Different modelling techniques from different disciplines are needed to model complex socio-technical systems and their requirements. This paper describes the application of RESCUE, a process that integrates 4 modelling techniques to model and analyse stakeholder requirements for DMAN, a system for scheduling and managing the departure of aircraft from major European airports. It describes how human activity, use case and i* modelling were applied and integrated using synchronisation checks to model requirements on DMAN. Synchronisation checks applied at predefined stages in RESCUE revealed omissions and potential inconsistencies in the models and stakeholder requirements that, in turn, led to improvements to the models and resulting specification. The paper ends with implications for requirements model integration, and describes future work to extend and apply RESCUE.
Content may be subject to copyright.
Submitted to CAiSE’2004
Model-Driven Requirements
Engineering: Synchronising Models
in an Air Traffic Management Case
Study
N.A.M. Maiden, S.V. Jones, S. Manning, J. Greenwood1, L. Renou2
Centre for Human-Computer Interaction Design, City University, London
1National Air Traffic Services, London, UK
2Sofreavia/CENA, Paris, France
Contact e-mail:
N.A.M.Maiden@city.ac.uk
Keywords
Requirements engineering, model synchronisation, air traffic management
Submitted to CAiSE’2004
Model-Driven Requirements Engineering: Synchronising
Models in an Air Traffic Management Case Study
Abstract: Different modelling techniques from different disciplines are
needed to model complex socio-technical systems and their requirements.
This paper describes the application of RESCUE, a process that integrates 4
modelling techniques to model and analyse stakeholder requirements for
DMAN, a system for scheduling and managing the departure of aircraft from
major European airports. It describes how human activity, use case and i*
modelling were applied and integrated using synchronisation checks to
model requirements on DMAN. Synchronisation checks applied at
predefined stages in RESCUE revealed omissions and potential
inconsistencies in the models and stakeholder requirements that, in turn, led
to improvements to the models and resulting specification. The paper ends
with implications for requirements model integration, and describes future
work to extend and apply RESCUE.
1. Introduction
Complex socio-technical systems such as air traffic management (ATM) – in which
people depend on computer systems to do their work – need to be analysed from
different perspectives. To do this we need to employ different modelling techniques in
synchronised ways to analyse a future system and its requirements from all necessary
perspectives. Research provides us with different system and requirements modelling
techniques (e.g. Chung et al. 2000, De Landtsheer et al. 2003, Hall et al. 2002,
Rumbaugh et al. 1998). However, further research is needed to synchronise them when
modelling complex socio-technical systems.
In particular, research must overcome 2 major challenges. Firstly, we need to be scale
existing techniques to model and analyse large systems in which people computer
systems interact. Whilst some techniques such as the Rational Unified Process and
UML are used to model large systems, more research-based techniques such as i* have
yet to be used extensively to model large socio-technical systems. Secondly, given the
divergent purposes for which these techniques were originally developed, we need to be
able to synchronise them to detect possible requirements omissions, inconsistencies
and conflicts. One problem is that established requirements techniques have emerged
from single disciplines – use cases from software engineering and task analysis from
human-computer interaction are two obvious examples. Safety-critical socio-technical
systems such as ATM demand rigorous analyses of controller work, software systems
that support this controller work, and the complex interactions between the
controllers, the air traffic and the software systems. To do this we need new processes
that synchronise and analyse models from the relevant disciplines. This paper presents
one such process, RESCUE, and describes its application to a large and computerised
ATM system project.
Previously, academic researchers worked with Eurocontrol to design and implement
RESCUE, an innovative process to determine stakeholder requirements for systems
that will provide computerised assistance to air traffic controllers. RESCUE was
successfully applied to determine the requirements for CORA-2, a complex socio-
technical system in which controllers work with a computerised system to resolve
conflicts between aircraft on a collision path (Mavin & Maiden 2003). The first half
of this paper reports the application of a new version of RESCUE to model the
requirements for DMAN, a socio-technical system for scheduling and managing the
departure of aircraft from major European airports such as Heathrow and Charles de
Gaulle. A requirements team that included engineers from UK and French air traffic
service providers modelled the DMAN system and requirements using techniques
including human activity modelling (Vicenze 1999), i* (Chung et al. 2000), and use
cases (Cockburn 2000). The second half of the paper reports the use and effectiveness
of RESCUE synchronisation checks for cross-referencing and integrating these
different model types during the RESCUE process.
The remainder of this paper is in 5 sections. Section 2 describes related research.
Sections 3 and 4 outline the RESCUE process and describe its synchronisation
checks. Section 5 reports the application of RESCUE to DMAN with emphasis on
data about the effectiveness of the synchronisation checks. The paper ends with
discussion and future research and applications.
2. Related Work
RESCUE draws together and extends work from different sources. Several authors,
including Cockburn (2000), have extended use case techniques with structured
templates. Our work adopts these best-practice extensions to use cases, but also adds
several use case attributes that inform scenario generation from use cases reported in
Mavin & Maiden (2003).
The i* method for agent-oriented requirements engineering is well documented (e.g.
Chung et al. 2000). More recently, researchers have been reporting examples that
demonstrate i*’s applicability for handling non-functional issues such as security and
privacy applied to healthcare systems (Liu et al. 2003). Whilst the reported examples
demonstrate i*’s potentially scaleability, most models have been developed by the
research team. In contrast, RESCUE requires other engineers to produce i* models for
the large socio-technical systems, thus providing additional data about the usability
and effectiveness of the method on industrial case studies.
Other researchers have integrated the i* goal modelling approach implemented in
RESCUE with use case approaches. Santander & Castro (2002) present guidelines for
automatically deriving use case models from i* system models, and Liu & Yu (2001)
integrate goal modelling with the GRL with use case maps to refine scenarios into
architectural designs with goal-based rationale. Our work in RESCUE is similar to the
latter work but exploits i* models to scope use case models, specify use cases and
inform scenario walkthroughs rather than derive architectures per se.
There has also been considerable focus on handling viewpoints and model
inconsistencies in software engineering, although most research is intended to handle
late requirements, specification and design (e.g. Nuseibeh et al. 1994), and imposes
significant analysis overheads on developers. In contrast, detecting and reasoning
across models during early requirements work has received little attention, especially
for socio-technical systems. Leveson et al. (2000) describe a safety and human-centred
approach that integrates human factors and systems engineering work. Although
similar in spirit to RESCUE, their approach includes safety hazard analysis and
verification that were outside RESCUE’s scope, and covers the full development
cycle. Elsewhere, Wright et al. (2000) address the relationship between work in
systems engineering, human-computer interaction and computer-supported
collaborative working with reference to case studies in aircraft design. We share their
concern that traditional systems engineering approaches to function allocation
(determining which system-level functions should be carried out by humans, and
which by machines) may lead to designs that are less than ideal. RESCUE seeks to
address this by linking human activity and use case modelling.
3. The RESCUE Process
The RESCUE (Requirements Engineering with Scenarios for User-Centred
Engineering) process was developed by multi-disciplinary researchers (Maiden et al.
2003, Jones & Maiden 2003). It supports a concurrent engineering process in which
different modelling and analysis processes take place in parallel. The concurrent
processes are structured into 4 streams shown in Figure 1.
Figure 1. The RESCUE process structure – activity modeling ends after the synchronization
stage at stage 2, system modeling after the synchronization stage at stage 3, and scenario-
driven walkthroughs and modeling requirements after synchronization checks at stage 5.
