A State-of-the-Practice Survey of Risk Management in Development with Off-the-Shelf Software Components

Authors:

Abstract and Figures

An international survey on risk management in software development with off-the-shelf (OTS) components is reported upon and discussed. The survey investigated actual risk-management activities and their correlations with the occurrences of typical risks in OTS component-based development. Data from 133 software projects in Norway, Italy, and Germany were collected using a stratified random sample of IT companies. The results show that OTS components normally do not contribute negatively to the quality of the software system as a whole, as is commonly expected. However, issues such as the underestimation of integration effort and inefficient debugging remain problematic and require further investigation. The results also illustrate several promising effective risk-reduction activities, e.g., putting more effort into learning relevant OTS components, integrating unfamiliar components first, thoroughly evaluating the quality of candidate OTS components, and regularly monitoring the support capability of OTS providers. Five hypotheses are proposed regarding these risk-reduction activities. The results also indicate that several other factors, such as project, cultural, and human-social factors, have to be investigated to thoroughly deal with the possible risks of OTS-based projects.
Content may be subject to copyright.
1
A State-of-the-Practice Survey on Risk
Management in Development with Off-
The-Shelf Software Components
Jingyue LI, Reidar CONRADI, Odd Petter N. SLYNGSTAD, Marco TORCHIANO, Maurizio
MORISIO, Christian BUNSE
Abstract-- An international survey on risk management in software development with OTS (Of-The-Shelf) components
is reported upon and discussed. Most studies on project risk management in this area have been limited to theoretical
proposals or case studies in specific project contexts. Without validation from representative, large-scale industrial
projects, it is difficult for project managers to use the proposed risk-management guidelines properly and efficiently on
new projects. The survey investigated actual risk-management activities and their correlations with occurrences of typical
risks in OTS component-based development. Data from 133 software projects in Norway, Italy and Germany were
collected using a stratified random sample of IT companies. Results show that OTS components normally do not
contribute negatively to the quality of the software system as a whole, as commonly believed. However, issues such as
underestimation of integration effort and inefficient debugging remain problematic and require further investigation.
Results also illustrate several promising effective risk reduction activities, such as: putting more effort into learning
relevant OTS components, performing integration testing early and incrementally, evaluating the quality of candidate
OTS components thoroughly, and regularly monitoring the support capability of OTS providers. Five hypotheses have
been proposed regarding these risk reduction activities and deserve further confirmative studies.
Index Terms--D.2.13. Software Engineering/Reusable Software, D.2.9. Software Engineering/Management, D.2.18.
Software Engineering/Software Engineering Process
I. INTRODUCTION
ong-term success in commercial software development is becoming increasingly
challenging. Clients of development companies expect software systems that follow industry
standards, are of high quality and reasonable priced, and have a short time to market. Hence,
software companies are finding it increasingly difficult to protect their technology investments
and maintain productivity levels. As a result, the software industry is turning to approaches that
promise a larger than normal return on investment (e.g., concerning software development
effort). Component-based software development (CBSD) [1] is believed to be one such
approach, since it is based on the idea of develop/buy once and use often. By reusing
L
Jingyue Li is with the Norwegian University of Science and Technology (NTNU), Trondheim, NO-7491 Norway. Email: jingyue@idi.ntnu.no
Reidar Conradi is with NTNU, Trondheim, NO-7491 Norway, Email: conradi@idi.ntnu.no
Odd Petter N. Slyngstad is with NTNU, Trondheim, NO-7491 Norway, Email: oslyngst@idi.ntnu.no.
