ResearchPDF Available

Journal of Financial Management of Property and Construction Article information: For Authors Analysis of causes of delay in Indian construction projects and mitigation measures

Authors:

Abstract

Analysis of causes of delay in Indian construction projects and mitigation measures Prasad K.V. If you would like to write for this, or any other Emerald publication, then please use our Emerald for Authors service information about how to choose which publication to write for and submission guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information. About Emerald www.emeraldinsight.com Emerald is a global publisher linking research and practice to the benefit of society. The company manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as well as providing an extensive range of online products and additional customer resources and services. Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for digital archive preservation. Abstract Purpose-Construction projects in India continue to suffer excessive delays. This paper aims to investigate the delay causes in India by project sector (transport, power, buildings and water) and carry out a comparative study of delay causes in design build (DB) projects with that of design bid build (DBB) projects along with mitigation measures. Design/methodology/approach-A questionnaire survey was conducted among major clients, contractors and consultants in India. Importance Index was used for ranking of the delay causes. Projects were categorized based on the type, and causes of delay in each project type were identified. Projects were also categorized based on type of contract, and delay causes in DB and DBB projects were compared. Statistical analysis of responses by Cronbach's alpha, one-way analysis of variance, Kruskal-Wallis tests was carried out with Statistical Package for Social Sciences. Semi-structured in-depth interviews were conducted with senior industry professionals to develop exhaustive mitigation measures. Findings-The research findings indicate finance-related causes as the most critical causes of delay in Indian projects. Delay in settlement of claims, contractor's financial difficulties, delay in payment for extra work/variations by owner, late payment from contractor to subcontractor or suppliers, variation orders/changes of scope by owner during construction and changes in design by owner were the highly ranked delay causes. The research found no significant difference in the delay causes in DB and DBB projects. Originality/value-This is the first study wherein delay causes for various project types within a single country are identified. In addition, the study has identified and compared the delay causes in DB projects and DBB projects. Mitigation measures developed in this study will help professionals and project managers not just in India but other developing countries as well to alleviate delay causes and in improvement of project timelines.
Journal of Financial Management of Property and Construction
Analysis of causes of delay in Indian construction projects and mitigation
measures
Prasad K.V., Vasugi V., Venkatesan R., Nikhil Bhat,
Article information:
To cite this document:
Prasad K.V., Vasugi V., Venkatesan R., Nikhil Bhat, (2019) "Analysis of causes of delay in Indian
construction projects and mitigation measures", Journal of Financial Management of Property and
Construction, https://doi.org/10.1108/JFMPC-04-2018-0020
Permanent link to this document:
https://doi.org/10.1108/JFMPC-04-2018-0020
Downloaded on: 22 January 2019, At: 05:07 (PT)
References: this document contains references to 70 other documents.
To copy this document: permissions@emeraldinsight.com
Access to this document was granted through an Emerald subscription provided by
Token:Eprints:fieMURtDGcCiJHQafhMs:
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald
for Authors service information about how to choose which publication to write for and submission
guidelines are available for all. Please visit www.emeraldinsight.com/authors for more information.
About Emerald www.emeraldinsight.com
Emerald is a global publisher linking research and practice to the benefit of society. The company
manages a portfolio of more than 290 journals and over 2,350 books and book series volumes, as
well as providing an extensive range of online products and additional customer resources and
services.
Emerald is both COUNTER 4 and TRANSFER compliant. The organization is a partner of the
Committee on Publication Ethics (COPE) and also works with Portico and the LOCKSS initiative for
digital archive preservation.
*Related content and download information correct at time of download.
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Analysis of causes of delay in
Indian construction projects and
mitigation measures
Prasad K.V. and Vasugi V.
School of Mechanical and Building Sciences, VIT University, Chennai, India
Venkatesan R.
National Institute of Construction Management and Research, Pune, India, and
Nikhil Bhat
Central Projects Planning, Hindustan Construction Co Ltd, Mumbai, India
Abstract
Purpose Construction projects in India continue to suffer excessive delays. Thispaper aims to investigate
the delay causes in India by project sector (transport, power, buildings and water) and carry out a
comparative study of delay causes in design build (DB) projects with that of design bid build (DBB) projects
along with mitigation measures.
Design/methodology/approach A questionnaire survey was conducted among major clients,
contractors and consultants in India. Importance Index was used for ranking of the delay causes.
Projects were categorized based on the type, and causes of delay in each project type were identied.
Projects were also categorized based on type of contract, and delay causes in DB and DBB projects were
compared. Statistical analysis of responses by Cronbachs alpha, one-way analysis of variance,
KruskalWallis tests was carried out with Statistical Package for Social Sciences. Semi-structured in-
depth interviews were conducted with senior industry professionals to develop exhaustive mitigation
measures.
Findings The research ndings indicate nance-related causes as the most critical causes of delay in
Indian projects. Delay in settlement of claims, contractorsnancial difculties, delay in payment for
extra work/variations by owner, late payment from contractor to subcontractor or suppliers, variation
orders/changes of scope by owner during construction and changes in design by owner were the highly
ranked delay causes. The research found no signicant difference in the delay causes in DB and DBB
projects.
Originality/value This is the rst study wherein delay causes for various project types within a single
country are identied. In addition, the study has identied and compared thedelay causes in DB projects and
DBB projects. Mitigation measures developed in this study will help professionals and project managers not
just in India but other developing countries as well to alleviate delay causes and in improvement of project
timelines.
Keywords Infrastructure projects, India, Construction time, Construction project management,
Construction in developing countries, Delays in project delivery
Paper type Research paper
Introduction
India is among the worlds most rapidly growing economies (ADB, 2013), and demand for
infrastructure development is tremendous. As per Indias Census 2011, 31 per cent of Indias
population, i.e. 377 million, live in urban areas and is expected to increase to 600 million by
2030. It is estimated that about US$650bn investment in India will be required for urban
Causes of
delay
Received 6 April2018
Revised 26 August2018
21 October 2018
20 November 2018
Accepted 30 November2018
Journal of Financial Management
of Property and Construction
© Emerald Publishing Limited
1366-4387
DOI 10.1108/JFMPC-04-2018-0020
The current issue and full text archive of this journal is available on Emerald Insight at:
www.emeraldinsight.com/1366-4387.htm
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
infrastructure alone over next 20 years (Planning commission, 2013). Growing population,
increasing urbanization and global competition have made it imperative that the
infrastructure is developed rapidly. Accordingly, the investment in infrastructure is planned
to be increased from Indian National Rupees (INR) 23.8tn in the 11th Five Year Plan period
(2007-2012) to INR 56.3tn in the 12th Five Year Plan Period (2012-2017) (Ernst and Young,
2014). This huge demand in infrastructure is to be met by the construction sector.
Construction sector is a catalyst for economic growth as it stimulates development in
other sectors (Ismail, 2007). The inuence of the construction sector spans across several
sub-sectors and thus becomes the input for socio economic development. Construction sector
in India has witnessed boom over the decade and is considered one of the most important
industries as it contributes approximately 8 per cent of Indias gross domestic product and is
the second largest employer (Ananthanarayanan, 2011).
Construction project delays are a global phenomenon (Sambasivan and Soon, 2007), and
India is not an exception. Even with an increase in the stimulus and support from the
government, the construction industry in India continues to struggle with delays. Projects in
India are experiencing widespread delays (Scholarly Editions, 2013). As per the project
implementation status report (IPMD, 2018) of Government of India, as on July 2017, out of
total of 1,257 ongoing projects (costing INR 1.5bn and more), 274 projects (22 per cent) are
suffering time overrun. There is a signicant shift in the capacity and volume of the
construction sector, which demands the need of a systematic study and assessment of the
reasons of project delays in India along with mitigation measures.
Literature review
Construction projects continue to suffer delays despite the application of advanced
technology and project management techniques (Stumpf, 2000). This is the reason why
construction project delays have attracted researchers over the years. A recent survey
(KPMG, 2015) revealed that only 25 per cent of the projects were completed within their
original deadlines. This research work started with an extensive review of the studies
carried out over the years. The extent of delays as documented by various studies,
summarized in Table I, reveals that the problem of delays is a global epidemic. During this
literature review phase, 53 research studies from 30 countries, with 38 studies in developing
countries and 15 studies in developed countries, were reviewed. From this detailed review,
the authors have presented the salient ndings of recent and near recent studies (post 1995)
in the following section of the paper. Delay studies were categorized into studies in
developed countries and developing countries, with the aim of bringing out the distinct
nature of delay causes in the two types of economy. Largely, studies in the past have
adopted questionnaire surveys as the research method for identifying the delay causes and
Relative Importance Index (RII), Importance Index (II) and Relative Importance Weight as
the means to rank the various causes of delay.