Each stream has a unique and specific purpose in the specification of a socio-technical
system:
1. Human activity modelling provides an understanding of how people work, in
order to baseline possible changes to it (Vicente 1999);
2. System modelling enables the team to model the future system boundaries, actor
dependencies and most important system goals (Chung et al. 2000);
3. Use case modelling and scenario-driven walkthroughs enable the team to
communicate more effectively with stakeholders and acquire complete, precise and
testable requirements from them (Sutcliffe et al. 1998);
4. Managing requirements enables the team to handle the outcomes of the other 3
streams effectively as well as impose quality checks on all aspects of the
requirements document (Robertson & Robertson 1999).
These 4 streams are supplemented with 2 additional processes. Acquiring requirements
from stakeholders is guided using ACRE (Maiden & Rugg 1996), a framework for
selecting the right acquisition techniques in different situations. Creativity workshops
(Maiden & Gizikis 2001) are ran at the beginning of the process to discover and
surface requirements and design ideas that are essential for system modelling and use
case authoring later in the RESCUE streams.
Sub-processes during these 4 streams (shown in bubbles in Figure 1) are co-ordinated
using 5 synchronisation stages that provide the project team with different
perspectives with which to analyse system boundaries, goals and scenarios. These
stages are implemented as synchronisation checks described later in the paper that are
applied to the models at each stage. The next sections describe each of the 4 streams in
more detail.
Human Activity Modelling
In this RESCUE stream the project team develops an understanding of the current
socio-technical system to inform specification of a future system. Activity modelling
focuses on the human users of the technical system, in line with the principle of
human-centred automation (ICAO 1994). To do this the project team must first
understand the controllers’ current work – its individual cognitive and non-cognitive
components and social and co-operative elements - to specify the technical systems
that can better support that work. Introducing artefacts, tools or procedures into the
work domain changes the way in which people work and process information. It also
brings about changes in the cooperative, and possibly organisational structures that are
related to the new system. The stream consists of two sub-processes – gathering data
about and modelling the human activity.
During the first sub-process, data about all components of the activity model are
gathered and recorded, initially in a relatively unstructured way. Techniques to gather
this data include: observation of current system use; informal scenario walkthroughs,
using scenarios that describe how the current system is used; interviews with
representative human users; and analysis of verbal protocols, or recordings of users
talking through scenarios or tasks. In particular the team is encouraged to record data
about what are called the ‘non-prescribed’ elements of the current system. Non-
prescribed elements are those elements – goals, actors, actions, etc – which the human
users of the system have developed to ‘finish the design’, often to work around
difficulties with the current system or increase its flexibility, thus also increasing
redundancy and hence safety.
In the second sub-process, the project team creates different activity models
corresponding to major types of activity in the current system. An activity model is a
repository of information about various aspects of the current system. Data is
structured using simple scenarios that enable it to be mapped to use case descriptions
that describe future system behaviour. Figure 2 describes 3 actions that make up one
human activity description how runway controllers at Heathrow give line-up
clearance to aircraft. Different aspects of the model are linked to the scenario as a
whole or each action, thus providing a structured but flexible description of current
work practices.
Goals: Decision made to when the next aircraft can line up, Pilot given line-up clearance, Strip
positioned correctly in the bay, LVP or MDI procedures adhered to, if in effect
1. Departure/Air controller decides which aircraft can next line up and when
Resources - strip
Physical actions - touch strip, look at airfield, aircraft, holding point and runway, move to
look out of window
Cognitive actions - read strip information, validate visually, recognise aircraft and match
with strip, recognise when it is appropriate to give line up clearance, formulate aircraft line
up clearance sequence, understand current airspace, runway and capacity situation
2. Runway ATCo calls Pilot and gives line up clearance
Resources - strip, radio, headset
Physical actions - touch strip, flick radio transmission switch, look aircraft, runway and
holding point, move to look out of window
Communication - talk to pilot, issue clearance, provide information
Cognitive actions - read strip information, validate visually,
3. Pilot confirms details
Resources - strip, radio, headset
Physical actions - touch strip
Communication - listen to radio communication, confirm details
Cognitive actions - recognise information given, compare information stated with read back
information from pilot
Figure 2. Part of the DMAN Human Activity Model
One key concept in an activity model is goals - the desired states of the system. Goals
may be: (i) high-level functional goals relating to the system as a whole, or local
goals relating to particular tasks; (ii) individual goals, relating to single actors, or
collective goals, relating to teams of actors; (iii) prescribed goals or non-prescribed
goals. Other aspects to describe in a model include:
Human actors - people involved in system;
Resources – means that are available to actors to achieve their goals, for example
flight strips and information about a flight;
Resource management strategies – how actors achieve their goals with the
resources available, for example writing down flight information on the flight
strips;
Constraints - environmental properties that affect decisions, for example the size on
the flight strip bay, which limits the number of strips to work with;
Actions - undertaken by actors to solve problems or achieve goals; and
Contextual features – situational factors that influence decision-making, for
example priorities are given to incoming aircraft.
Data describing these concepts is structured into activity descriptions such as the one
presented in Figure 2.
System Modelling
In this RESCUE stream the project team models the future system’s actors (humans
and otherwise), dependencies between these actors and how these actors achieve their
goals, in order to explore the boundaries, architecture and most important goals of the
socio-technical system. RESCUE adopts the established i* approach (Chung et al.
2000) but extends it to model complex technical and social systems, establish different
types of system boundaries, and derive requirements. i* is an approach originally
developed to model information systems composed of heterogeneous actors with
different, often-competing goals that nonetheless depend on each other to undertake
their tasks and achieve these goals – like the complex socio-technical systems found
in ATM.
The systems modelling stream requires 3 analyses to produce 3 models. The first is a
context diagram, similar to the REVEAL process (Praxis 2001) but extended to show
different candidate boundaries for:
The technological systems, expressed in terms of software and hardware actors;
The redesigned work system, expressed primarily in terms of human actors;
Other hardware and software systems directly influenced by the redesign of the
new system;
Systems that interact with the new system but are not influenced by its redesign.
To help determine these system boundaries we also adopt the notion of different types
of adjacent actors (Robertson & Robertson 1999). The result is an extended context
model with typed actors that provides a starting point for i* system modelling.
The second model is the i* Strategic Dependency (SD) model, which describes a
network of dependency relationships among actors identified in the context model. The
opportunities available to these actors can be explored by matching the depender who
is the actor who “wants” and the dependee who has the “ability”. Since the dependee’s
abilities can match the depender’s requests, the system-wide strategic model is
developed. Figure 3 shows a draft SD model for the DMAN system. It specifies other
systems that either depend on or are depended on by DMAN (e.g. TACT and A-
SMGCS), and human roles that depend on DMAN to do their work (e.g. Runway
ATCO and Departure Clearance ATCO). For example, the SD model specifies that
DMAN depends on TACT to achieve the goal CTOT and slot messages updated, and
A-SMGCS depends on DMAN to undertake the task update taxi time estimates.
Likewise, DMAN depends on the Tower Departure Sequencer ATCo to have the
departure sequence manual update, and the Departure Clearance ATCo depends on
DMAN to achieve the soft goal workload not increased.
Figure 3. Part of the SD Model for DMAN.
RESCUE provokes the team to ask important questions about systems boundaries by
re-expressing them in terms of the goal dependencies between actors on either side of a
boundary. Actors with goals that the team will seek to test for compliance are, by
definition, part of the new system. Such re-expression also leads to more effective
requirements specification by referring to named actors that will be tested for
compliance (e.g. “The controller using DMAN shall have access to the departure
sequence”). It also suggests a first-cut architecture and functional allocation for the
socio-technical system by defining which actors undertake which tasks.