Marco Torchiano is with Politecnico di Torino, I-10129 Torino, Italy, Email: torchiano@polito.it
Maurizio Morisio is with Politecnico di Torino, I-10129 Torino, Italy, Email: morisio@polito.it
Christian Bunse is with the International University in Germany, D-76646 Bruchsal, Germany, Email: Christian.Bunse@i-u.de
2
Commercial-Off-The-Shelf (COTS) and Open Source Software (OSS) components (collectively
called OTS components), in addition to components made in-house, the expected benefits
increase even more. Unfortunately, using such external components introduces a number of
additional risks. One is the fact that the functionality and quality of a candidate component may
be unknown. Another is the market-related instability of a component provider, who may
terminate maintenance support [2] [3] [4] [5]. Thus, project managers have to identify and
evaluate possible risks before deciding to acquire an external component instead of developing
and reusing an in-house component. Several risks and risk-reduction activities in OTS-based
development have been identified by previous case studies [2]-[12]. (A risk-reduction activity is
an activity that is designed to minimize a particular risk or group of risks, i.e., to minimize the
probability that a problem corresponding to the risk(s) will occur.) However, few subsequent,
large-scale empirical studies have confirmed the conclusions of these studies. As a result,
software project managers have only a few effective and well-proven guidelines for assessing the
various risks and for deciding upon effective methods of reducing them. Our study is the first
step to empirically validate effectiveness of the proposed risk-reduction activities, i.e. investigate
state-of-the-practice in large scale and formulate hypotheses. We consider a scenario concerning
the (re)use of OTS components such that they will be integrated into a new software system or
product. Thus, our focus is on a software developer who plays a combined role; that of a project
manager/system integrator.
The background of the survey presented in this article was inspired by a qualitative study [13]
in 2002 of COTS usage in seven IT companies in Norway and Italy. The study identified six
“theses” on COTS usage, which theses partly challenge commonly held beliefs. To build upon
this previous study, we conducted a qualitative prestudy [14] in 2003 by performing structured
3
interviews. We interviewed 16 industrial developers from 13 IT companies in order to
summarize lessons learned from experience of COTS-based development. The principal insights
of this prestudy were (i) that COTS-related activities can be integrated successfully into most
development processes (incremental and waterfall), and (ii) that components are habitually
selected in an ad-hoc manner, using either in-house expertise or web-based search engines. This
led us to conclude that there is a need to store component-related experience in a systematic
manner.
The study presented herein is a quantitative follow-up of the qualitative prestudy [14]. It was
performed from May 2004 to August 2005and addressed IT companies in Norway, Italy and
Germany. The survey performed postmortem investigations on the actual problems and risk-
reduction activities in 133 completed OTS component-based projects. The study addressed three
research questions:
RQ1: Which problems occurred more frequently than others?
RQ2: Which risk-reduction activities were performed most frequently?
RQ3: Which risk-reduction activities were promising for avoiding particular risks?
It was, of course, a necessary precondition for addressing RQ1 that we first identified the
problems that occurred. The results showed that the most frequent problems in OTS-based
development are effort underestimation and costly identification of the location of defects. It is
worthy of note that problems regarding the quality of OTS components do not occur frequently,
which is commonly believed. The results also illustrate several promising risk-reduction
activities to ensure the success of OTS component-based development, such as: study and
understand the OTS components completely, evaluate their quality thoroughly, maintain a
continual watch on the reputation of providers and their ability to provide support, limit the
4
number of different components used in one project, and manage and share the company’s
knowledge on OTS components. Several hypotheses have been proposed based on the
effectiveness of these risk-reduction activities upon certain risk items.
The remainder of the paper is organized as follows: Section 2 presents related work. Section 3
discusses the research design and related research questions. Profiles of the collected samples are
presented in Section 4. Section 5 presents the empirical results of the research questions. Section
6 contains discussions of the results. Section 7 concludes, notes unresolved issues, and states
intentions for further work.
II. RELATED WORK
A. Risk management in software development
Risks are factors that may adversely affect
a project, unless project managers take
appropriate countermeasures. Risk
management includes two primary steps, i.e.,
risk assessment and risk control, each with
three subsidiary steps as described by Boehm
[15] and shown in Figure 1.
Risk identification produces lists of project-
specific risk items that are likely to
compromise the success of a project. Several lists of possible risks in software projects have been
compiled [16] [17] [18], and classified [19]-[23]. Risk analysis and risk prioritization rank the
identified risk items by assessing the probability and severity of the loss for each risk item. Risk
management planning defines how risk reduction will be conducted in a particular project by
Fig.1. Risk Management Framework
5
defining, among other things, risk-reduction tasks, responsibilities, activities, and budget. Risk-
reduction activities must take into account viewpoints regarding process [24], organization [21],
[25], and technology [26]. Risk resolution produces a situation in which the risk items are
eliminated or otherwise resolved. Risk monitoring involves tracking the progress of a project
towards resolving its risk items and performing corrective activities where appropriate.
Risk management is particularly important in the context of software development projects,
due to the inherent uncertainties that most software projects face. Project management has to
anticipate risks, understand their impact on the project, and take steps to avoid them [27, p.105].