Some of the notable studies carried out in developed countries include Ahmed et al. (2003)
in Florida, Hwang et al. (2013) in Singapore, Wong and Vimonsatit (2012) in Australia,
Shebob et al. (2012) in the UK, Chen et al. (2017) in China and Larsen et al. (2015) in Denmark.
These studies concluded building permits approval, change order, changes in drawings,
incomplete documents and inspections, site management, skill shortages, labor shortage,
material price changes, extreme weather conditions, onsite labor and material availability,
subcontractor problems, unsettled/lack of project funding, delay or long process times
caused by project authorities, lack of project planning, errors or omissions in construction
work and lack of identication of needs as the major causes of delay.
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
There have been many studies in developing countries, such as Odeh and Battaineh (2002)
in Jordan, Frimpong et al. (2003) in Ghana, Alaghbari et al. (2007) in Malaysia, Assaf and Al-
Hejji (2006) in Saudi Arabia, Sweis et al. (2006) in Jordan, Kaming et al. (1997) and Toor and
Ogunlana (2008) in Thailand, Lo et al. (2006) in Hong Kong and Doloi et al. (2012) in India.
Project nancing by contractor, interference from owner, contractors inadequate
experience, nancing of project, labor productivity, shortage of labors, difculties in
monthly payments, poor contract management, procurement of materials, late supervision
and slowness of decision, slowness in instruction by consultant, lack of materials in market,
ineffective planning and scheduling of project by contractor, poor site management and
supervision, etc. were found to be the major causes of delay in these studies.
While there has been extensive research to identify delay causes, it was important to
understand whether mitigation measures were also identied. The review of literature on
mitigation measures is summarized in Table II.
From the review of literature, it is found that nature of delay causes in developing
countries is signicantly different from that in developed countries. In the case of
developing countries, delay causes are originating internally from contractor or client, such
as nancial difculties, cash ow problems, change orders by client and payment delays by
owner (Islam and Trigunarsyah, 2017). In the case of developed countries, external causes
such as weather, prices of materials, permits and labor supply are critical causes. This may
be the case as contractors working in developing economies work under special constraints,
which are not as serious in developed countries (Ogunlana et al., 1996).
Construction projects are unique and share distinct characteristics. The physical and
operational features of the project have a signicant impact and contribute hugely to project
success or failure (Kwoeet al.,2014). This is a signicant gap in the previous studies as
many previous studies have investigated causes of delays without investigating the delay
Table I.
Extent of delays in
construction projects
in various countries
Study Country Type of projects Time delays documented
Semple et al. (1994) Canada Generic Delays in several cases exceeded
original contract duration by over 100%
Arditi et al. (1985) Turkey Utility projects 34.6% delay in contractors projects,
43.6% delay in public projects
Chan and Kumaraswamy
(1995)
Hong Kong Building and Civil
Works
Average delay in excess of 20%, only
40% Government buildings, 25%
private buildings, 35% civil engineering
works completed within schedule
Odeyinka and Yusif (1997) Nigeria Housing Seven out of ten housing projects
suffered delays
Olatunde and Alao (2017) Ghana Buildings Average time overrun in construction of
public university buildings was 62.7%
Eliis and Thomas (2003) USA Highway Time overrun in 150 projects averaged
272 days or 25% of contract duration
Koushki et al. (2005) UAE Residential Buildings Out of 450 buildings, 56% projects
experienced delay
Sambasivan and Soon (2007) Malaysia Government projects 17.3% of the projects experienced
delays of more than 3 months
Ansar et al. (2016) Many
countries
Mixed Average schedule overrun was 42.7%
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
causes in a specic type of projects (Prasad and Vasugi, 2017). Studies have been mostly
generic, except a few studies investigating delay causes in buildings and roads. Further, it is
also a fact that the construction industry in India has evolved from traditional rate contracts
to lump sum and design build (DB) contracts (Ernst and Young, 2014). None of the previous
studies have drawn a comparison of the delay causes in a different nature of contracts. An
understanding of this can aid in evaluating the lacunae and shortcomings in project
implementation and in improvement of project performance.
Most of the studies, including an earlier study in India (Doloi et al.,2012), have ended up
with the identication of delay causes without corrective steps, practical recommendations
and exhaustive mitigation measures to prevent the causes of delay, which is of relevance
and importance. A previous study (AlSehaimi et al., 2013) concluded that most of the delay
studies have not recommended any solution, and the recommendations do not match with
the ndings and have ended up providing recommendations which are non-practical. In
addition, mitigation measures provided by earlier studies (Table II) are cursory and lack the
depth and specics for control of delay. Professionals and project managers in the industry
will need specic, implementable and practical solutions to overcome problems causing
delay.
With the above identied research gaps, this study intends to:
identify the critical causes of delay in Indian construction projects in various types
of project and analyze the results by each project type (transport, buildings, water
and power);
compare the delay causes in DB and design bid build (DBB) projects in India; and
identify steps and measures of mitigation through the project life cycle from the
contract award phase to executing phase to control critical delay causes.
Research methodology
Research design
A questionnaire was designed to solicit the responses of major contractors, clients,
consultants and designers in India. In total, 60 causes of delay from literature were adopted
for the questionnaire and were grouped into seven categories. The causes and categories are
listed in Table IV. The questionnaire consisted of ve sections. The rst section introduced
the problem, objective of the survey; the second section collected personal information of the
respondents, such as name, experience, role and contact details; the third section collected
Table II.
Mitigation measures
identied by
previous research
Mitigation measures Studies
Comprehensive contract documents Abdul-Rahman et al. (2006),Kasimu and Abubakar (2012)
Accurate initial estimates Love et al. (2000),Ng (2007),Chai et al. (2015)
Improve planning and control Assaf and Al-Hejji (2006),Faridi and El Sayegh (2006)
Right resources, right software Zewdu (2016)
Minimize changes in design Abdul-Rahman et al. (2006),Alaghbari et al. (2007)
Accelerate site activities Chai et al. (2015),Abdul-Rahman et al. (2006);
Ensure delivery of materials on time Abdul-Rahman et al. (2006)
Ensure adequate nancing Abdul-Rahman et al. (2006),Lo et al. (2006)
Implement new management techniques Mezher and Tawil (1998),Arditi et al. (1985)
Improve communication Mezher and Tawil (1998),Arditi et al. (1985)
Frequent progress meetings Abdul-Rahman et al. (2006),Ng (2007)
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
information about the project for which respondents ll the delay causes; and the fourth and
fth sections were designed to collect the response on the delay causes. The respondents
were asked to rate frequency, with rating of 1 for a cause that never occurs and 5 for most
frequent cause, and degree of severity, with rating of 1 for a cause with no impact and 5 for a
cause with very high impact, on a particular project in which they had worked/had
experience. Combining Likert scales into indexes adds values and variability to the data
(Allen and Seaman, 2007). Survey data resulting from the use of questionnaires are
frequently analyzed using the RII method (Holt, 2014), and this helps in generating an index,
which is then used to rank the delay causes. Accordingly, this method is adopted for
calculating the frequency and severity indexdened below.
The frequency index (FI) and severity index (SI) of the causes were calculated as:
FI=SI ¼PW
AN
ðÞ
where W is the rating assigned (ranging from 1 to 5) for each cause by the respondents, A is
the maximum rating/score that can be assigned to a cause, which in the present case is 5,
and N denotes the total number of respondents of the survey.
The causes were ranked based onII determined as a product of FI and SI:
II ¼FI SI
Importance Index (II) calculated by the above formula factors the two equally important
dimensions of frequency of occurrence and severity of impact of delay causes and has been
adopted in previous research studies as well.
The values of FI, SI and II ranged from 0.2 to 1. A higher value (closer to 1) of FI meant
that the cause was more frequent, and a higher the value of SI meant that the cause had a
very high impact. Finally, the causes were ranked based on the values of II. Higher the value
of II, higher the ranking and its signicance in causing delay in construction projects.
Projects were also categorized based on project sectors, namely, transportation, power,
buildings and water supply/irrigation projects, and delay causes in each project type were
identied and discussed.
To understand the inuence and criticality of delay causes in different contract
environments, responses were analyzed by categorizing the projects by type of contract. The
present research work covered projects of two contract types DB and DBB.
Sampling and questionnaire dissemination
As future projects in India are expected to be in the range of INR 10-15bn (PWC, 2008), the
research work specically targeted contracting companies, clients and consultants engaged
in operating mega projects with contract value of >INR 10bn in India. A questionnaire was
disseminated to various organizations through the online mode using the Google Forms
platform.
Interviews for identication of mitigation measures. To develop mitigation measures,
present research adopted the methodology of an earlier study Olawale and Sun (2010).