The second type of i* model is the Strategic Rationale (SR) model, which provides an
intentional description of how each actor achieves its goals and soft goals. An element
is included in the SR model only if it is considered important enough to affect the
achievement of some goal. The SR model includes the SD model, so it describes
which actors may be able to accomplish something by themselves, or by depending
on other actors. It specifies goals, tasks, resources and soft goals linked by dependency
links from the SD model, task decomposition links, means-end links, and the
contributes-to-soft goal links (Chung et al. 2000). Figure 4 shows part of the SR
model for DMAN for the human Runway ATCO actor. This actor undertakes one
major task – control flight around the runway – that is decomposed into other tasks
such as issue line-up clearance and issue take-off clearance. The former task can be
further decomposed into sub-tasks and sub-goals which, if undertaken and achieved,
contribute negatively to the achievement of an important soft goal – that workload
should not be increased. Furthermore, to do the issue line-up clearance task, the
Runway ATCO depends on the resource flight information from the electronic flight
strip.
Figure 4. Part of a draft SR model for DMAN, showing elements for the Runway ATCo actor
and its dependency link with other actors.
We have developed REDEPEND to support i* modelling within RESCUE.
REDEPEND is a graphical modelling tool developed as a plug-in to Microsoft Visio
2002 that enables the team to construct and analyse i* SD and SR models (Maiden et
al. 2002).
This stream provides key inputs to the managing requirements and scenario-driven
walkthroughs. Goals and soft goals in i* SR models become requirements in the
managing requirements stream. Context and i* models define the system boundaries
essential for use case modelling and authoring. The i* SR models define goal and task
structures that suggest skeletal use case descriptions to refine the scenario-driven
walkthroughs stream.
Scenario-driven Walkthroughs
In this RESCUE stream the team writes use cases then generates and walks through
rich scenarios to discover and acquire stakeholder requirements that are complete,
precise and testable. It uses the research-based ART-SCENE environment, which
supports the automatic generation of scenarios from use case descriptions and
systematic scenario walkthroughs to discover, acquire and describe requirements. The
ART-SCENE environment was successfully to discover requirements for the CORA-2
system (Mavin & Maiden 2003). In this paper we focus on 2 out of the 5 sub-
processes.
The first sub-process is use case modelling (Jacobson et al. 2000) that we have
extended to model and investigate different system boundaries identified in the context
model. The outcome is a use case model with use cases and short descriptions that are
inputs into use case authoring. Figure 5 shows the DMAN use case diagram. It
specifies human actor roles and their associations with 13 use cases and one abstract
use case. The layout of the use cases, from top to bottom of the diagram, suggests a
simple ordering of the use case behaviour in the departure of one aircraft.
Figure 5: A draft use case diagram for DMAN.
In the second sub-process the team writes detailed use case descriptions using the
structured templates derived from use case best-practice (e.g. Cockburn 2000).
Authoring is guided using use case style and content guidelines from the CREWS-
ECRITOIRE method (Ben Achour et al. 1999), temporal semantics expressed as
action-ordering rules, and an extensive lexicon of ATM nouns and verbs elicited from
controllers. To write each description the team draw on outputs from the other streams
UC1 - Give the Departure Clearance
Dep Clearance ATCO
Runway ATCO
ATC Tower
Supervisor
Tower Dep
Seq ATCO
TMA Dep Coordinator
Ground ATCO
TMA Dep ATCO
TMA Tactical Flow Mgr
UC3: Give the Pushback Clearance
UC6: Manually Update the Departure Sequence
UC5: Monitor Taxiing Aircraft
UC7: Give Line-Up Clearance
UC4: Give the Taxi Clearance
UC2: Give the Start-Up Clearance
UC15: Investigate What-Ifs
UC8: Change the Runway Configuration
UC13: Stream Departures ready for Handover
UC9: Change the Runway Spacing Strategy
UC10: Fix the Runway Allocation Strategy
UC11: Plan de-icing
UC12: Change TMA Flow Constraint
activity models, i* strategic rationale models, stakeholder requirements, and
innovative design ideas from the creativity workshops. Once each use case description
is complete and agreed with the relevant stakeholders, the team produce a use case
specification from it, and parameterise it to generate scenarios automatically from each
description. Part of a use case description is shown in Figure 6.
UC9 Change the Runway Spacing Strategy
Date 16 October 2003
Source Stage 1 Document
Actors ATC Tower Supervisor, Tower Departure Sequencer ATCO, TMA Departure Co-ordinator, AMAN,
Tower Departure Sequencer ATCO (other airports), ATC Tower Supervisor (other airports), Tactical
Flow Manager.
Problem
Statement (now) Integrate runway spacing strategy into departure planning process
Triggering Event An imbalance between arrival and departure delay is predicted
Assumptions We assume that the runway spacing is defined by the number of take off and landing per hour for
each runway.
Successful End
States A time to implement new runway spacing is agreed by ATC Tower Supervisor and TMA Departure
Coordinator. The DMAN departure sequence takes into account the change in runway allocation.
Unsuccessful End
States DMAN departure plan does not allow for runway spacing change at the correct time.
Normal Course 1. The ATC Tower Supervisor looks at the predicted arrival delays in AMAN
2. The ATC Tower Supervisor looks at the predicted departure delays in DMAN
3. The ATC Tower Supervisor considers the predicted arrival and departure delays
4. The ATC Tower Supervisor decides that a different spacing strategy would be preferable.
5. Abstract Use Case 14(the ATC Tower Supervisor performs “What-Ifs” with DMAN)
6. The ATC Tower Supervisor contacts the TMA Departure Coordinator by telephone
7. The ATC Tower Supervisor states the proposed new runway spacing strategy.
8. The TMA Departure Coordinator agrees the new spacing strategy.
9. AMAN re-plans arrivals taking into account the new runway configuration
10. AMAN notifies DMAN that the re-planning of arrivals is complete
11. CALL UC6 (DMAN Updates the Departure Sequence) for this airport.
Figure 6. Part of a draft DMAN use case description for UC9: Change the runway spacing
strategy.
Managing Requirements
In this fourth RESCUE stream the project team documents, manages and analyses
requirements generated from the other 3 streams automation and process
requirements emerging from human activity modelling, system actor goals and soft
goals from i* system modelling, and requirements arising from scenario
walkthroughs.
Each requirement is documented using the VOLERE shell (Robertson & Robertson
1999), a requirement-attribute structure that guides the team to make each requirement
testable according to its type. Use cases and scenarios are essential to making
requirements testable. Each new requirement is specified either for the whole system,
one or more use cases of that system, or one or more actions in a use case. This
RESCUE requirement structure links requirements to and places them in use cases and
use case actions “in context”, thus making it much easier to a write a measurable fit
criterion for each requirement. Figure 7 shows a fragment of UC3 Give the
pushback clearance – containing 2 use case actions and 3 DMAN requirements linked
to those actions.
1. The pilot calls the Ground ATCo and requests pushback..
UR4: DMAN shall allow all controllers to retain their flexibility in their operational
procedures.
FR20: The DMAN sequencing shall take into account inbound traffic for planning the off-
block time.
2. The Ground ATCo looks for the flight information on the controller display
IR1: The DMAN display shall be synchronised with the EFPS (Electronic flight strips).
Figure 7. Fragment of the draft DMAN Requirements Document, showing 2 use case actions
and 3 linked requirements.
RESCUE requirements are documented using Rational’s Requisite Pro. Outputs from
other streams, such as use case, context and i* models, are also included in the
document. We have implemented workarounds with Requisite Pro to support the
complex use case and requirements structures within RESCUE and provide the
essential rich traceability for each requirement.