Although previous studies have identified risk items [16]-[23], different risk taxonomies may be
required by different project contexts, because building one complete and universally applicable
risk taxonomy is quite unrealistic [28]. Although several risk-reduction strategies have been
proposed [21] [24] [25] [26], there is a growing demand for empirical research to provide
information about the efficiency of proposed risk-reduction tools and techniques [29].
B. Specific risk management in development with OTS components
When doing research in the area of component-based development, the most prevalent issue
concerns what constitutes a component. Of course, there are standard definitions, such as those
provided by [30] or [31]. However, these definitions might differ from the view of component
marketplaces, such as ComponentSource.com and SourceForge.net. In order to define a common
basis within this study, we used the following definitions:
- Component: A program unit of independent production, acquisition, and deployment
that can form part of a functioning system. We limit ourselves to components that it
has been decided explicitly to build from scratch or acquire externally as an OTS-
component. That is, such components are not shipped with the operating system, not
6
provided by the development environment, and not included in any pre-existing
platform. This means that platform (“commodity”) software, e.g., Linux, DBMSes,
various servers, or similar software, is not considered. Furthermore, components
usually follow some component model, as expressed by the COM, CORBA, EJB, .Net,
or Web Service standards, or they can be a C++/Java library.
- OTS component: A component provided by a commercial COTS vendor or obtained
from the Open Source community. OTS components may come with certain
obligations, e.g., payment or licensing terms. Further, control over features and their
evolution lies mostly with the provider. The source code of an OTS component is not
usually modified, even if it is available.
OTS component-based development encompasses three primary types of stakeholder:
component developers, application assemblers/integrators, and clients. Different stakeholders
might experience different risks and challenges [11]. This study focuses on risk-management
issues in the context of OTS-based development; hence, we only investigate those risks that are
relevant to the assemblers or integrators of the application. Further, since the term OTS
component covers both COTS and OSS
components, we have to limit ourselves to
risks and risk-reduction activities that address
common issues in component-based
development, COTS-based development, and
OSS-based development. This range of issues
is shown in Figure 2.
Several studies have been conducted that investigate the challenges, risks, and risk-
Fig. 2. OTS Component-based Development Risks
7
management strategies involved in developing software with OTS components (see Table 1 for a
summary of their findings). An examination of their results reveals that the risk items that were
identified are based on either common-sense assumptions [32] or small, non-representative case
studies [8] [9] [12] [33] [34]. Without evidence from large-scale empirical studies, it is difficult
to convince practitioners that the risk items identified constitute typical problems that need to be
addressed prior to starting a project. Without knowing the frequency of occurrence of typical
problems, it is difficult for practitioners to estimate the likelihood that identified risk items will
result in corresponding problems arising in the project and to prioritize the risks. Furthermore,
most of the risk-reduction strategies that have been proposed are derived from lessons learned
from experience or best-practice know-how. Best practices may contribute positively to the
project as a whole [14]. However, it is not clear which particular best practice might serve to
reduce the probability that a problem corresponding to a particular risk item might occur during
the project. Thus, further investigation is required if the preconditions and possible benefits of
using best practices are to be identified. In addition, different risk-reduction strategies may have
been proposed to reduce the likelihood that a risk item will occur as a problem during the project.
For example, to reduce the risk of selecting an improper OTS component, components may be
selected on the basis of project requirements and negotiation with clients [2] [3]. Another
proposed risk-reduction strategy is to focus more on matches with the proposed architecture than
requirements [13]. Without being able to consult the findings of empirical studies that compare
the effectiveness of different strategies, it is difficult for practitioners to focus on the most cost-
effective risk-reduction activities.
8
TABLE 1 STUDIES ON RISK AND RISK MANAGEMENT IN OTS COMPONENT-BASED DEVELOPMENT
Study unit Result/finding Examples*
Identified the specific challenges of using COTS software by
comparing with everything built in-house [32]. Choosing the wrong COTS software may be more
expensive than building it in-house.
Summarized lessons learned from COTS-based university
projects and proposed corresponding risk-management strategies
[3].
Overly optimistic COTS learning curve (a more
likely learning curve must be assessed during
planning and scheduling).
Summarized 10 risk factors in COTS-based development and
proposed risk-reduction activities [8]. Risk factor: rapid and asynchronous changes.