A series of in-depth semi-structured interviews were held with senior construction
industry professionals. The experts interviewed had a work experience of more than 20
years in Indian construction projects and were from contracting and consulting
organizations. Ten experts were interviewed. The interviewees comprised one head of
planning, three deputy project managers, two project managers, one senior general
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
manager of engineering, one general manager of contracts, one joint chief operating
ofcer from a contracting organization and one associate director from a consulting
organization. The interview duration ranged from 30 to 60 min. The interviews were
semi-structured, which allowed unhindered discussion and to inquire further as
necessary during the discussion. For focused interview and discussion, the top six causes
of delay were only considered for this exercise. Mitigation measures were further
categorized into the following three categories:
Preventive: These are measures/steps to be taken as a precaution to prevent the
occurrence of a delay cause.
Organizational: These are measures/steps that will affect all projects of a
company and are not project-specic and would reect how the wider
organization works.
Corrective: These are measures initiated after the occurrence of a delay cause to
mitigate and prevent the further impacts and bring situation under control.
Results and discussion
The questionnaire was sent to 200 respondents. In all, 130 responses were received (a
response rate of 65 per cent), of which 123 responses were valid. The responses covered
projects from 20 states spread across the length and breadth of India. The median and
average of delay in the 123 projects was 24 and 31 months, respectively. The summary of
responses received, prole of respondents and projects covered are as in Table III. The
survey responses were analyzed using SPSS version 24.
Cronbachs alpha is a measure of the internal consistency or average correlation of the
items in a survey instrument. The test is most commonly used on Likert scale questions in a
survey and determines the reliability of the scale (Santos, 1999). The test results returned
values of 0.955, 0.975 and 0.980 for frequency responses, severity responses and overall
questionnaire, respectively. A value of alpha greater than 0.7 implies that the instrument is
acceptable and the results conrm that the questionnaire is reliable.
A one-way ANOVA test was conducted to analyze and examine for any signicant
differences in the perceptions of the three different groups of respondents contractors,
clients and consultants. Results are summarized in Table IV, and out of a total of 120
possible cases for frequency and severity put together, 87 cases (73 per cent) were found to
have no signicant difference statistically, which meant that the three groups of
respondents largely agree.
Delay causes in Indian projects (overall)
Results of the survey with top ten causes of delay in Indian construction projects are
presented in Table V. Delay in settlement of contractor claims by the owner, contractors
nancial difculties, delay in payment for extra work/variations by owner, late payment
from contractor to subcontractor or suppliers, variation orders/changes of scope by owner
during construction, changes in design by owner or his agent during construction, shortage
of labor, failure to provide construction site by owner, delay by owner in revision and
approval of design documents and owners slow decision-making process are found to be the
top ten causes of delay. The results indicate nancial causes as the most critical in Indian
projects. Top six causes of delay, which were ranked high in all the project types (results
presented in next section), are discussed.
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Top two causes of delay identied in this study, namely, delay in settlement of contractor
claims and contractorsnancial difculties, are explained by the fact that an estimate as
high as INR 700bn is tied up in arbitration and the average settlement time of these claims is
more than seven years (PIB, 2016). Government of India has recognized the gravity of this
problem and has come up with some relief measures (PIB, 2016).
Table III.
Summary of
responses and prole
of respondents
Characteristics Frequency % of total
Role
Clients 18 15
Contractors 96 78
Consultants 9 7
Total 123
Education
Diploma 2 2
Graduate 38 31
Post Graduate 82 67
PhD 1 1
Total 123
Experience
<5 Years 27 22
5-10 Years 47 38
10-15 Years 19 15
>15 Years 30 24
Total 123
Job prole
Site Engineering/works 10 8
Engineering/methodology 8 7
Planning/Project management 61 50
Project control/PMO 20 16
Contracts/Quantity survey 16 13
Others 8 7
Total 123
Occupational level
Non executive 33 27
Executive 49 40
Middle management 31 25
Senior management 10 8
Total 123
Contract type
DB 72 58
DBB 51 42
Total 123
Project prole
Transportation 45 37
Buildings 30 24
Water supply/Irrigation 17 14
Power 22 18
Marine 7 6
Others 2 2
Total 123
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Category Cause of delay
ANOVA (Sigma)
Frequency Severity
Planning, Design and
Engineering
Poor scope denition by contractor 0.384 0.187
Inadequate early planning of project 0.022* 0.070
Ineffective project planning and scheduling 0.409 0.066
Improper technical study by contractor during bidding 0.654 0.073
Inaccurate estimate of materials 0.635 0.192
Improper or inaccurate cost estimation by contractor 0.616 0.226
Exceptionally low bids by contractor 0.176 0.135
Inadequate integration on project interfaces 0.723 0.493
Mistakes/changes in design criteria provided by the
employer
0.175 0.032*
Unclear and inadequate details in drawings 0.092 0.013*
Changes in design by owner or his agent during construction 0.001* 0.004*
Errors and omissions in design made by designers 0.650 0.195
Delays in producing design documents by contractor 0.481 0.179
Poor design with constructability problems 0.614 0.441
Delay by owner in revision and approval of design
documents
0.002* 0.017*
Procurement Difculties in obtaining construction materials from market 0.335 0.972
Shortages of materials 0.747 0.835
Shortage of equipment 0.962 0.947
Delay in delivery of imported materials and plant items 0.605 0.313
Financial Delay in monthly payments from owners 0.194 0.929
Gap between construction costs and stage payments 0.005* 0.042*
Contractorsnancial difculties 0.635 0.717
Late payment from contractor to subcontractors or suppliers 0.778 0.728
Delay in payment for extra work/variations by owner 0.000* 0.000*
Delay in settlement of contractor claims by owner 0.000* 0.004*
Human resource Poor labor productivity 0.166 0.049*
Shortage of labor 0.870 0.750
Lack of skilled operators for specialized equipment 0.777 0.898
Poor skills and experience of labor 0.717 0.301
Lack of experience/incompetence of contractors key staff 0.993 0.833
Project execution Failure to provide required construction site by owner 0.001* 0.038*
Delay in mobilization by the contractor 0.130 0.133
Poor site management and supervision 0.897 0.793
Lack of contractors experience and control over project 0.051 0.948
Equipment breakdown and maintenance problem 0.185 0.411
Owners slow decision-making process 0.002* 0.027*
Poor monitoring and control 0.352 0.347
Inappropriate or obsolete construction methods 0.226 0.290
Rework due to errors during construction 0.433 0.193
Works in conict with existing utilities 0.365 0.208
Site accidents due to negligence and lack of safety measures 0.748 0.843
Non-performance of subcontractors and nominated suppliers 0.372 0.609
Delay in inspection and testing of completed work 0.002* 0.115
(continued)
Table IV.
Delay causes,
categories and
results of one-way
ANOVA test
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
The third cause of delay, i.e. delays in payment for extra work, is one of the most frequent
problems faced by Indian contractors (Al-Quershi and Kishore, 2017). During the course of
project execution, depending upon the projects requirements, owners may instruct
contractors to execute items which were not part of the original contract bill of quantities.
As this being a new item, rates need to be nalized. Contractors are expected to carry out
these extra work without nalization of rates, burdening the nances of contractor and
affecting time performance.
Late payment to suppliers/subcontractors is a resultant of payment delays from owners.
Governments and private owners implementing large projects are delaying payments, and
in the challenge of managing stressed cash ow, contractors are forced to delay payments to
vendors (Livemint, 2015).
Variation orders/scope changes is one of the most important phenomena in the
construction projects. Change orders issued during construction are major causes of time
and cost overruns (Alnuaimi et al.,2010). Frequent changes require contractors to augment/
allocate resources for these changes and also re-sequence the work. While this has a direct
cost impact for additional resources, frequent changes also lead to loss of productivity (Ibbs
and Vaughan, 2015), leading to time delays.
Changes in design can occur at any stage of the project. However, the earlier a design
change occurs, the lesser will be the impact on the project than a change at later phases of
the project (Braganca et al.,2014). Design changes increase the cost and time of construction
projects substantially (Chang et al., 2011).
Category Cause of delay
ANOVA (Sigma)
Frequency Severity
Contract management Unrealistic contract duration imposed by owner 0.001* 0.011*
Ambiguity in specications and conicting interpretation by
parties
0.003* 0.054
Errors or inconsistencies in project documents 0.141 0.084
Variation orders/changes of scope by owner during
construction
0.000* 0.017*
Noncompliance with conditions of contract 0.384 0.187
Unrealistic inspection and testing methods proposed in
contract
0.022* 0.070
Unreasonable risk allocation in contract 0.409 0.066
Lack of process for comprehensive dispute resolution 0.654 0.073
External Government tendering system requirement of selecting the
lowest bidder
0.034* 0.032*
High ination, insurance and interest rates 0.012* 0.001*
Adverse weather conditions 0.035* 0.612
Public interruptions 0.006* 0.071
Differing or unforeseen site/subsurface conditions 0.034* 0.008*
Issues regarding permissions/ approvals from other
stakeholders
0.148 0.280
Changes in government regulations and laws 0.059 0.297
Force majeure: war, revolution, riot, strike, earthquake, etc. 0.144 0.836
Project fraud and corruption 0.718 0.656
Note: *Indicates difference in perception of contractors, clients and consultants is signicant at 0.05
level Table IV.