4. Synchronisation Checking
Work and deliverables from RESCUE’s 4 streams are coordinated at 5 key
synchronisation points at the end of the 5 stages shown in Figure 1, implemented as
one or more workshops with deliverables to be signed off by stakeholder
representatives:
1. The boundaries point, where the team establishes first-cut system boundaries
and undertakes creative thinking to investigate these boundaries;
2. The work allocation point, where the team allocate functions between actors
according to boundaries, and describe interaction and dependencies between these
actors;
3. The generation point, where required actor goals, tasks and resources are
elaborated and modelled, and scenarios are generated;
4. The coverage point, where stakeholders have walked through scenarios discover
and express all requirements so that they are testable;
5. The consequences point, where stakeholders undertake walkthroughs of the
scenarios and system models to explore impacts of implementing the system as
specified on its environment.
The synchronisation checks applied at these 5 points are designed using a RESCUE
meta-model of human activity, use case and i* modelling concepts constructed
specifically to design the synchronisation checks. It is shown in simplified form in
Figure 8 – the darker horizontal lines define the baseline concept mappings across the
different models used in RESCUE. In simple terms, the meta-model maps actor goals
in human activity models to requirements in use case descriptions and i* goals and
soft goals. Likewise, human activities map to use cases, and human actions to use
case actions that involve human actors in use cases and tasks undertaken by human
actors in i* models. Human activity resources map to i* resources and objects
manipulated in use case actions, and actors in all 3 types of model are mapped. The
complete meta-model is more refined. Types and attributes are applied to constrain
possible mappings, for example use case descriptions and i* models describe system
actors, however only human actors in these models can be mapped to actors in human
activity models.
Figure 8. RESCUE concept meta-model as a UML class diagram showing mappings between
constructs in the 3 model types.
This paper reports the application of synchronisation checks at the first 2 stages, so it
describes them in more detail. At Stage 1, data about human activities and the
extended context model are used to check the completeness and correctness of the use
case model. Use case summaries are used to check system-level requirements. Checks
are:
Check 1.1 Every major human activity (e.g. applying resolutions) should correspond to one or
more use cases in the use case model.
Check 1.2 Every actor identified in human activity modelling is a candidate actor for the context
model.
Check 1.3 Every adjacent actor (at levels 2, 3 or 4 of the context model) that communicates
directly with the technical system (level 1 in the context model) should appear as an
actor in the use case diagram.
Check 1.4 The system boundary in the use case diagram should be the same as the boundary
between levels 1 and 2 in the context model.
Check 1.5 Services and functions related to use cases in the use case model should map to system
level requirements, i.e. high-level functional and non-functional requirements, in the
requirement database.
Use case
1
m
0..1
1..2
Requirement
0..m
0..m
0..m
0..m
0..1
0..m
Goal/Soft goal
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
0..m
Depends on
Decomposes
into
Contributes
to
Goal
Human activity model Use case description i* system model
Action
Actor
Task
Actor
Activity
Action
Actor
Resource
Object
Resource
At Stage 2, most cross checking is done in order to bring the human activity and first-
cut i* models to bear on the development of correct and complete use case
descriptions. Checks are:
Check 2.1 Actors, resources, goals, actions and resource management strategies identified in
activity modelling should be represented in the i* SD and SR models as appropriate.
Check 2.2 Actors, resources, goals, actions, differences due to variations, and differences due
to contextual features in the activity models should appear in relevant use case
descriptions.
Check 2.3 Goals identified in the activity models should be reflected in the system and use
case-level requirements in the requirement database
Check 2.4 All external actors in the i* SD model should correspond to actors in the use case
descriptions.
Check 2.5.1 Each low level task (i.e. each task that is not decomposed into further lower-level
tasks) undertaken by an actor in the i* SR model, should correspond to one or more
actions in a use case description.
Check 2.5.2 Each resource used in, or produced from, a task in the i* SR model should be
described in a use case description.
Check 2.5.3 Ensure that dependencies modelled in the i* models are respected in the use case
descriptions, in particular:
For goal and soft goal dependencies, the dependee must first produce whatever
is needed for the depender to achieve the goal or soft goal;
For resource dependencies, the dependee must first produce the resource that
the depender needs in order for the depender to be able to use it;
For task dependencies, the dependee must first make available whatever the
depender needs in order for the depender to be able to do the task, perhaps via
communication.
Check 2.6 All goals and soft-goals to be achieved by the future system according to the i* SR
model should be specified in the system requirements specification and stored in the
requirements database.
Check 2.7 All requirements associated with a use case in the use case template should be
expressed in the system requirements specification and stored in the requirements
database.
These synchronisation checks have so far been applied in first 2 stages of DMAN, as
described in the remainder of this paper.
5. DMAN Case Study
The RESCUE process was applied to specify the operational requirements for DMAN,
Eurocontrol’s new system for scheduling and managing departures from major
European airports. DMAN is a complex socio-technical system involving a range of
human actors including tower controllers and aircraft pilots, interacting with other
computer-based systems related to both airport and air movements, and supporting
aircraft movement from push back from the gate to take off from the runway. The
project was led by the UK’s National Air Traffic Service (NATS) and involved
participants from Centre d'Etudes de la Navigation Aerienne (CENA) and City
University’s RESCUE experts. The DMAN team was composed of 2 systems
engineers employed by NATS and CENA and one RESCUE team member from City.
It also worked with 4 UK and 4 French air traffic controllers who were seconded to the
project, other NATS and CENA engineers, and software engineering academics. At the
beginning of the project the City experts trained 5 NATS and CENA engineers,
including the 2 in the DMAN team, in the RESCUE process using presentations and
exercises. There were two days training on i* system modelling, two days on use
cases, scenarios and requirements management, and one day on human activity
modelling.
The project started in February 2003 and was timetabled to take 9 months to produce
DMAN’s operational requirements document. Stages 2 and 3 were completed in
September 2003, with stage 4 scenario walkthroughs taking place in October and
November 2003. Stage 2 deliverables included a human activity model describing how
UK controllers at Heathrow currently manage the departure of aircraft, a DMAN use
case model and use case descriptions, system-level requirements, and some i* SD and
SR models for DMAN. The human activity model was divided into 15 scenarios
describing controller work, reported in a 50-page deliverable. The use case model
contained 8 actors and 15 use cases. Each use case contained, on average, 13 normal
course actions and 3 variations to the normal course behaviour. The majority of these
use case actions were human actions or actions involving interaction with DMAN and
other computer-based systems, rather than system actions. The i* SD model specified
15 actors with 46 dependencies between these 15 actors. The SR model was more
complex, with a total of 103 model elements describing 7 of the 15 actors defined in
the SD model.
Stage 2 RESCUE deliverables were developed in parallel based on signed off
deliverables from stage 1 of the RESCUE process by staff with the relevant available
resources and expertise. The human activity model was developed primarily by City
staff, the use case model and descriptions by NATS staff, and the i* models by CENA
staff. Throughout stage 2 all staff had access to intermediate versions of the models
under development elsewhere in the project. Therefore, synchronisation checks were
needed at the end of stage 2 to detect omissions, ambiguities and inconsistencies in the
requirements models that arose in spite of regular communication between partners.
The RESCUE stage 2 synchronisation checks were described in the previous section.
In DMAN, all/which rules were applied by the RESCUE quality gatekeeper, one
member of City staff responsible for maintaining the DMAN requirements repository
and validating inputs to it. The synchronisation checks took the gatekeeper
approximately 8 days of full-time work to apply. Results were documented using pre-
designed tables with issues and action lists that were reported to DMAN team
members to resolve.