Risk factor: different quality practices.
COTS in
general1
Summarized COTS lessons learned from several industrial case
studies [33]. Choosing an appropriate vendor is important for
success.
OSS in
general2 Identified possible problems of development with OSS in
industrial settings [9] [12] [34]. If the OSS-based system has no proper license
permission, the licensor may claim damages.
CBSD 3 Identified challenges to, and inhibitors of, component-based
development [35]. Component-based development lacks engineering
methods.
Identified and classified possible risks in COTS component-
based development in different development phases, and
proposed corresponding risk-management strategies to mitigate
the risks [2].
COTS components may have asynchronous update
cycles (try to involve senior analyst in analysis of
the updates and derive effective field upgrade
procedure and schedules).
Summarized challenges in COTS component-based development
[36]. There is insufficient information to evaluate COTS
component in the market.
COTS
component4
Summarized problems and good practices in COTS component-
based development [14]. Problem occurred: the learning effort was
underestimated.
Good practice: do integration testing early and
incrementally.
*Examples of the proposed risk-management strategies are in brackets.
1COTS in general: any software bought from third-party companies.
2OSS in general: any software acquired from the Open Source community.
3CBSD: using components without differentiating between in-house built COTS, or OSS components.
4COTS component: software component bought from third-party companies
III. RESEARCH DESIGN
In practice, the creation of a project management plan requires project managers to first
estimate the likelihood that a problem corresponding to a particular risk will arise during the
project, how much effort is needed to perform a specific risk-reduction activity, and how risks
might systematically be managed. In order to help project managers to predict the probability
that problems that correspond to a particular risk will arise during the project and to plan risk
management efficiently, it is necessary to summarize practices and results of risk-reduction
activities from past projects (e.g., in the form of guidelines that may be tailored to different
organizations). This being so, the motivation for the research is to perform a posteriori
measurements and collect experience based on both actual project risks and the impact of
performed risk-reduction activities. This study is designed to be exploratory; to report on the
state of the practice, and to generate hypotheses for further testing.
9
A. Research questions
As mentioned in Section II, previous studies identified risk items on the basis of a few case
studies, without knowing whether the identified risks occur frequently or happened incidentally.
Our first research question RQ1, as shown in Figure 3, was designed to determine the relative
frequency with which particular risks were
present in various OTS component-based
development projects. In general, the abstract
OTS-based development process consists of
the following phases [37]: the assessment
and selection of OTS components, the
tailoring and integration of OTS components,
and the maintenance of OTS and non-OTS
parts of the system. Each phase of OTS-
based development has risks, which can be
classified as relating to integrating the application (e.g., satisfying requirements), project
management (e.g., quality control), and marketing (e.g., vendor relationship) [11]. To identify
risks that pertain to software development with OTS components, we performed a systematic
review of the literature, which resulted in our selecting a number of publications ([2] [3] [10]
[11] [12] [14]). These papers listed risk items on the basis of experience or lessons learned. We
believe that these items may occur frequently in practice and warrant further investigation. From
the publications, we selected those risk items (see Table 2) that satisfy the following criteria:
Fig. 3. Research questions
- The risk item must be a common issue in CBSD-, COTS-, and OSS-based
development. This resulted in the exclusion of a number of items. For example, risks
10
relevant to OSS licensing [12] were excluded because they rarely occur in COTS-
based development.
- The risk item should be relevant only to the assemblers or integrators of the
application. This also resulted in a number of items being excluded; for example, risks
related to the producers of components in [11].
TABLE 2 TYPICAL RISKS IN OTS COMPONENT-BASED DEVELOPMENT
Stage Issue Risk item Description
Project manag. Selection effort Effort to select OTS components is not estimated satisfactorily [3].
Project manag. Integration effort Effort to integrate OTS components is not estimated satisfactorily [2].
Integration Negative reliability OTS components affect system reliability negatively [10] [11] 12].
Integration Negative security OTS components affect system security negatively [10] [11] [12].
Integration Negative perform. OTS components affect system performance negatively [10] [11] [12].
Integration Follow req. changes OTS components cannot be adapted sufficiently to changing requirements [3].
Integration Negotiate req. It is not possible to (re)negotiate requirements with the client, if OTS components do not
satisfy all requirements [14].