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Sectoral analysis of delay causes
The distribution of sample of projects by category is given in Table III. Although marine
projects were part of the study, as the sample size was too small, these were excluded from
the analysis and comparison. The delay causes arranged by the rank of the causes are
provided in Table V.
Results indicate that nance-related causes are critical in all project sectors.
Transport sector projects are delayed by land acquisition delays and works in conict
with utilities. Land acquisition is found to be one of biggest roadblocks because of poor and
unsystematic land records in India coupled with undervaluation and lengthy acquisition
process (Development Management, 2017). Utility shifting is one of the critical causes of
delay in Indian road and bridge construction projects (Vilventhan and Kalidindi, 2016). The
gap in construction costs and stage payments can be attributed to the fact that in India, road
construction projects are being largely implemented on engineering procurement and
Table V.
Top ten causes of
delay by project type
Overall Transport Power Buildings
Water/
irrigation
Delay causes II Rank II Rank II Rank II Rank II Rank
Delay in settlement of contractor claims 0.608 1 0.620 1 0.662 2 0.574 2 0.663 1
Failure to provide required construction
site by owner 0.453 8 0.581 2 0.365 40 0.366 26 0.583 4
Delay in payment of extra work/variations 0.535 3 0.573 3 0.602 4 0.505 6 0.483 11
Contractorsnancial difculties 0.550 2 0.517 4 0.677 1 0.535 4 0.490 9
Variation orders/change of scope by owner 0.494 5 0.493 5 0.475 14 0.461 11 0.530 7
Late payment from contractor to
subcontractor or suppliers 0.511 4 0.487 6 0.531 5 0.535 3 0.441 19
Exceptionally low bids by contractor 0.425 17 0.457 7 0.456 20 0.425 15 0.400 25
Owners slow decision-making process 0.447 10 0.454 8 0.490 11 0.366 27 0.469 15
Works in conict with existing utilities 0.397 20 0.446 9 0.331 48 0.392 20 0.460 16
Gap between construction costs and stage
payments stipulated in contract 0.429 15 0.435 10 0.419 26 0.425 16 0.470 14
Changes in design by owner during
construction 0.475 6 0.429 11 0.489 12 0.598 1 0.367 31
Delay by owner in revision and approval of
design documents 0.452 9 0.425 13 0.463 16 0.453 12 0.489 10
High ination, insurance and interest rates 0.398 19 0.422 14 0.496 10 0.341 38 0.441 20
Issues regarding permissions from
stakeholders 0.433 13 0.419 15 0.407 27 0.475 10 0.595 3
Unrealistic contract duration imposed by
owner 0.441 12 0.413 16 0.523 6 0.379 23 0.541 5
Mistakes/changes in the design criteria
provided by employer 0.442 11 0.409 17 0.457 17 0.512 5 0.404 23
Public interruptions 0.432 14 0.406 18 0.610 3 0.309 46 0.606 2
Lack of process for comprehensive dispute
resolution 0.394 21 0.393 20 0.349 45 0.453 13 0.531 6
Shortage of labor 0.455 7 0.390 21 0.497 9 0.482 9 0.451 17
Poor labor productivity 0.413 18 0.387 22 0.503 7 0.377 24 0.422 21
Improper or inaccurate cost estimation by
contractor 0.375 26 0.364 26 0.503 8 0.373 25 0.408 22
Unclear and inadequate details in
drawings 0.382 22 0.342 33 0.438 24 0.497 7 0.294 50
Errors and omissions in design made by
designers 0.348 34 0.305 45 0.352 44 0.482 8 0.269 55
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
construction basis with lump sum milestone/stage payments. Till the achievement of
milestone, a contractor continues to incur costs for the input materials and needs to fund the
expenses, which can create nancial woes to the contractor, resulting in delays
(Infrastructure today, 2011).
Public interruptions, poor labor productivity, shortage of labor and unrealistic contract
durations are found to be the critical causes of delay in power sector projects. The sample of
power projects in this research work included nuclear and hydro power projects.
Construction of a nuclear building requires about 3,500 skilled workers at peak (NEI, 2012).
Shortage of labor and shortage of skills lower the productivity, resulting in schedule delays.
Hydro power plants cause population displacement, and the affected families need
rehabilitation with employment. Inadequate resettlement results in resistance, political
tensions and entails project delays (World Bank, 1997).
Successful completion of a building project requires close coordination and cooperation
between the owner, designer and contractor. Lack of proper interfacing and clarity in the
concept stage may lead to a gap in the design and construction phases. Changes in design is
a common phenomenon in building projects (Mohamad et al.,2012) and is evident from the
results of this study, which has design changes by owner, mistakes in design, unclear and
inadequate detail in drawings, design errors andomissions as the critical causes.
Unlike other projects, water projects are least affected by nance-related causes and are
impacted by land acquisition, public interruptions and permission from other stakeholders.
Table VI.
Top ten causes of
delay in DB projects
in India
Cause
Frequency
index (FI)
Severity
index (SI)
Importance
index (II)
Delay in settlement of contractor claims by owner 0.772 0.738 0.570
Contractorsnancial difculties 0.715 0.758 0.542
Late payment from contractor to subcontractors or suppliers 0.715 0.718 0.514
Variation orders/change of scope by owner during construction 0.704 0.713 0.502
Failure to provide required construction site by owner 0.693 0.685 0.474
Delay in the settlement of contractor claims by owner 0.693 0.682 0.472
Shortage of labor 0.679 0.662 0.449
Changes in design by owner during construction 0.676 0.662 0.448
Differing or unforeseen site/subsurface conditions 0.673 0.659 0.444
Owners slow decision-making process 0.651 0.673 0.438
Table VII.
Top ten causes of
delay in DBB
projects in India
Cause
Frequency
index (FI)
Severity
index (SI)
Importance
index (II)
Delay in settlement of contractor claims by owner 0.777 0.777 0.604
Delay in payment for extra work/variations by owner 0.765 0.773 0.592
Contractorsnancial difculties 0.704 0.762 0.536
Shortage of labor 0.696 0.708 0.493
Late payment from contractor to subcontractors or suppliers 0.692 0.712 0.493
Changes in design by owner during construction 0.673 0.719 0.484
Delay by owner in revision and approval of design documents 0.658 0.700 0.460
Variation orders/change of scope by owner during construction 0.677 0.677 0.458
Poor labor productivity 0.669 0.669 0.448
Mistakes/changes in the design criteria provided by the employer 0.685 0.650 0.445
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Table VIII.
KruskalWallis Test
on median of delay
cause categories in
DB and DBB Projects
Delay cause category PDE* Procurement Financial
Human
resource
Project
execution
Contract
management External
Frequency
KruskalWallis H 0.048 0.294 0.305 0.521 0.082 0.380 1.143
Df 1 1 1 1 1 1 1
Asymp. Sigma 0.827 0.588 0.580 0.470 0.774 0.538 0.285
Severity
KruskalWallis H 0.104 0.310 1.048 1.048 0.062 0.187 0.145
Df 1 1 1 1 1 1 1
Asymp. Sigma 0.747 0.578 0.306 0.306 0.803 0.665 0.703
Note: *PDE: Planning, Design and Engineering
Table IX.
Mitigation measures
for delay in
settlement of claims
Responsibility
Mitigation measures Category CO
a
CL
b
EN
c
Agreement on records, software required, methodology of assessing
delays, evidence of claims and compensation mechanism Preventive 
Contract documentation: Unambiguous, clear, fair allocation of risks
in the contract, free of errors and omissions Preventive 
Review of scope of work, bid quantities coordinated with drawings,
specications, equipment, methods, schedule feasibility, payment
mechanisms, quality control requirements Preventive 
Detailed site investigation to cover surface, subsurface conditions,
local labor availability, logistics, access to site, existing hindrances Preventive 
Review of project schedule for adequacy, feasibility considering site
constraints, existing encumbrances, for logic, sequence, resources,
intermediate milestones, site access dates, timeline for drawings
approval etc. Preventive 
Hindrance register indicating the hindrances for work, extent of
delay and party responsible to be mandatorily reviewed signed off
periodically Preventive 
Panel for Dispute Adjudication, Dispute Resolution and Arbitration
to be pre-dened Preventive 
A thorough and detailed contract risk analysis to cover performance
criteria, completion schedules, payment terms, penalties,
legislations, change order, dispute resolution procedures etc. Organizational
Documentation of changes, instruction for change, notication of
change, impact of change on time and cost, records of costs and
man-hours for changed work Corrective
Analysis of the contractor claim, impact, contractual provisions,
records, certication of changed work, payment on pro-rata basis for
changed work, appointment of panels in case of non-resolution Corrective 
Payment for contractors claim immediately on upon third party
adjudication against security bonds Corrective
Notes:
a
Contractors;
b
Clients;
c
Engineer
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Delay causes in design build and design bid build projects.