Results from the synchronisation checks
Table 1 summarises the number of checks applied, issues arising, and actions
resulting from the checks. Furthermore check 2.0, that verifies that the i* SR model
is consistent with its originating SD model, led to 19 additional issues to be resolved
– mostly SD elements and dependency links that were missing from the SR model.
Likewise, other within-stream checks, such as verifying all use case descriptions
against the originating use case model were undertaken. In the remainder of this paper
we focus on the more interesting results arising from the model synchronisation
checks across the streams.
Table 1 shows that the synchronisation checks generated very different numbers and
types of issue and actions for the team to resolve. Three checks – 1.3, 2.4 and 2.5.3 -
generated nearly 92% of all identified issues. In contrast, Checks 1.5, 2.3 2.6 and 2.7
were not applied due to the model-driven approach adopted by the DMAN team –
rather than establish VOLERE requirements at the same time as the models, the team
chose to derive such requirements from the models at the end of stage 3, hence there
were no requirements in the data base to check against. Check 2.1 was also not applied
in Stage 2 due to lack of resources. The check verifies the human activity and i*
models – given the importance of scenarios in RESCUE, resources were focused on
verifying the use case descriptions against other models.
Check ID Total issues
arising Issues and actions for RESCUE models
Check 1.1 3 Activities without use cases, no action required.
Check 1.2 4 Actors missing from context model, no action required.
Check 1.3 21 Missing actors and actor links in use case model, incorrect actor
naming, needs changes.
Check 1.4 0 No issues arising between context and use case model.
Check 1.5 0 No system-level requirements.
Check 2.1 - Not applied yet – reason explained in text.
Check 2.2 1 Ambiguity detected, needs changes.
Check 2.3 0 No use case-level requirements.
Check 2.4 37 Omitted actors from use case descriptions, needs changes.
Check 2.5.1 5 Omissions from use case descriptions, needs changes.
Check 2.5.2 0 All resources included.
Check 2.5.3 55 Ambiguities needing clarification, missing use case elements,
dependencies between use cases discovered, use case
decomposition needed, action ordering wrong, missing non-
functional requirements, needs changes.
Check 2.6 0 No use case-level requirements.
Check 2.7 0 No use case-level requirements.
Table 1. Quantitative summary of synchronisation checks applied to RESCUE models arising
from stages 1 and 2.
Synchronisation with the human activity model was verified using checks 1.1, 1.2 and
2.2. Check 1.1 revealed 3 current human activities that were not included in a DMAN
use case – subsequent analysis revealed that these activities were not part of the
DMAN socio-technical system, and no model changes were needed, and the rationale
for this was documented. Likewise, check 1.3 revealed that 4 human actor roles
missing from the context model were no longer roles in the new DMAN system, and
no changes were made to the model. Check 2.2 verified whether contextual features in
the human activity model had been included in the use case descriptions, and one issue
arose. The activity model revealed the importance of removing flights completely
from the departure sequence – activities without responding use cases and actions in
the use case description. The issue led to a pending change to the use case model.
A retrospective interview with the NATS engineer responsible for writing the use case
descriptions revealed the use of human activity models to write the use case
descriptions, in particular to identify all relevant actors and actors. In contrast, other
activity model concepts were less useful. The model would be more useful if it
provided more information on some activities (e.g. how controllers handle the flight
strips) at the expense of others (e.g. how controllers use the radios). He also reported
that activity model constraints can provide direct inputs to discovering system
requirements for DMAN.
Check 1.3, verifying that actors in the context model are also specified in the use case
model, revealed 21 issues to synchronise. Of these 21 issues, 2 were discrepancies in
actor names, 13 were missing links between the actor and the use case, and 6 actors
were missing from the use case diagram. A pattern emerged. All but one of the
missing actors were external software systems (e.g. FDPS and A-SMGCS) while the
missing links were with human actors such as Ground ATCO. This was because of a
decision to simplify the stage 1 use case model to only show primary rather than
secondary actors on the use case diagram. One consequence from this decision is the
result of check 2.4, which identified 37 actors that were missing from the use case
descriptions. During the retrospective interview, the NATS systems engineer reported
that use case descriptions provided effective mechanisms for describing detailed
interaction, but at the expense of structure (“it’s always hard to see both the wood and
the trees”). New mechanisms to show the overall structure of an individual use case
were needed.
Checks 2.5.1 to 2.5.3 verified the use case descriptions against the i* models. Check
2.5.2 revealed no missing resources from the use case descriptions. Check 2.5.1
identified 5 SR model tasks undertaken by actors that are not described in any use case
description. The tasks Departure Clearance ATCO, Ground ATCO and Runway all
respect the CTOT, the Runway ATCO issues takeoff clearance, and Tower Departure
Sequencer ATCO gets discrepancy between capacity and departure demand lacked
corresponding actions in the use cases, suggesting omissions and further actions to
synchronise the use case descriptions and i* models.
Check 2.5.3, which investigates whether use case descriptions respect i* model
dependencies, revealed 55 important issues to resolve in the RESCUE models.
Furthermore, only 14 of the total of 69 checks did not raise an issue, suggesting that
check 2.5.3 is more useful to apply than other checks. Table 2 describes the different
types of issues and their frequency of occurrence that arose from applying check 2.5.3.
Types of issues arising from application of Check 2.5.3 Total instances of
occurrence
Checks resulting in no issue or change 14
Potential ambiguities requiring clarification and resolution 18
Actors and/or actors missing from use case description 17
Important dependencies between use cases discovered 6
Other elements missing from use case description 5
Error or inconsistent data in the use case description 2
Use case and use case description missing 2
Soft goals or non-functional requirements missing from use case 2
General ambiguity identified in the use case 1
Potential decomposition of a use case and its description needed 1
Actions in use case description in the wrong order 1
Table 2. Total instance of different types of result arising from applying Check 2.5.3.
Most of the 18 potential ambiguities arose from i* dependencies that require a specific
ordering of actions both within and across use cases. Each ambiguity gave rise to a
potential inconsistency that might arise due to un-stated assumption about the DMAN
system. For example, the i* models specified that the Ground ATCo depends on
DMAN to undertake the task Check MOBT (measured off-block time), and DMAN
must update the MOBT. Use case UC3 specifies 2 actions: (2) The Ground ATCO
looks for the flight information on the DMAN display: (3) The Ground ATCO checks
that the status of the flight in DMAN is ‘OK to Push’. The two dependencies are true
if we assume that MOBT information is provided by DMAN and is included in the
check undertake by the ATCO. The resulting action was to establish and document the
underlying domain assumption and, where necessary, change one or more of the
models.
The check also revealed 17 cases of actor actions missing from the use case
descriptions. For example, the i* models specified that the Runway ATCO (an actor
in many use cases) depends on the Tower Departure Sequencer (TDS) ATCO to have
the departure sequence followed and updated, which in turn depends on the TDS ATCO
planning the departure sequence. However, no actions in which the TDS ATCO plans
the departure sequence are specified in the use case descriptions. Other use case
elements were also missing, for example, the i* models specified that DMAN depends
on the Ground ATCO to achieve the goal of ready status updated, which in turn
depends on the Ground ATCO doing the task forward ready status, but no actions
corresponding to the task were specified in the use case descriptions. In 2 cases, these
dependencies revealed a possible missing use case – an actor uses DMAN to evaluate
capacity and demand.
Finally, the check revealed potentially important dependencies between use cases that
were not explicitly identified beforehand. Again, consider one of the simpler examples.