Integration Locate defect It is difficult to identify whether defects lie inside or outside the OTS components [3].
Selection and
integration
Integration Incompatible deploy OTS components are not sufficiently compatible with the production environment when
the system is deployed [11].
Project manag. Plan maintenance It is difficult to plan system maintenance, because different OTS components have
asynchronous release cycles [2].
Project manag. Update comp. It is difficult to upgrade the system with the last OTS component version [2].
Vendor
relation Lack provider info. Information about the reputation and technical support ability of the provider is
inadequate [2] [9].
Maintenance
Vendor
relation Lack support The provider does not provide sufficient technical support/ training [2] [9].
As discussed in Section II, the majority of published risk-reduction strategies are based on a
few case studies with specific contexts. To convince practitioners to apply these strategies, it is
important to demonstrate that the strategies have been used successfully with positive results.
Therefore, the purpose of our second research question RQ2 (see Figure 3) was to investigate the
application of risk-reduction activities in actual industrial projects. We selected a set of risk-
reduction strategies (see Table 3) using the process and criteria as for the risk items from the
literature [2] [3] [8] [13] [14].
The purpose of the third research question RQ3 was to examine the correlation between the
level of risk presence and the degree to which risk-reduction activities were adopted. If we found
a significant negative correlation between the performed risk-reduction activity and the actual
11
occurrence of a certain risk, we assumed that the risk-reduction activity may have helped to
reduce the likelihood that the risk item would occur as a problem for the project. For a specific
risk, we were interested in the most effective reduction strategy. In addition, we hypothesized
that the capability to cope with the project risks is also contingent upon several factors that
pertain to the context of a project. These include business characteristics (time-to-market
pressure and project budget) and technology characteristics (project complexity and quality
requirements). We also expected that individual project members’ experience of OTS-based
development is an important predictor for managing risks successfully. In addition to
investigating the direct correlations between risk occurrences and performed risk reduction
activities, we were also interested in determining the impact on these direct correlations of the
factors that pertain to the context of a project.
TABLE 3 TYPICAL RISK-REDUCTION ACTIVITIES IN OTS COMPONENT-BASED DEVELOPMENT
Stage Risk management activity Description
Client attend decision Client was actively involved in the “acquire” vs. “build” decision of OTS components [8] [14].
Client attend selection Client was actively involved in the selection of OTS components [2] [3] [8].
Architecture based selection OTS components were selected mainly on the basis of architecture and compliance with standards,
instead of expected functionality [13].
Good quality evaluation The characteristics of OTS components with respect to quality (reliability, security etc.) were
considered seriously in the selection process [2] [3] [14].
Add learning effort Effort required to learn OTS components was considered seriously in effort estimation [3].
Add testing effort Effort expended in black-box testing of OTS components was considered seriously in effort
estimation [3] [14].
First integrate unfamiliar comp. Unfamiliar OTS components were integrated first [14].
Selection
and
integration
Incremental testing Integration testing was done incrementally (after each OTS component was integrated) [14].
Follow comp. update Local OTS experts actively followed updates to, and possible consequences of integrating, OTS
components [14].
Track substitute comp. Maintained a continual watch on the market and looked for possible substitute components [14].
Maintenance
Track provider Maintained a continual watch on the reputation of providers and their ability to provide support [2].
B. Survey design
We have used a structured questionnaire to collect data. The questionnaire had five major
parts. The first part was introductory. It defined our unit of study as a completed software
development project that uses one or more OTS components. The participants were asked to
select one such project that they were familiar with as a basis for completing the questionnaire.
12
The second part provided definitions of key concepts used in the questionnaire, such as the
definition of an OTS component. The third part was aimed at collecting background information
about the company, actual (“chosen”) project, and respondents. The fourth part contained
detailed questions, especially on risk management and process improvement. The last part was
aimed at collecting more detailed information about one particular component used in the
project. Information obtained from the last part is not reported herein. Data was collected by
asking participants to respond to the following questions that were presented, in most cases,
using a five-point Likert scale [38].
- The first question concerned the risk variables. Participants were asked “Did risk factor
x occur?” The alternatives provided to the participants were “don’t agree at all”,
“hardly agree”, “agree somewhat”, “agree mostly”, “strongly agree”, or “don’t know”,
with 1 being assigned to “don’t agree at all and 5 being assigned to “strongly agree”.