The top ten causes of delay in DB and DBB projects are presented in Tables VI and VII. The
key conclusions from the comparison are as follows:
Financial causes are rated high in both DB and DBB projects.
Shortage of labor exists in both the types of contracts in Indian projects.
Design-related causes play a major role in delay of DBB projects, which is
evident as three out of top ten causes are related to design, namely, design
changes, delay in revision and approval of design documents and mistakes in
design criteria.
The ranking of all the causes in DB and DBB projects was assessed, and Spearmans rank
correlation coefcient was determined. The result of the test was 0.81, indicating that there
were no signicant differences in the importance of the causes in DB and DBB projects in
India.
The results were further closely examined by computing the median of delay categories
in DB and DBB projects and subjecting to KruskalWallis Test at 95 per cent condence
level. The values of sigma for all delay categories were greater than 0.05, proving that there
Table X.
Mitigation measures
for contractors
nancial difculties
Responsibility
Mitigation measures Category CO
a
CL
b
EN
c
A thorough and detailed risk analysis before bid decision to cover
payment clauses, stage and milestone related payments, forex
currency forecast and uctuations, cash ow based project plan Organizational
Assess the nancial strength, working capital levels, contractors
organization market liability, contract performance record, credit
rating Preventive 
To adopt market price-based escalation formulae than indices based,
to prevent mismatch between price rise and escalation compensation Organizational
To adopt project based funding mechanism, i.e. cash generated from
project to be used for the sole purpose of that project only Organizational
Owners to pay against mobilization of pre-dened equipment and
clear mobilization targets, to prevent diversion of fund by the
contractors Preventive
To maintain due records of pour cards, RFIs, QA/QC clearances.
Invoice to owners in a timely manner, maintain minimum inventory
and tie agreements with vendors, suppliers, subcontractors in line with
owners payment conditions Preventive
To pre dene and set aside a contingency sum based on the type of the
contract, and risks involved, to be used for nancial related risk events Preventive
Align payment milestones to be in sync with contractors vendor
payment terms. Allow exibilities within the original contract
payment schedule to support the working capital requirements of
contractor
Preventive-
Corrective
To do away with the tradition of retaining a xed percentage sum of
usually 5% to 10% of cash from contractor bills Organizational
Notes:
a
Contractors;
b
Clients;
c
Engineer
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
was no signicant difference in the delay causes of DB and DBB projects. The results are
shown in Table VIII.
Comparison of results with earlier studies
Results of this research were compared with top delay causes of earlier studies in developing
countries. Cash ow problems, delay in payment by contractor to subcontractors, delay of
payments by owners, design and material changes, poor labor productivity, slowness in
owners decisions and variation orders were found to be the top causes of delay as
documented by earlier studies (Shehu et al.,2014;Kazaz et al.,2012;Manseld et al.,1994;Al-
Khalil and Al-Ghay(1999),Pourrostam and Ismail (2012),Marzouk and El-Rasas (2014),
Kaming et al.,1997). This comparison reects a common pattern and characteristic in
developing countries as summarized in literature review. The results of present study are in
close agreement with that of earlier studies in developing countries. Projects are delayed
mostly due to payment-related problems from the owner to contractor and from contractor to
subcontractors, cash ow and nance-related difculties of the contractor.
Mitigation measures
As indicated and detailed in the research methodology, semi-structured interviews
were conducted to develop mitigation measures. Responsibility matrix among
Table XI.
Mitigation measures
for delay in
settlement of
variations and
changes in scope
Responsibility
Mitigation measures Category CO
a
CL
b
EN
c
Ensure the contract clauses dene mechanism related to price for extra
work, time extension eligibility and limit of extra work Preventive 
Distinctly dene the procedure for evaluation of rates for Extra work
and substituted items, provision of escalation money payable on the
extra work and substituted items Preventive 
Review of scope of work, bid quantities coordinated with drawings,
construction methods, resource productivities etc. Preventive 
Thorough, detailed site investigations to cover surface, subsurface
conditions, local labor availability, logistics, access to site, existing
hindrances and obstructions, records of levels and benchmarks,
records of meeting with clients representatives at site Preventive 
Ensure instructions for extra work and variations are provided in
writing only. Dene a timeline for nalizing the rates for new items,
not later than a month before the start of extra work Corrective 
Owners to ensure to get appropriate funding sanctions from the
project investors/ministries to cater for the increase in the work and
contract value Preventive
Seek all instructions in writing, submit the impact of extra work/
variations on the project schedule and cost Corrective
Records of changes, instruction for change, notication of change,
impact of change on time and cost, records of costs and man-hours for
changed work Corrective
Commence work on extra items after nalization of rates/agreement
on payment mechanism Corrective 
Notes:
a
Contractors;
b
Clients;
c
Engineer
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
contractors, clients and consultants/engineer was prepared. Mitigation measures for
delay in settlement of extra work/variations and variation orders/changes of scope by
owner were combined as the measures are common for both the causes. Mitigation
measures are shown in Tables IX-XIII.
Conclusions
(1) The study has investigated the causes of delay in India and found nance-
related causes to be the most critical causes resulting in delay of projects in
India. Comparison of the results of this study with other developing countries
indicated that nance-related causes were found to be the most critical causes
in other developing countries as well.
(2) The delay causes in India on different types of projects were identied, and the
study established that the delay causes and the criticality vary from one project
type to another. This study identied.
(3) Land acquisition and utility-related delays were main reasons in transport projects
(4) Public interruptions, labor shortage and poor productivity were main delay causes
in power projects.
(5) Design-related causes were found critical in buildings.
Table XII.
Mitigation measures
for late payment to
suppliers and
subcontractors
Responsibility
Mitigation measures Category CO
a
CL
b
EN
c
Prescribe limit for outsourcing of works by main contractor to
subcontractor either in terms of value or as a % of contract Preventive 
Maintain a database of pre-qualied suppliers and subcontractors as
in the case of contractors and ensure multiple sources/agencies are
specied in the contract Organizational 
Assess the subcontractors, suppliers based on the performance record,
nancial health who have the bandwidth to carry out work, in case of
disruptions in payments (if any) Preventive 
Major subcontracts to be nalized with due clearance from clients
mandatory clearances Preventive 
Finalize agreements with subcontractors on the same payment terms
as that of main contract to ensure no cash ow gap and burden Preventive
Flexibility to break up the payment schedules in case of lump sum
contracts into intermediate stages than all payments at end of work Corrective
Material supply against secured bonds/guarantees, which can be
encashed by subcontractors in case of undue delay in payments by
main contractor Organizational
Owners to initiate payments toward major subcontractors and
suppliers directly against the bills of the main contractor/bonds/bank
guarantees in the event contractor fails Corrective
Payment conditions of subcontractors and suppliers to include
provisions of interest on delayed and withheld payments without
justications Preventive
Notes:
a
Contractors;
b
Clients;
c
Engineer
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
(6) Water projects were delayed by land acquisition and public interruptions.
(7) This study identied the delay causes in DB and DBB projects, and a comparison
was drawn between delay causes in both contract types. Statistically, there were
no signicant differences observed in the delay causes of DB and DBB projects.
However, design-related causes were found to be critical in the case of DBB
projects.
(8) Unlike many studies of the past which ended without conclusive and denitive
mitigation measures, this study has developed exhaustive measures for the critical
causes of delay. These detailed mitigation measures can act as a checklist of best
practices and help construction industry professionals not only in India but also in other
developing countries to control delay causes and contribute to improvement in project
delivery.
Table XIII.
