağ ilinde yabancı sermayeli üretici firmalarının sahip oldukları lojistik yetenekleri ile mali performans değişkenleri arası ilişkiler ele alınmıştır. Bu amaç ve kapsam doğrultusunda, bir araştırma modeli ve modele bağlı araştırma hipotezleri geliştirilmiştir. Modelde geliştirilen hipotezleri test edebilmek için araştırma kapsamında faaliyet gösteren ve tesadüfi örnekleme yöntemiyle seçilen 53 yabancı sermayeli üretici firmasında yönetici pozisyonunda çalışan 106 yöneticiye, araştırma için oluşturulan anket uygulanmıştır. Yapısal Eşitlik Modellemesi yöntemi kullanılarak yapılan analizler, lojistik yeteneklerin mali performans üzerinde pozitif etkide bulunduğunu göstermektedir. Ayrıca, lojistik yetenek göstergelerinin kombinasyonun sağlanarak performans üzerinde etkide bulunduğu belirlenmiştir. Özellikle lojistik yeteneklerin rekabet gücü üzerinde pozitif bir etkide bulunarak yüksek performans ediniminde önemli bir tamamlayıcı olduğu sonucu elde edilmiştir.
Article
Full-text available
Three organizational structures for business enterprises are examined for their ability to enhance profitability and competitiveness. The structures, namely: the modular, virtual, and barrier-free, are studied using value chain analysis. Results show that the three structures complement each other and enable executives to achieve seemingly unattainable objectives by taking advantage of technological innovations or penetrating new markets.
Article
Full-text available
The construction industry relies on the skills of structural engineers for all projects. There exists a large volume of design and detailing work for structural engineering in the United States (US) and there are insufficient numbers of qualified designers in the US to do the work. Recent changes in the telecommunications sector make off-shoring structural design work to developing countries like India and China a realistic possibility. Economics of outsourcing is a key reason for this possibility to be realized. It is logical to consider the effects of outsourcing in the design sector and its effects on the construction industry. The manuscript will present the author's finding based on detailed case-study model research with two companies that are outsourcing work to India from the US. The author conducted detailed interviews with principals in US structural design firms and then traveled to Bangalore, India to interview their Indian counterparts. Results from these interviews are presented. The author will present an empirical model for outsourcing construction activities. Processes in the construction industry that are most suited for outsourcing and off-shoring are presented. Issues surrounding outsourcing such as training, economics and logistics are discussed.
Article
Projects developed by the Federal Government of Nigeria (FGN) are very crucial to the economy of the nation. The failure of contractors to deliver them on time has serious negative implications on the growth of the Nigerian economy. This study investigates the factors that affect contractors' contribution to delay in the delivery of FGN projects. The objectives are to evaluate the relative effects and significant difference in the effects of selected factors that affect the contribution of indigenous and expatriate contractors to delay in the delivery of FGN projects. To achieve these objectives, a field survey involving a sample of 78 project leaders was conducted. Data were collected using structured questionnaires and analysed using percentage, Relative Effect Index (REI) and t-tests. The results reveal that the effects of the factors that affect the contribution of indigenous and expatriate contractors to delay do not differ. It was equally discovered that material management problems, Plants and Equipment (P&E) management problems, poor construction planning and scheduling, poor communication and coordination, delay in mobilising to site and inadequate provision of required utilities on site which are contractor related rank high in factors that contribute to delay in FGN projects. The major conclusions are that the effects of the factors on delay in projects executed by the two categories of contractors are the same and that several contractor-related factors found in previous studies to be responsible for project delay still persist in the delivery of FGN projects. The main suggestions are that the contractors should adopt effective and efficient material and P&E management strategies, effective communication, construction planning and scheduling, avoid delay in mobilising to site and ensure the provision of essential utilities on site.
Article
A framework is proposed that develops the dimensions of vertical integration strategies and proposes key factors that might augment their uses within various scenarios. These represent new hypotheses and conjectures about make-or-buy decisions that require empirical testing. If the framework is valid, strategists could formulate better hybrid vertical integration strategies by recognizing the hypothesized effects of these forces on the industries that might be linked.
Article
The present paper unmasks the actual experiences of outsourcing of services in Kenyan public universities with the aim of outlining the challenges, opportunities and lessons for future outsourcing initiatives. It is based on primary data obtained from six public universities that were qualitative studied. Anchored on the decision theory (Jurison, 1995) and aspects of the risk theory (Bauer, 1967), the study's key informants were interviewed and questionnaires were administered. The inquiry revealed that through outsourcing, the universities are able to cut costs, improve efficiency and meet their rising demands for greater accountability. The major challenges noted in outsourcing included negative attitude of staff, poor monitoring and evaluation, non-cooperation by students to the outsourced and interference by community. It is hoped that the findings will be beneficial to universities, particularly those that are considering outsourcing or broadening the range of such services.
Article
The improper use of outsourcing is playing an important role in the continuing competitive decline of many Western firms. Western managers often view outsourcing as a defensive operational measure. The approach tends to be incremental. A whole series of incremental outsourcing decisions, taken individually, may make economic sense, but collectively they may also represent the surrender of the business's capability to compete. However, properly understood and managed as an overall part of strategy, outsourcing can aid competitiveness. This article, based on the authors' research with firms in North America, Europe, and Asia, discusses the manner in which the improper use of outsourcing can destroy the future of a business, and how the proper use of outsourcing can help build competitive advantage.