Table 2 lists the examined risk variables and defines what they measure.
- To collect data concerning the risk-reduction activity variables, we listed possible risk-
reduction activities, as shown in Table 3, and asked participants whether such activities
had been performed, providing the same alternatives as used for the risk variables.
- To measure the respondents’ views regarding the business characteristics of the
project, we asked participants about the time to market and cost/effort emphasis of the
project. The alternatives provided were “very low”, “low”, “medium”, “high”, “very
high”, or “don’t know”, with 1 being assigned to “very low” and 5 being assigned to
“very high”.
- To measure respondents’ views regarding the technology characteristics of the selected
project, we used the same alternatives as for business characteristics and asked the
13
participants to rate the reliability, security, and performance of the final
system/product. Since the number of different COTS packages used in one project may
influence the complexity of the project dramatically [39], we also asked the
respondents to state the number of different OTS components that were used.
- We asked participants to state what percentage of project members had previous
experience with OTS-based development in general.
C. Data collection
We used random sampling to select companies and convenience sampling to select projects
inside a company. The survey was performed in Norway, Italy and Germany.
- In Norway, we gathered a company list from the Norwegian Census Bureau (SSB)
[40] containing large (100 or more employees), medium (20-99 employees), and small
(5-19 employees) IT companies. Using the number of employees as the criterion of
size, we selected the 115 largest software-intensive companies (100 IT companies and
15 IT departments in the largest three companies in five other sectors), 200 medium-
sized software companies (20-99 employees), and 100 small companies (5-19
employees) as the original contact list (415 companies in all).
- In Italy, we first identified 43,580 software companies from the Yellow Pages and
compiled a numbered list. We then selected companies from this list at random by
using a random number generator. We visited the website of these randomly selected
companies to confirm that they really were software companies. We verified that 196
of the companies were software companies, and included them in the original contact
list.
- In Germany, we composed a list of companies using names from an organization
14
similar to the Norwegian Census Bureau and selected 476 of them in a manner similar
to that in which we selected companies in Norway. We then used an existing client
database to get contact information of these companies.
To avoid a bias in the process of data collection, we constructed the following guidelines for
contacting potential respondents before the survey started. We first contacted them by telephone.
If the potential respondents had undertaken suitable OTS-based projects and wished to
participate in our study, we sent them a username and password for the web-based Simula
Experiment Support Environment (SESE) [41] and an electronic version of the questionnaire in
MS Word format. The respondents could use either the SESE web tool or the electronic version
to complete the questionnaire. We also registered those potential respondents who did not want
to complete the questionnaire. We logged the main reasons for not wanting to respond, such as
“no software development”, “no OTS-based projects”, and “busy”. In total, we contacted (by
phone) 1087 companies in three countries. Four hundred and twenty-five of these 1087
companies were software companies and had experience with OTS component-based
development. Of the 425, 234 companies declared willingness to participate the study, and the
other companies claimed that they were too busy to attend the study. We sent questionnaire to
these 234 companies. However, we managed to collect data from only 127 companies. The
remaining 107 companies, which claimed willingness without answering the questionnaire,
mainly gave excuse as “no time”. This study is probably the first major software engineering
survey to use census-type data. We found that the entire sampling and contact process can be
unexpectedly expensive. Given a person-year of total effort just in Norway, the cost of a single
completed questionnaire is about one person-week. The study reveals that, at best, we can
achieve a stratified-random sample of IT companies, followed by a convenience sample of
15
relevant projects. All respondents in Norway and Italy used the SESE tool to complete the
questionnaire. A number of questionnaires were filled in by the researcher in Germany through
telephone interviews, because of the concerns of some companies regarding confidentiality.
Detailed discussions of sample selection, contact process, and response rate are reported in [42].
D. Data analysis
Although the variables in this study were measured using a five-point Likert scale, we treated
them as interval variables. Spector [43] has shown that people tend to treat categories in Likert
scales as equidistant, regardless of the specific categories employed. In addition, using
parametric tests for scales that do not contain strictly equal intervals does not lead, except in
extreme cases, to incorrect statistical conclusions [44]. Hand concluded that restrictions on
statistical operations that arise from scale type are more important in contexts pertaining to
model fitting and hypothesis testing than in contexts pertaining to model generation or
hypothesis generation. In the latter contexts, in principle, anything is legitimate in the initial
search for potentially interesting relationships [45].