Mitigation measures
for changes in design
Responsibility
Mitigation measures Category CO
a
CL
b
EN
c
Pre-tender evaluation of scope of work, quantities to be detailed and
not rushed through Organizational
Review of project scope, assumptions, design criteria, constructability
with design consultants at pre tender stage Organizational
Contract to dene the design philosophy, design criteria, codal
requirements, performance criteria and tests of acceptance Preventive 
Site visit before the bid submission to inspect and validate contract
data and assess possible risks Organizational
Tender documents to provide all pertinent site investigation data,
design consultants analysis and proposal, calculations Organizational
Dene the process of design change management with clear
authorities for initiating the change Organizational 
Timelines for nalization of Designs and Issue of Good For
Construction (GFC) drawings to be dened Preventive 
Ensure the design evaluation and changes (if any) are initiated at the
early Planning and Designstages rather than late in the contract Corrective 
Designs shall be duly considering the constructability aspects, and
ensure standardization of various components and material Preventive 
Evaluate the possible changes in the designs and the impact of design
changes Preventive
Use of advanced technology such as BIM and integration across all
project participants Organizational 
Evaluation of the root cause of the design changes Corrective 
Assess the impact of design changes on the project schedule and
overall costs and margins and formal submission Corrective
Augmentation of resources to cope up with the changed designs Corrective
Formal change orders with agreement on schedule and cost impact,
before start of work as per changed design Organizational 
Communication of change in design to all project participants and
stakeholders Organizational 
Notes:
a
Contractors;
b
Clients;
c
Engineer
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Future scope of work
Further specic research should investigate the causes for disputes, delays in claim
settlements, causes for payment delays and change orders in construction projects
can be taken up.
Studies investigating delay causes in different phases of projects project initiation/
mobilization, planning and design and execution phases may provide further
deeper insights and appropriate steps for mitigation.
References
Abdul-Rahman, H., Berawi, M.A., Berawi, A.R., Mohamed, O., Othman, M. and Yahya, I.A. (2006),
Delay mitigation in the malaysian construction industry,Journal of Construction Engineering
and Management, Vol. 132 No. 2, pp. 125-133.
Ahmed, S.M., Azhar, S., Kappagantula, P. and Gollapudi, D. (2003), Delays in construction: a brief
study of the FL construction industry,Proceedings of 39th Annual Conference,Clemson
University-Clemson,SC, pp. 257-266.
Alaghbari, W., Kadir, M.R.A., Salim, A. and Ernawati, (2007), The signicant factors causing delay of
building construction projects in Malaysia,Engineering, Construction and Architectural
Management, Vol. 14 No. 2, pp. 192-206.
Al-Khalil, M.I. and Al-Ghay, M.A. (1999), Important causes of delay in public utility projects in Saudi
Arabia,Construction Management and Economics, Vol. 17 No. 5, pp. 647-655.
Allen, E.I. and Seaman, C.A. (2007), Likert scales and data analyses, available at: http://asq.org/
quality-progress/2007/07/statistics/likert-scales-and-data-analyses.html
Alnuaimi, A.S., Taha, R.A., Al Mohsin, M. and Al-Harthi, A.S. (2010), Causes, effects, benets, and
remedies of change orders on public construction projects in Oman,Journal of Construction
Engineering and Management, Vol. 136 No. 5, pp. 615-622.
Al-Quershi, M.T. and Kishore, R. (2017), Claim causes and types in indian construction Industry
Contractors perspective,American Journal of Civil Engineering and Architecture, Vol. 5 No. 5,
pp. 196-203.
AlSehaimi, A., Koskela, L. and Tzortzopoulos, P. (2013), Need for alternative research approaches in
construction management: case of delay studies,Journal of Management in Engineering,
Vol. 29 No. 4, pp. 407-413.
Ananthanarayanan, K. (2011), Indian construction industry, available at: www.jacic.or.jp/acit/
indian_national.pdf
Ansar, A., Flyvbjerg, B., Budzier, A. and Lunn, D. (2016), Does infrastructure investment lead to
economic growth or economic fragility? Evidence from China,Oxford Review of Economic
Policy, Vol. 32 No. 3, pp. 360-390.
Arditi, D., Akan, G.T. and Gurdamar, S. (1985), Reasons for delays in public projects in Turkey,
Construction Management and Economics, Vol. 3 No. 2, pp. 171-181.
Asian Development Bank (ADB) (2013), The service sector in India, ADB Economics Working Paper
Series, No, 352, June 2013.
Assaf, S.A. and Al-Hejji, S. (2006), Causes of delay in large construction projects in Saudi Arabia,
International Journal of Project Management, Vol. 24 No. 4, pp. 349-357.
Braganca, L., Vieira, S.M. and rade, J.B. (2014), Early stage design decisions: the way to achieve
sustainable buildings at lower costs,The Scientic World Journal, pp. 1-9.
Chai, C.S., Yusof, A.M. and Habil, H. (2015), Delay mitigation in the malaysian housing industry:
a structural equation modelling approach,Journal of Construction in Developing Countries,
Vol. 20 No. 1, pp. 65-83.
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Chan, W.M. and Kumaraswamy, M.M. (1995), Differing perceptions as to general causes of
construction time overruns in Hong Kong,Proc., 11th Annual ARCOM Conference, Association
of Researchers in Construction Management,York, UK, pp. 318-329.
Chang, A.S., Shih, J.S. and Choo, Y.S. (2011), Reasons and costs for design change during production,
Journal of Engineering Design, Vol. 22 No. 4, pp. 275-289.
Chen, G.X., Shan, M., Chan, A.P.C., Liu, X. and Zhao, Y.Q. (2017), Investigating the causes of delay in
grain bin construction projects: the case of China,International Journal of Construction
Management, pp. 1-14.
Development Management, Theory and Practice (2017), Routledge studies in development economics,
available at: www.routledge.com/Development-Management-Theory-and-practice/Bawole-
Hossain-Ghalib-Rees-Mamman/p/book/9781138646414
Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S. (2012), Analysing causes affecting delays in indian
construction projects,International Journal of Project Management, Vol. 30 No. 4, pp. 479-489.
Ellis, R.D. and Thomas, H.R. (2002), The root causes of delays in highway construction,Submitted for
Presentation at the 82nd Annual Meeting of the Transportation Research Board,Washington,
DC, January 12-16, 2003.
Ernst, Young, L.L.P. (2014), Engineering procurement andConstruction (EPC), making India brick by
brick, India, available at: www.ey.com/Publication/vwLUAssets/EY.../EY-making-india-
brick-by-brick.pdf
Faridi, A.S. and El-Sayegh, S.M. (2006), Signicant factors causing delay in the UAE construction
industry,Construction Management and Economics, Vol. 24 No. 11, pp. 1167-1161,176.
Frimpong, Y., Oluwoye, Y. and Crawford, L. (2003), Causes of delay and cost overruns in construction
of groundwater projects in a developing countries; Ghana as a case study,International Journal
of Project Management, Vol. 21 No. 5, pp. 321-326.
Holt, G.D. (2014), Asking questions, analysing answers: relative importance revisited,Construction
Innovation, Vol. 14 No. 1, pp. 2-16.
Hwang, B.-G., Zhao, X. and Ng, S.I. (2013), Identifying the critical factors affecting schedule
performance of public housing projects,Habitat International, Vol. 38, pp. 214-221.
Ibbs, W. and Vaughan, C. (2015), Change and the loss of productivity in construction: a eld guide,
available at: www.ibbsconsulting.com/uploads/Changes_Field_Guide_Feb_2015.pdf
Infrastructure and Project Monitoring Division (Ministry of Statistics and Programme Implementation,
Government of India) (2018), Flash report 2018, [online] available at: www.cspm.gov.in/
english/lsmfr.htm
Infrastructure today (2011), EPC: who should be responsible for our projects?, Feb, available at: www.
infrastructuretoday.co.in
Islam, M.S. and Trigunarsyah, B. (2017), Construction delays in developing countries: a review,
Journal of Construction Engineering and Project Management, Vol. 7 No. 1, pp. 1-12.
Ismail, S. (2007), Productivity performance of the construction sector,Malaysian Construction
Research Journal, Vol. 1 No. 1, pp. 67-73.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997), Causes inuencing construction time
and cost overruns on high-rise projects in Indonesia,Construction Management and Economics,
Vol. 15 No. 1, pp. 83-94.
Kasimu, A.M. and Abubakar, D.I. (2012), Causes of delay in Nigeria construction industry,
International Journal of Contemporary Research in Business, Vol. 4 No. 2, pp. 785-794.
Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A. (2012), Causes of delays in construction projects in
Turkey,Journal of Civil Engineering and Management, Vol. 18 No.3, pp. 426-435.
Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005), Delays and cost increases in the construction of
private residential projects in Kuwait,Construction Management and Economics, Vol. 23 No. 3,
pp. 285-294.
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
KPMG (2015), Climbing the curve, global construction survey, available at: https://assets.kpmg.com/
content/dam/kpmg/.../global-construction-survey-2015.pdf
Kwoe, T.E., Fugar, F., Adinyira, E. and Ahadzie, D.K. (2014), Identication and classication of the
unique features of mass housing projects,Journal of Construction Engineering, Vol. 2014,
pp. 1-10.
