DataPDF Available

Security- Constrained Economic Dispatch

Authors:
SECURITY CONSTRAINED
ECONOMIC DISPATCH
(SCED)
Tanzim Mokammel
Sarmad Zulfiqar
Mellitus Ezeme
Overview
Efficiently model a security
constrained economic dispatch
problem
Analyze Optimal point to dispatch power
without violating limits
Demonstrate contingency ranking using
performance index
Suggest best approach to operate
the power system
Introduction
In North America (NA) and Europe
(EU), power systems are subject to
near limit operation due to:
Cheaper generation in distant locations
Easy transportation of power
Leads to the necessity of analyzing
varying operating conditions under
multiple contingency scenarios to
ensure
No sudden cascaded failures resulting
from overloading
Failure from equipment malfunction or
natural disasters
Introduction (Cont’d)
Operators always focus on
dispatching on highest profit
margin
Efficient operation while
maintaining system security
becomes a vital need
Agenda
1. Treating Economic Dispatch
2. Security Analysis
3. Security Assessment
4. Contingency Analysis
5. Case Study
1. Economic Dispatch
Determine quantity of
power to dispatch by
each generator to meet
demand at minimum cost
Usually neglects line and
generator constraints, but
SCED requires it
2. Security Analysis
Monitoring
Use real time system measurements
to determine the operating conditions
of the system
Check if normal, otherwise command
control to take action
Assessment
Check if the system is secure from
probable contingencies
Control
Take action to revert system to
normal operating conditions
3. Security Assessment
Check robustness of system subject to
perturbations with the following methods:
Direct Approach
Use the probability of the system, given current
state and load projections
Depends on a unit to fail to determine if the
entire system is at risk
Indirect Approach
Ensure there are enough reserve margins to
cope with emergencies
Captures more constraints, increases cost
Decision to use either method depends
on performance index
Integrated approach is used in the case
study
4. Contingency Analysis
A way of analyzing the power
system to determine overload and
other problems resulting from
contingencies:
Line Outage
Results in overloading remaining
lines
Power flow readjustment needed
Generator failure
Sudden load increases
4. Contingency Analysis (Cont’d)
Main Tradeoff:
Increased security requires
increased costs
Solution
Identify lines which require
preventive action, and lines that
require post-contingency action
Goal
Maintain integrity of the system and
ensure no damage to transmission
equipment
5. Case Study
IEEE Standard 5-Bus System
Given system topology, load conditions, and ratings of
transmission and generation units:
Determine optimal operating conditions under base case (ignore TL
limits)
Determine line flow of each line using DC flow equation: Plines =
BΔΘ
Check for line flow violations; if found, re-run optimal dispatch with
new limits
Determine PI by removing one line at a time
Rank contingency based on PI
5. Case Study (Cont’d)
1 2 3 4 5 6
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
Line Violaons under Outages
Line Limits
Line 2 Outaged
Line 4 Outaged
Line 6 Outaged
Lines
Power Flow (pu)
5. Case Study (Cont’d)
2 4 6
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
9.2532
2.4352
0.9836
Performance Index of Outaged Lines
Performance Index
Lines
Performance Index
5. Case Study (Cont’d)
1 2 3 4 5 6
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
Security Constrained Economic Dispatch
Base ($460/hr)
Preven've using Line 2 Condi'ons
($540/hr)
Line Limits
Lines
Power Flow (pu)
5. Case Study (Cont’d)
1234567
420
440
460
480
500
520
540
560
Cost Comparison
Line Dispatch at Op'mal Condi'ons w/o Line
Constraints
Line Dispatch at Op'mal Condi'ons w/ Line
Constraints
Lines
Cost ($)
Conclusion
Efficiently modeled a SCED problem
Suggestion
Preventive vs Post-Contingency
Run system in preventive conditions with increased cost to avoid
unquantifiable damages
Reputation
Death
Ripple Effects
Q&A
Backup
5. Case Study (Cont’d)
Line Dispatch at Opmal Condions w/o Line Constraints
LOT
Lines Base 1 2 3 4 5 6
10.0839 0.0000 0.6000 0.0000 -0.0400 0.1200 -0.0250
2-0.5161 -0.6000 0.0000 -0.6000 -0.6400 -0.4800 -0.6250
30.0839 0.0000 0.6000 0.0000 -0.0400 0.1200 -0.0250
40.3097 0.2857 0.4571 0.2857 0.0000 0.4000 0.3750
50.0903 0.1143 -0.0571 0.1143 0.4000 0.0000 0.0250
6-0.1742 -0.1143 -0.5429 -0.1143 -0.3600 -0.1200 0.0000
Cost 460.0000 460.0000 460.0000 460.0000 460.0000 460.0000 460.0000
Line Dispatch at Opmal Condions w/ Line Constraints
LOT
Lines Base 1 2 3 4 5 6
1 0.6000 0.2000 0.0000
2 0.0000 -0.4000 -0.6000
3 0.2000 -0.2000 -0.0333
4 0.3200 0.0000 0.3667
5 0.0800 0.4000 0.0333
6 -0.2000 -0.2000 0.0000
Cost 460.0000 460.0000 540.0000 460.0000 520.0000 460.0000 465.0000

File (1)

Content uploaded by Okwudili Ezeme
Author content
Office Document
ResearchGate has not been able to resolve any citations for this publication.
ResearchGate has not been able to resolve any references for this publication.