The i* models specified that the TMA Departure ATCO depends on the Runway
ATCO to do the task control flight after takeoff (referred to here as task T1), which in
turn depends on the Runway ATCO doing the task transfer flight to TMA Departure
ATCO (referred to as task T2). Task T1 maps to action-7 in UC7, and task T2 maps
to action-6 in UC13. This reveals an implied dependency between UC7 and UC13, and
that action-6 in UC13 shall happen before action-7 in UC7. From this and 5 other
similar dependencies, we have produced a simple model showing previously un-stated
dependencies between DMAN use cases that have important implications for the
timing and order of actor behaviour in the future DMAN system.
Furthermore, more application of synchronisation check 2.5.3 is still possible. At the
time of writing, the DMAN specification includes 23 dependencies between i* SR
actor models that could not be checked due to incomplete elaboration of i* SR models
for all actors, and 16 of these dependencies were specific to the central DMAN system
actor. We will be exploring these dependencies and generating further issues and
actions for the DMAN project team.
Case Study Conclusions
The DMAN requirements process is continuing, but it has enabled us to investigate
and report the effectiveness of RESCUE and some of its model synchronisation checks
on a real and complex project. Several key findings emerge. Systems engineers with
the pre-requisite training are able to apply advanced modelling techniques such as i* to
model complex socio-technical systems, and these models do provide new and useful
insights. In spite of this success, further method engineering work is needed to
support the development of scaleable i* models. For example, constructing a single
SR models specifying all actors and their dependencies is very difficult due to number
and nature of these dependencies.
In the use case descriptions, the systems engineers provided more specification of
human actor behaviour rather than system actor behaviour, perhaps due to the focus of
socio-technical systems in RESCUE. Furthermore, to our surprise, very few system-
level requirement statements were specified in the first 2 stages – instead the engineers
were satisfied to develop and agree requirements models in the form of use case
descriptions and i* models from which approximately 120 requirement statements
have subsequently been derived.
The RESCUE synchronisation checks required resources to apply, due primarily to the
degree of human interpretation of the models needed. Furthermore, some
synchronisation checks were more effective than others at revealing insights into the
DMAN specification. Synchronisation checks often resulted in further knowledge
elicitation and document (specification of the ‘world’ in REVEAL terms) to resolve
potential model ambiguities. Finally, synchronisation checks appeared to fall into 2
basic types: (i) synchronisation of models based on their first-order properties often
related to naming conventions (e.g. check 1.3), and: (ii) synchronisation of models
based on their derived properties, such as in check 2.5.3, which leads to in-depth
verification of the use case descriptions using i* actor and element dependencies. These
latter types of checks appear to be more useful to the engineers.
6. Discussions and Future Work
This paper describes intermediate results from an industrial case study that applied and
integrated established and research requirements modelling techniques to a complex
socio-technical system in air traffic management. It reports 2 major innovations:
1. New requirements modelling techniques namely i*, with simple process
extensions, can be applied effectively to model socio-technical systems;
2. The analysis of these models combined in the RESCUE stream and
synchronisation structure shown in Figure 1 revealed important insights that are
unlikely to have been obtained using other modelling techniques.
Most research-based requirements engineering techniques have been developed in
isolation. Our results, although preliminary, suggest that there are benefits from
extending current and designing future techniques to integrate with established ones.
Conceptual meta-models, such as the RESCUE meta-model in Figure 8, provide one
foundation for model synchronisation, but more research in method engineering is
needed to design integrated techniques for process guidance (which models to develop
in what order), model synchronisation (which checks to do when) and model
integration (when is one integrated model preferable to several different models). A
good example of method integration emerging from the DMAN experience is the use
case dependency model generated as a result of applying check 2.5.3.
This DMAN case study also has implications for the multi-disciplinary requirements
and design teams advocated by other authors (e.g. Viller & Sommerville 1999 for the
ATM domain). The DMAN team was composed of engineers with systems and
software rather than human factors backgrounds, and yet adequate training and
methodology enabled the production of human activity models that effectively
underpinned the development and analysis of the system models and were praised by
the client.
Future research will refine and formalise the specification of the synchronisation
checks, with a view towards introducing software tool support for model
synchronisation. Given the need for human interpretation, we believe that software
tools will be limited to detecting and ranking candidate issues in pairs of models –
issues that engineers with considerable domain expertise will still have to resolve. In
this sense, we view our work as different to ongoing research of viewpoints (e.g.
Nuseibeh et al. 2003) and inconsistency management (e.g. Nentwich et al. 2003).,
that is increasing formal specification of system requirements and automation of
development processes. The advantage of RESCUE here is that it implements existing
and tried-and-tested modelling techniques, limited between-model synchronisation
based on simple concept meta-models and types, and guided synchronisation strategies
for engineers to adopt.
7. Acknowledgements
The authors acknowledge the support from Eurocontrol, NATS and Sofeavia/CENA in
the DMAN project.
8. References
Ben Achour C., Rolland C., Maiden N.A.M. & Souveyet C., 1999, 'Natural Language
Studies on Use Case Authoring', Proceedings 4th IEEE Symposium on Requirements
Engineering, IEEE Computer Society Press, 36-43.
Chung L., Nixon B., Yu E. and Mylopoulos J., 2000, ‘Non-Functional Requirements in
Software Engineering’, Kluwer Academic Publishers.
Cockburn A., 2000, ‘Writing Effective Use Cases’, Addison-Wesley Pearson Education.
De Landtsheer R., Letier E. & van Laamsweerde A., 2003, ‘Deriving Tabular Event-Based
Specifications from Goal-Oriented Requirements Models’, Proceedings 11th IEEE
International Conference on Requirements Engineering, IEEE Computer Society Press,
200-210.
Hall J., Jackson M., Laney R., Nuseibeh B. & Rapanotti L., 2002, ‘Relating Software
Requirements and Architectures using Problem Frames’, Proceedings 10th International
Joint Conference on Requirements Engineering’, IEEE Computer Society Press, 137-144.
ICAO, 1994, ‘Human Factors in CNS/ATM systems. The development of human-centred
automation and advanced technology in future aviation systems’ ICAO Circular 249-
AN/149.
Jacobson I., Booch G. & Rumbaugh J., 2000, ‘The Unified Software Development
Process’, Addison-Wesley.
Leveson N, de Villepin M., Srinivasan J., Daouk M., Neogi N., Bachelder E, Bellingham
J., Pilon N. & Flynn G., 2001, ‘A Safety and Human-Centred Approach to Developing
New Air Traffic Management Tools’, Proceedings Fourth USA/Europe Air Traffic
Management R&D Seminar.
Liu L., Yu E. & Mylopoulos J., 2003, ‘Security and Privacy Requirements Analysis within a
Social Setting’, Proceedings 11th IEEE International Conference on Requirements
Engineering, IEEE Computer Society Press, 151-161.
Liu L. & Yu E., 2001, ‘From Requirements to Architectural Design – Using Goals and
Scenarios’, Proceedings first STRAW workshop, 22-30.
Maiden N. & Gizikis A., 2001, ‘Where Do Requirements Come From?”, IEEE Software
September/October 2001 18(4), 10-12.
Maiden N.A.M., Jones S.V. & Flynn M., 2003, 'Innovative Requirements Engineering
Applied to ATM', Proceedings ATM (Air Traffic Management) 2003, Budapest, June 23-
27 2003.
Mavin A. & Maiden N.A.M., 2003, ‘Determining Socio-Technical Systems Requirements:
Experiences with Generating and Walking Through Scenarios’, Proceedings 11th
International Conference on Requirements Engineering, IEEE Computer Society Press,
213-222.