Larsen, J.K., Qiping Shen, G., Lindhard, S.M. and Brunoe, T. (2015), Factors affecting schedule delay,
cost overrun, and quality level in public construction projects,Journal of Management in
Engineering, Vol. 32 No. 1, available at: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391
Livemint (2015), L&T stretches out payment cycle to manage cash ows, available at: www.livemint.
com
Lo, T.Y., Fung, I.H. and Tung, K.F. (2006), Construction delays in Hong Kong civil engineering
projects,Journal of Construction Engineering and Management,Vol.132No.6,
pp. 636-649.
Love, P.E.D., Li, H., Irani, Z., Treloar, G.J. and Faniran, O.O. (2000), MiDiCON: a model for mitigating
delays in construction, Paper presented at the 1st International Conference on Systems
Thinking in Management, ICSTM2000. Geelong, Australia, 8-10, November.
Manseld, N.R., Ugwu, O.O. and Doran, T. (1994), Causes of delay and cost overruns in nigerian
construction projects,International Journal of Project Management, Vol. 12 No. 4, pp. 254-260.
Marzouk, M. and El-Rasas, T.I. (2014), Analyzing delay causes in egyptian construction projects,
Journal of Advanced Research, Vol. 5 No. 1, pp. 49-55.
Mezher, T.M. and Tawil, W. (1998), Causes of delays in the construction industry in Lebanon,
Engineering, Construction and Architectural Management, Vol. 5 No. 3, pp. 252-260.
Mohamad, M., Nekooie, M. and Al-Harthy, A. (2012), Design changes in residential reinforced concrete
buildings: the causes, sources, impacts and preventive measures,Journal of Construction in
Developing Countries, Vol. 17 No. 2, pp. 23-44.
Ng, L.F. (2007), Determinant factors of implementing build then sell in Malaysia: housing developers
point of view, MSc Diss., Universiti, Sains Malaysia, Pulau Pinang, Malaysia.
Nuclear Energy Institute (NEI) (2012), Job creation and economic benets of nuclear energy, available
at: www.nei.org
Odeh, A.M. and Battaineh, H.T. (2002), Causes of construction delay: traditional contracts,
International Journal of Project Management, Vol. 20 No. 1, pp. 67-73.
Odeyinka, H.A. and Yousif, A. (1997), The causesand effects of construction delays on completion cost
of housing projects in Nigeria,Journal of Financial Management of Property and Construction,
Vol. 2, pp. 31-44.
Ogunlana, S.O., Promkuntong, K. and Jearkjirm, V. (1996), Construction delays in a fast-growing
economy: comparing Thailand with other economies,International Journal of Project
Management, Vol. 14 No. 1, pp. 37-45.
Olatunde, N.A. and Alao, O.O. (2017), Quantitative appraisal of cost and time performance of
construction projects in public and private universities in Osun state, Nigeria,Journal of
Engineering, Design and Technology, Vol. 15 No. 5, pp. 619-634.
Olawale, Y.A. and Sun, M. (2010), Cost and time control of construction projects: inhibiting causes and
mitigating measures in practice,Construction Management and Economics, Vol. 28 No. 5,
pp. 509-526.
Planning commission (Government of India) (2013), Twelfth Five Year Plan (2012-2017) Economic
Sectors, SAGE Publications, Vol. 2, available at: http://planningcommission.gov.in/plans/
planrel/12thplan/pdf/12fyp_vol2.pdf
Pourrostam, T. and Ismail, A. (2012), Causes and effects of delay in iranian construction projects,
IACSIT International Journal of Engineering and Technology, Vol. 4 No. 5, pp. 201-203.
Causes of
delay
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
Prasad, K.V. and Vasugi, V. (2017), Delays in construction projects: a review of causes, need and scope
for further research,Malaysian Construction Research Journal, Vol. 23 No. 3, pp. 89-113.
Press Information Bureau (PIB) (2016), Cabinet approves initiatives to revive the construction sector.
available at: http://pib.nic.in
PWC (2008), Infrastructure in India: a vast land of construction opportunity, available at: www.pwc.
in/assets/pdfs/infrastructure-in-india.pdf
Sambasivan, M. and Soon, Y.W. (2007), Causes and effects of delays in malaysian construction
industry,International Journal of Project Management, Vol. 25 No. 5, pp. 517-526.
Santos, J.A. (1999), Cronbachs alpha: a tool for assessing the reliability of scales,Journal of Extension,
Vol. 37 No. 2, pp. 1-5.
Scholarly Editions (2013), Issues in issues in innovation, indicators, and management in technology,
pp. 99-99, available at: www.scholarlyeditions.com
Semple, C., Hartman, F.T. and Jergeas, G. (1994), Construction claims and disputes: causes and
cost/time overruns,Journal of Construction Engineering and Management, Vol. 120 No. 4,
pp. 785-795.
Shebob, A., Dawood, N., Shah, R.K. and Xu, R.(2012), Comparative study of delay causes in libyan and
the UK construction industry,Engineering, Construction and Architectural Management,
Vol. 19 No. 6, pp. 688-712.
Shehu, Z., Endut, I.R. and Akintoye, A. (2014), Factors contributing to project time and hence cost
overrun in the malaysian construction industry,Journal of Financial Management of Property
and Construction, Vol. 19 No. 1, pp. 55-75.
Stumpf, G. (2000), Schedule delay analysis,Cost Engineering Journal, Vol. 42 No. 7, pp. 32-43.
Sweis, G., Sweis, R., Hammad, A.A. and Shboul, A. (2006), Delays in construction projects: the case of
Jordan,International Journal of Project Management, Vol. 26 No. 6, pp. 665-674.
Toor, S.R. and Ogunlana, S. (2008), Problems causing delays in major construction projects in
Thailand,Construction Management and Economics, Vol. 26 No. 4, pp. 395-408.
Vilventhan, A. and Kalidindi, S.N. (2016), Interrelationships of factors causing delays in the relocation
of utilities: a cognitive mapping approach,Engineering, Construction and Architectural
Management, Vol. 23 No. 3, pp. 349-368.
Wong, K. and Vimonsatit, V. (2012), A study of the factors affecting construction time in Western
Australia,Scientic Research and Essays, Vol. 7 No. 40, pp. 3,390-3,398.
World Bank (1997), Hydropower dams and social impacts: a sociological perspective, Social
Assessment Series, Paper No. 16, January 1997.
Zewdu, Z.T. (2016), Construction projects delay and their antidotes: the case of ethiopian construction
sector,International Journal of Business and Economic Research, Vol. 5 No.4, pp. 113-122.
Corresponding author
Vasugi V. can be contacted at: vasugi.v@vit.ac.in
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com
JFMPC
Downloaded by Mr K V Prasad At 05:07 22 January 2019 (PT)
... Figure 1 summaries the root causes of the project postponement from previous researchers. Venkatesan (2019) state that, changes of scope by owner during construction, changes in design by owner, failure to provide construction site by owner, delay by owner in revision and approval of design documents and owner's slow decision making process are found to be the causes of project postponement. Late release budget or funds is one of the most important cause of project delay. ...
... Soomro et al., 2019;Venkatesan, 2019; Hasmori et al., 2018). Inflation or price increases in material also has been identified as a major cause of project postpone(Ramli et al., 2018). ...
Article
Full-text available
The number and frequency of claims in the current context of very complex and heavy budgeted projects in India are noticeably high which have negative impacts on the budgetary of owners and cause losses of liquidities and restrictions in cash flow for contractors. This study is conducted to determine the main causes of claims and their sources in Indian construction industry. Further, the study is conducted to determine the frequency of different claim types in Indian construction projects, and to provide recommendations and suggestions to avoid/mitigate claims in Indian construction industry. The objectives of the study have been achieved through a valid questionnaire that was distributed and obtained from different contractor's construction organizations working in Indian construction industry. The results showed that the most important factors that contributed to the generation of claims are delay in handing over site, variation between actual and original quantities, excessive change orders by owner, delay of shop drawings approval by owner's representative, and scope change of the project. The results also showed that the most frequent claim type in Indian construction projects is extra-work claims.
Article
Full-text available
The Ethiopian construction sector has shown a remarkable growth and is given high prominence. However, several defects are being noted in the sector that need immediate action. The current study was conducted to access the level of techniques and software packages used for project time control; to identify factors affecting delay in construction projects and to recommend possible mitigation measures. The study adopts quantitative and qualitative methods with the help of primary and secondary data. Primary data was collected using self-administered questionnaires on 140 respondents and key informant interviews with ten experienced practitioners in the construction sector. Secondary data was collected through reviewing of related materials. Analysis of the quantitative data was made using SPSS version 20. The study revealed low level application of techniques and software packages for project planning and time control. It also identified top five delay factors. The study suggested that current project planning and time control can be improved by adopting the right tools, assigning the appropriate staff. The study implied that delay factors can be managed by proactive planning on alternative resources, appropriate allocation of resources, application of timely knowledge based decisions, and adoption and application of suitable methodologies and resources at the right place and time coupled with provision of continuous trainings for the staff.