For research questions RQ1 and RQ2, we analyzed the level of presence of risks and level of
adoption of risk-reduction activity using the median and mode. In addition, we have analyzed the
inter-correlations between occurrences of risk items and risk-reduction activities respectively.
For research question RQ3, we viewed the level of presence of risks as a dependent
(“success”) variable, and the various risk-reduction activities as independent variables. Hence,
for each risk item shown in Table 2, we were interested in the relative predictive importance of
the risk-reduction activities displayed in Table 3. However, the purpose of our study was to
generate hypotheses and propose possible effective risk-reduction activities for reducing the
probability that a problem corresponding to a risk will arise during the project.
16
The risk items and risk-reduction activities in Table 3 are categorized as belonging to either the
selection and integration phase, or the maintenance phase. For the risk items and risk-reduction
activities of each phase, we first used Pearson’s correlation analysis (excluding missing data
pairwise) [46, p. 242] to identify those risk-reduction activities that have significant (with p-
value <.05) negative correlations with a certain risk item. If a risk item was correlated
significantly with more than one risk-reduction activity, we used stepwise multiple regressions
[46, p. 532] to compare the effectiveness of those risk-reduction activities respectively.
With respect to research question RQ3, further analysis is needed to identify the possible
effects of contextual factors on the correlations between risk items and the most effective risk-
reduction activities. Since we were concerned that the correlation between the risk items and the
risk-reduction activities may be partially confounded by different project contexts, we asked the
question “What is the correlation between risk items and the risk reduction activities when the
project context variables are controlled?” We used hierarchical multiple regression [46, p. 523]
to examine the effects of each project context variable. For each risk item, a project context
variable was entered in the first block of the hierarchical multiple regression analysis. The
corresponding most efficient risk-reduction activity (i.e., the result of stepwise multiple
regression) was entered in the second block of the hierarchical multiple regression analysis. The
results for the second block told us how much additional variation in the risk item is accounted
for by the corresponding risk-reduction activity, once the effect of the project context has been
accounted for.
IV. COLLECTED DATA
We gathered results from 133 projects (47 from Norway, 48 from Germany, and 38 from Italy)
in 127 companies. In general, we selected one project from each company. However, we selected
17
more than one project in three Norwegian IT companies because those companies had many
OTS-based projects and wanted to contribute more to this study.
The respondents came from 29% small, 31% medium and 40% large companies. The main
business areas of the sampled companies were as follows: software house (50%), IT consulting
company (32%), IT department of traditional industry (16%), and telecommunication industry
(2%). The final systems produced by these 133 projects are deployed in various business
domains: public sector (25%), banking or finance (16%), traditional industry (31%), ICT sector
(9%), and others (19%).
In the selected 133 projects, 83 used only COTS components, 44 used only OSS components,
and six used both. The mean value of the number of different OTS components used in a project
was 3 (median value is 2). The mean value of the effort used before the first delivery of the
project was 86 person-months, and the median value was 32 person-months.
Most respondents of the 133 projects had a solid IT background. More than 90% of them were
IT managers, project managers, or software architects. Most of them had more than two years’
experience with OTS-based development. All of them held at least a Bachelor’s degree in
computer science or telecommunication.
The OTS components used in the investigated projects include components that follow the
COM, DCOM, and EJB models. There were also some components in the format of C++ or Java
libraries. Examples of the selected components are listed in Table 4.
TABLE 4 EXAMPLES OF OTS COMPONENTS
Name of OTS component OSS/
COTS Functionality Component model /
technique
Log4j OSS Logging and tracing Library
Snoopy OSS RSS parser PHP Library
Crystal Report COTS Report design and development J2EE, .NET, COM
MapObjects COTS Collection of embeddable mapping and GIS components Library
18
V. RESULTS FOR THE RESEARCH QUESTIONS
A. RQ1: Occurrences of risks in OTS component-based projects
The median and mode value of the risk occurrences (excluding missing data) are shown in
Table 5 and correlations between them are in Table 6. Data in table 5 illustrate that 11 out of 13
risks reported to occur infrequently. Among them, the least frequent risks are the possible
negative effects of OTS components on the quality of the whole system, such as reliability,
security, and performance. Surprisingly, 26% of the answers to the risks related to security are
missing. This probably indicates that few respondents really care about the security effects of the
OTS components on the whole system. Two risks, i.e., underestimation of integration effort and
inefficient defect localization, occurred more frequently than others. Data in Table 6 illustrate
correlations between occurrences of different risk and show that unsatisfied effort estimation on
selection and integration are highly correlated. In addition, occurrences of quality related risks
and maintenance related risks are highly inter-correlated respectively. Moreover, the difficulties
of following requirements changes are highly correlated with the occurrence of unsatisfied
selection effort estimation and the bad quality system. Inefficient debugging is strong correlated
with unsatisfied integration effort estimation and inefficient system deployments.