Maiden N.A.M. & Rugg G., 1996, 'ACRE: Selecting Methods For Requirements
Acquisition, Software Engineering Journal 11(3), 183-192.
Maiden N.A.M., Jones S.V. & Flynn M., 2003, 'Integrating RE Methods to Support Use
Case Based Requirements Specification', Poster paper, Proceedings 11th International
Conference on Requirements Engineering, IEEE Computer Society Press, 369-370.
Nentwich C., Emmerich W. & Finkelstein A.C.W, 2003, ‘Flexible Consistency Checking’,
ACM Transactions on Software Engineering and Methodology 12(1), 28-63.
Nuseibeh B., Kramer J., & Finkelstein A.C.W., 2003, ‘Viewpoints: Meaningful
Relationships are Difficult’, Proceedings 25th IEEE International Conference on Software
Engineering, IEEE Computer Society Press, 676-681.
Nuseibeh B., Kramer J., & Finkelstein A.C.W., 1994, 'Expressing the Relationship
Between Multiple Views in Requirements Specifications', IEEE Transactions on Software
Engineering 20(10), 760-773.
Praxis, 2001, ‘REVEAL: A Keystone of Modern Systems Engineering’, White Paper
Reference S.P0544.19.1, Praxis Critical Systems Limited, July 2001.
Robertson S. & Robertson J., 1999, ‘Mastering the Requirements Process’, Addison-
Wesley.
Rumbaugh J., Jacobson I. & Booch G., 1998, ‘The Unified Modelling Language Reference
Manual’, Addison-Wesley.
Santander V. & Castro J, 2002, ‘Deriving Use Cases from Organisational Modeling’,
Proceedings IEEE Joint International Conference on Requirements Engineering (RE’02),
IEEE Computer Society Press, 32-39.
Sutcliffe A.G., Maiden N.A.M., Minocha S. & Manuel D., 1998, 'Supporting Scenario-
Based Requirements Engineering', IEEE Transactions on Software Engineering, 24(12),
1072-1088.
Vicente, K., Cognitive work analysis, Lawrence Erlbaum Associates, 1999.
Viller S. & Sommerville I., 1999, ‘Social Analysis in the Requirements Engineering
Process: from Ethnography to Method’, Proceedings 4th IEEE International Symposium
on Requirements Engineering, IEEE Computer Society Press, 6.13.
Wright P., Dearden A. & Fields R., 2000, ‘Function Allocation: A Perspective from Studies
of Work Practice’, International Journal of Human-Computer Studies 52(2), 335-355.
... They can be used for communication among stakeholders (i.e., when they express high-level specifications), for analytical tasks such as finding inconsistency and detecting feasibility, or for serving the entire software development process. As a first step within the development process, an analyst refines an initial set of high-level requirements into lower-level specifications and may use conceptual models as an artifact that represents the major entities and relationships that are referred to in the high-level requirements [18,29,42]. In this work, we limit our attention to static/structural conceptual models that emphasize the domain entities and their relationships. ...
... Conceptual models can help refine an initial set of high-level requirements into lower-level specifications, by representing the major entities and relationships that are referred to in the high-level requirements [18,29,42]. Several researchers have investigated the derivation of such models from use cases. ...
Chapter
Full-text available
[Context and motivation] Notations for expressing requirements are often proposed without explicit consideration of their suitability for specific tasks. Consequently, practitioners may choose a sub-optimal notation, thereby affecting task performance. [Question/problem] We investigate the adequacy of two well-known notations: use cases and user stories, as a starting point for the manual derivation of a static conceptual model. In particular, we examine the completeness and correctness of the derived conceptual model. [Principal ideas/results] We conducted a two-factor, two-treatment controlled experiment with 118 subjects. The results indicate that for deriving conceptual models, user stories fit better than use cases. It seems that the repetitions in user stories and their conciseness contribute to these results. [Contribution] The paper calls for evaluating requirements notations in the context of various requirements engineering tasks and for providing evidence regarding the aspects that need to be taken into account when selecting a requirement notation.
... Maiden et al. [24][25][26], have presented several case studies in the Air Traffic Management (ATM) domain to validate RESCUE, a scenario-driven requirements engineering process. In the studies, the authors ran several creativity workshops with ATM experts with different expertise to study how RESCUE helps to discover stakeholder and system requirements. ...
... Eliciting the evolution of requirements, hence, is problematic and should be an iterative process with the essential work amount. Although there exist empirical studies on this issue such as the work by Herrmann et al. [23] and Maiden et al. [24][25][26], it would be promising to run empirical studies on different subjects of users (such as experts in a specific domain, or requirement analysts and more) to understand to which level of abstraction and completeness that requirements evolution could be produced. ...
Chapter
Full-text available
Over the past three years, our groups at the University of Leuven and the University of Trento have been conducting a number of experimental studies. In particular, two common themes can be easily identified within our work. First, we have investigated the value of several threat modeling and risk assessment techniques. The second theme relates to the problem of preserving security over time, i.e., security evolution. Although the empirical results obtained in our studies are interesting on their own, the main goal of this chapter is to share our experience. The objective is to provide useful, hands-on insight on this type of research work so that the work of other researchers in the community would be facilitated. The contribution of this chapter is the discussion of the challenges we faced during our experimental work. Contextually, we also outline those solutions that worked out in our studies and could be reused in the field by other studies.
... According to different theoretical structures, these methods can be generally divided into two categories [5,6], i.e., the model-driven methods and the data-driven methods. e former category is based on mathematical theory, which uses a small amount of data samples to determine model parameters. ...
Article
Full-text available
The recent proposed Spatial-Temporal Residual Network (ST-ResNet) model is an effective tool to extract both spatial and temporal characteristics and has been successfully applied to urban traffic status prediction. However, the ST-ResNet model only extracts the local spatial characteristics and ignores the very important global spatial characteristics. In this paper, a novel Global-Local Spatial-Temporal Residual Correlation Network (GL-STRCN) model is proposed for urban traffic status prediction to further improve the prediction accuracy of the existing ST-ResNet model. The GL-STRCN model firstly applies Pearson’s correlation coefficient method to extract high correlation series. Then, considering both global and local spatial properties, two components consisting of 2D convolution and residual operation are used to capture spatial features. After that, based on Long Short-Term Memory (LSTM) or Gated Recurrent Unit (GRU), a novel long-term temporal feature extraction component is proposed to capture temporal features. Finally, the spatial and temporal features are aggregated together in a weighted way for final prediction. Experiments have also been performed using two datasets from TaxiCD and PEMS-BAY. The results indicated that the proposed model produces a better prediction performance compared with the results based on other baseline solutions, e.g., CNN, ST-ResNet, GL-TCN, and DGLSTNet.
... More constrained notations may be useful for analytical tasks such as finding inconsistencies [10], or when the requirements are a starting point for model-driven development [11]. We focus on the task of refining high-level, user requirements 1 through the construction of a conceptual model that represents the major entities, and relationships that are referred to in the requirements [11][12][13]. A conceptual model [14] can be seen as a collection of statements, often represented via a graphical model [15], that specify a given domain. ...