Article
Full-text available
Abstract Infrastructure plays a key role & governs the economic development of any nation. It is needless to mention that infrastructure development & economic growth go hand in hand. However, construction projects which service the infrastructure requirements are plagued by a phenomenon of global occurrence: "Delays & Cost Overruns". The primary purpose this paper is to identify the critical causes of delays and mitigation strategies globally, identify the gaps in literature and present the scope for future research work, aimed at an improvement in construction project delivery. Fifty three research articles on causes of delays in different countries were reviewed in this study. Based on the country of research work, literature is segregated among developing and developed countries so as to distinctly compare and analyze the causes in these economies. The findings from the review of literature clearly indicated that the causes of delay vary from country to country; especially the critical causes in a developing country are quite different than in a developed country. Top ten causes of construction project delay in developing economies and developed economies are identified. The paper has presented the gaps in past studies and discussed the scope, direction for future research studies with the objective to address the root cause of construction project delays.
Article
Full-text available
Construction delay is one of the basic constrains to achieve the project objectives in developing countries. This study aims to find the causes and effects of construction delays in developing countries. A thorough literature review has been done following the content analysis method. The relevant literature of 28 developing countries was collected from the scholarly journals published in the period of 2006 to 2016. The different developing countries are grouped into three geographic regions, i.e. South and Southeast Asia, Middle East, and Africa. In these regions, total 53 potential causes of delay under 8 major groups are identified. Frequency and ranking of these factors have been done. The factors, delay in progress payment by owner, contractors' cash flow problem, improper planning and scheduling, poor site management, and change order by owner during construction, are acknowledged as critical causes of delay in developing countries. This study will assist both academic and professional experts providing more insight about the construction delays and project management in developing countries.
Article
Full-text available
The prevalent view in the economics literature is that a high level of infrastructure investment is a precursor to economic growth. China is especially held up as a model to emulate. Based on the largest dataset of its kind, this paper punctures the twin myths that (i) infrastructure creates economic value, and that (ii) China has a distinct advantage in its delivery. Far from being an engine of economic growth, the typical infrastructure investment fails to deliver a positive risk-adjusted return. Moreover, China’s track record in delivering infrastructure is no better than that of rich democracies. Investing in unproductive projects results initially in a boom, as long as construction is ongoing, followed by a bust, when forecasted benefits fail to materialize and projects therefore become a drag on the economy. Where investments are debt-financed, overinvesting in unproductive projects results in the build-up of debt, monetary expansion, instability in financial markets, and economic fragility, exactly as we see in China today. We conclude that poorly managed infrastructure investments are a main explanation of surfacing economic and financial problems in China. We predict that, unless China shifts to a lower level of higher-quality infrastructure investments, the country is headed for an infrastructure-led national financial and economic crisis, which is likely also to be a crisis for the international economy. China’s infrastructure investment model is not one to follow for other countries but one to avoid.
Article
Purpose The purpose of this paper is to compare the cost and time performance of construction projects in public and private universities in Osun State, Nigeria. Design/methodology/approach Purposive sampling technique was adopted to select four universities (two public and two private) used for the study. Archival data on 40 completed construction projects (ten from each university) was used in the study. Data were analysed with percentile and t-test. Findings The study showed that only 35 per cent of the construction projects in public and 10 per cent of those in private universities were completed at the estimated cost. There were no construction projects completed within the planned time in public universities, but 20 per cent were completed within the planned time in private universities. The t-test showed there is no significant difference in performance of construction projects in public and private universities in Nigeria. The study concluded that time performance of public and private universities in Nigeria was still below acceptable international best practices. Research limitations/implications The findings of this study are limited to universities’ construction projects and may be of little application to other construction projects outside university settings. Practical implications It is recommended that construction stakeholders be more proactive in ensuring that significant improvement is achieved in cost and time performance of construction projects both in public and private universities; the clients need to be more detailed in their briefs and requirements, the designers (architects and engineers) need to be more precise and avoid varying their designs, the quantity surveyors should use their professional competency in cost engineering adequately and the contractor should avoid spurious claims that result in increase in construction cost and time so that performance of construction projects can be improved. Originality/value The study is an attempt to compare cost and time performance of construction projects in public and private universities in Osun State, Nigeria.
Article
Construction delay is a common issue in diverse types of projects and has attracted sustained attention from the industry and academia. However, it has seldom been addressed in grain bin projects which have a stricter requirement for on-time delivery to ensure prompt and appropriate grain storage. The aim of this study is to investigate the significant causes of delay in grain bin construction projects in China. To achieve this goal, a comprehensive literature review and 15 structured interviews were carried out, and a self-administered questionnaire was sent out to 108 respondents with experiences in constructing grain bin projects. Results showed that the top five delay causes for grain bin construction projects were ‘shortage of adequate equipment,’ ‘poor communication among contracting parties,’ ‘problems with subcontractors,’ ‘inadequate experience of the design team’ and ‘frequent change orders by clients.’ Also, results showed that the most significant delay cause category in grain bin construction projects was contractor-related causes. This study has provided the industry and academia with a deep understanding of the delay issue ingrain bin construction projects, which has also reinforced the knowledge body of delay research in the construction engineering and management domain.
Article
The housing industry is one of the major contributors to the economy in Malaysia due to the constantly high housing demand. The housing demand has increased due to the rapid growth in population and urbanisation in the country. One of the major challenges in the housing industry is the late delivery of housing supply, which in some instances leads to sick and abandoned housing projects. Despite being extensively investigated, this delay is still a common phenomenon of the housing industry in Malaysia. As delay in delivery could result in a negative impact, there is a strong need to review the housing delay mitigation measures practised in Malaysia. This paper aims to evaluate the current delay mitigation measures and its main objective is to explore the relationship between the mitigation measures and delay in housing via a Structural Equation Modelling (SEM) approach. A questionnaire survey through an online survey tool was conducted across 13 states and three Federal Territories in Malaysia. The target respondents are the local authorities, developers, consultants (principal submitting persons) and contractors. The findings show that 17 mitigation criteria can be extracted using principal component analysis. These measures were categorised as predictive, preventive, organisational or corrective. This paper demonstrates that preventive measures are the most influential mitigation measures for housing delivery delay.
Article
Delays are major problems that face the Western Australia’s construction industry. Delays can lead to many negative effects such as cost overruns, and is of high concern to those who are involved in the construction industry. This study was set to identify the major causes of delays in the Western Australian construction industry, by means of a literature review and a questionnaire survey. A total of 48 delay factors were obtained from literature review and were further categorised into eight major groups that contributed to the causes of delay. The questionnaire survey was distributed to the targeted respondents from a combination of clients, contractors, and consultants in Perth, Western Australia. About 32 respondents participated in the survey. Based on the data received, albeit limited, the top ten most important causes identified were: (1) Shortage of skills; (2) Financial difficulties; (3) Shortage of labour; (4) Unrealistic deadlines for project completion; (5) Unforeseen ground conditions; (6) Poor organization of the contractor or consultant; (7) Poor communication; (8) Underestimation of time of completion; (9) low speed of decision; and (10) Design errors made by designers.
Article
Purpose – Relocation of utilities is a major source of delay in Indian infrastructure projects. This delay is particularly critical in road and bridge construction projects. The purpose of this paper is to identify the various factors and also the interrelationships between the factors which influence the delays in the relocation of utilities. Design/methodology/approach – Case studies were conducted on 11 road and bridge projects in India with varying levels of complexity and size. Factors causing relocation delays were identified using computer aided qualitative analysis methodology. Cognitive mapping technique was used to map the interrelationships between the factors and to identify the critical delay factors. Findings – Factors affecting delays were identified across two groups, namely, technical and organizational factors. The study offers insights into the kinds of interactions of factors that can lead to delays in a project. The critical factors causing delays were identified as slow response from utility agencies, difficulty in identification of underground utilities, lack of information on underground utilities and conflict between agencies. Research limitations/implications – The limitations of the study are that the interview respondents are not evenly distributed among the type of organizations which may have induced some bias in responses. The impact of the utility relocation delays on the overall project delay has to be detailed further. Practical implications – The interrelationships between factors has the potential to help the officials of highway department, contractors, utility agencies and others understand how various interactions/linkages of factors contributes to delays in utility relocations. Recommendations are provided for the practical use and to reduce the impact of delays. Originality/value – Utility relocation has received very little attention in the extant literature and this paper seeks to contribute to knowledge in this area by identifying the linkages between factors and the critical factors of utility relocation delays in India.