Article
Full-text available
Context: There are numerous textual notations and techniques that can be used in requirements engineering. Currently, practitioners make a choice without having scientific evidence regarding their suitability for given tasks. This uninformed choice may affect task performance. Objective: In this research, we investigate the adequacy of two well-known notations: use cases and user stories, as a starting point for the manual derivation of a structural conceptual model that represents the domain of the system. We also examine other factors that may affect the performance of this task. Methods: This work relies on two experiments. The first is a controlled classroom experiment. The second one is a quasi-experiment, conducted over multiple weeks, that aims at evaluating the quality of the derived conceptual model in light of the notation used, the adopted derivation process, and the complexity of the system to be. We measure quality in terms of validity and completeness of the conceptual model. Results: The results of the controlled experiment indicate that, for deriving conceptual models, user stories fit better than use cases. Yet, the second experiment indicates that the quality of the derived conceptual models is affected mainly by the derivation process and by the complexity of the case rather than the notation used. Contribution: We present evidence that the task of deriving a conceptual model is affected significantly by additional factors other than requirements notations. Furthermore, we propose implications and hypotheses that pave the way for further studies that compare alternative notations for the same task as well as for other tasks. Practitioners may use our findings to analyze the factors that affect the quality of the conceptual model when choosing a requirements notation and an elicitation technique that best fit their needs.
... One of the widely used requirements analysis approaches is the modeldriven methodology, which provides a clear understanding of the system as well as an easy transformation into different types of software artifacts. To date, many researchers [1][2][3][4][5][6][7][8][9] have proposed various methods for model-driven requirements analysis. For example, Piras et al. [7] proposed Agon framework, which uses a multi-layer meta-model that represents the knowledge of gamification to analyze acceptance requirements. ...
Article
Full-text available
Modeling of natural language requirements, especially for a large system, can take a significant amount of effort and time. Many automated model-driven approaches partially address this problem. However, the application of state-of-the-art neural network architectures to automated model element identification tasks has not been studied. In this paper, we perform an empirical study on automatic model elements identification for component state transition models from use case documents. We analyzed four different neural network architectures: feed forward neural network, convolutional neural network, recurrent neural network (RNN) with long short-term memory, and RNN with gated recurrent unit (GRU), and the trade-offs among them using six use case documents. We analyzed the effect of factors such as types of splitting, types of predictions, types of designs, and types of annotations on performance of neural networks. The results of neural networks on the test and unseen data showed that RNN with GRU is the most effective neural network architecture. However, the factors that result in effective predictions of neural networks are dependent on the type of the model element.
... The separation of requirement from context in B-SCP, in line with the precepts of problem frames [17], has clarified and simplified goal modeling. Comprehension and as such scalability of i* was a problem as noted in [29] that the authors had to convert the models into simple text in order for their stakeholders to understand. ...
Chapter
[Context and Motivation] User stories are a popular notation for representing requirements, especially in agile development. Although they represent a cornerstone for developing systems, limited research exists on how user stories are refined into conceptual design. [Question/Problem] We study the process of deriving conceptual models from user stories, which is at the basis of information systems development. We focus our attention on the derivation of a holistic view of structural and interaction aspects, represented via class diagrams and use case diagrams, respectively. In this paper, we examine whether providing guidelines has an effect on the ability of humans to derive complete and valid conceptual models. [Principal Ideas/Results] We design example-based guidelines for the derivation of class and use case diagrams from user stories. Then, we conduct a two-factor, two-treatment controlled experiment with 77 undergraduate students serving as subjects. The results indicate that the guidelines improve the completeness and validity of the conceptual models in cases of medium complexity, although the subjects were neutral on the usefulness of the guidelines. [Contribution] The guidelines may assist analysts in the refinement of user stories. Our initial evidence, besides showing how the guidelines can help junior analysts derive high-quality conceptual models, opens the doors for further studies on the refinement of user stories, and to the investigation of alternative guidelines.KeywordsRequirements engineeringConceptual modelingUse casesDerivation processGuidelinesClass diagramUser storiesControlled experiment
Chapter
[Context and motivation] Creating a shared understanding of requirements between all parties involved about a future software system is difficult. Imprecise communication can lead to misunderstanding of requirements. Vision videos demonstrate and visualize the functionality, use and impact of a software system before the actual development process starts. They stimulate discussions about the software system and its associated requirements. [Question/problem] Vision videos should be produced with as little effort as possible, in terms of resources and time consumption, yet with sufficient quality. This raises the questions: Does the presentation of a vision video influence its perception by the audience? Do animated vision videos offer an alternative to real videos to communicate a vision? [Principal ideas/results] We conducted an experiment with 20 participants comparing animated and real videos showing the same content. The videos illustrate the population decrease in rural areas and envision a possible solution to counteract the consequences of grocery store closings. The participants suggested own solutions for the problem of grocery store closings, rated the videos and chose their preferred type of video representation. The results of the experiment show no difference in neither the amount of solutions proposed nor the rating of the videos. Likewise, the results show no difference in the preferred type of video representation. [Contribution] Our study indicates that animated vision videos offer an adequate alternative to real videos. Thus, vision video producers have another viable option to choose for achieving a shared understanding of a future software system.
Conference Paper
[Context and motivation] Choreographies are a form of service composition in which partner services interact in a global scenario without a single point of control. The absence of an explicitly specified orchestration requires changes to requirements practices to recognize the need to optimize software services choreography and monitoring for satisfaction with system requirements. [Question/problem] We developed a requirements-led approach that aims to provide tools and processes to transform requirements expressed on service-based systems to QoS-aware choreography specifications. [Principal ideas/results] The approach is used by domain experts to specify natural language requirements on a service-based system, and by choreography designers to adapt their models to satisfy requirements more effectively. Non-functional requirements are mapped to BPMN choreography diagrams as quality properties, using the Q4BPMN notation, that support analysis and monitoring facilities. [Contribution] We report the new integrated approach and provide lessons learned from applying it to a real-world example of dynamic taxi management.
Article
Full-text available
1 Abstract This paper describes a safety-driven, human-centered process for designing and integrating new components into an airspace management system. The general design of a conflict detection function currently being evaluated by Eurocontrol is being used as the testbed for the methodology, although the details differ somewhat. The development and evaluation approach proposed is based on the principle that critical properties must be designed into a system from the start. As a result, our methodology integrates safety analysis, functional decomposition and allocation, and human factors from the very beginning of the system development process. It also emphasizes using both formal and informal modeling to accumulate the information needed to make tradeoff decisions and ensure that desired system qualities are satisfied early in the design process when changes are easier and less costly. The formal modeling language was designed with readability as a primary criterion and therefore the models can act as an unambiguous communication medium among the developers and implementers. The methodology is supported by a new specification structuring approach, called Intent Specifications, that supports traceability and documentation of design rationale as the development process proceeds. 2 Introduction The current Air Traffic Control systems have proven over time to be very safe. This high safety level can be attributed to a variety of factors, all of which are important: a high level of professionalism in the ATC work force, designed-in redundancy and mutual checking, large error margins (e.g., in the separation criteria for aircraft), and loose coupling (so that errors are contained and do not propagate rapidly throughout the various components). The li * mits of such a conservative system, however, along with growing demand for increased system capacity are leading to the introduction of new automation.
Article
Full-text available
RESCUE is an innovative and multi-disciplinary process for specifying requirements for the complex socio-technical systems found in ATM. It supports 4 concurrent process streams - human activity modeling, system modeling, scenario-driven walkthroughs and managing requirements. RESCUE integrates these streams using synchronisation stages to cross check models from each stream, ensure that these models are shared between the 4 streams, and support decision-making about system requirements and designs. It draws on established research in different disciplines to support the 4 streams. RESCUE was applied successfully to the Eurocontrol ASA programme's CORA-2 project to produce an operational requirements document. Lessons learned have led to improvements reported in this paper as the basis for further applications of RESCUE in the ASA programme.