TABLE. 5. RISK OCCURRENCES
Risk item Number of answers (valid/missing) Median Mode
Selection effort 128/5 2 2
Integration effort 130/3 3 3
Negative reliability 117/16 1 1
Negative security 98/35 1 1
Negative perform. 121/12 1 1
Follow req. changes 131/2 2 2
Negotiate req. 123/10 2 1
Locate defect 129/4 3 3
Incompatible deploy 123/10 2 2
Plan maintenance 123/10 2 1
Update comp. 129/4 2 1
Lack provider info. 119/14 2 1
Lack support 112/21 2 1 and 2
19
TABLE. 6. CORRELATIONS BETWEEN RISK OCCURRENCES
Risk Items
Integration
effort Negative
security Negative
perform. Follow
req.
changes
Negotiate
req. Locate
defect Incompatible
deploy Update
comp. Lack
provider
info.
Lack
support
Selection effort
.614
(.000)
[128]
.370
(.000)
[127]
.196
(.033)
[119]
Integration effort
.286
(.001)
[129]
.336
(.000)
[126]
Negative
reliability
.581
(.000)
[97]
.559
(.000)
[114]
.430
(.000)
[115]
.297
(.002)
[107]
.295
(.002)
[108]
Negative security .424
(.000)
[96]
.342
(.001)
[97]
.226
(.033)
[89]
Negative perform. .239
(.009)
[119]
Follow req.
changes .209
(.021)
[122]
.201
(.023)
[128]
.292
(.001)
[122]
Locate defect .446
(.000)
[120]
Plan maintenance .312
(.000)
120
.227
(.010)
[112]
.227
(.020)
[105]
Update comp. .371
(.000)
[116]
.180
(.061)
[109]
Lack provider
info. .306
(.002)
[105]
Numbers in () are p-value
Numbers in [] are numbers of cases
B. RQ2: Performed risk-reduction activities
The median and mode of the performed risk-reduction activities (excluding missing data) are
shown in Table 7. The correlations between occurrences of risk-reduction activities are shown in
Table 8. Data in Table 7 illustrate that 7 out of 11 risk-reduction activities were infrequently
performed. Activities relevant to the clients, such as involving the client in the “acquire vs.
build” decision, or in the selection of OTS components, were rarely performed. Some risk-
reduction activities were performed more frequently, for example, developers usually evaluated
the quality of the OTS components seriously during the selection phase; some developers tried to
performed integration testing as early as possible, and integrated the unfamiliar components first.
To maintain the system successfully, some developers also consulted internal experts to follow
20
the updates of an OTS component. Data in Table 8 illustrate that clients will be involved in
selecting OTS components if they attend the decision of using OTS components. In addition, the
learning and testing effort is granted if the quality of components will be evaluated carefully.
Furthermore, developers usually catch the information of the component itself and its provider
meanwhile.
TABLE. 7. OCCURRENCES OF RISK-REDUCTION ACTIVITIES
Risk management activity Number of answers (valid/missing) Median Mode
Client attend decision 131/2 1 1
Client attend selection 129/4 1 1
Architecture based selection 131/2 2 2
Good quality evaluation 130/3 3 5
Add learning effort 129/4 3 2
Add testing effort 124/9 2 2
First integrate unfamiliar comp. 115/18 3 3
Incremental testing 127/6 3 3
Follow comp. update 131/2 3 3
Track substitute comp. 130/3 2 1 and 2
Track provider 125/8 2 1
TABLE. 8. OCCURRENCES OF RISK-REDUCTION ACTIVITIES
Client attend
selection Good quality
evaluation Add learning
effort Add testing
effort Incremental
testing Follow
comp. update Track substitute
comp Track
provider
Client attend
decision .799
(.000)
[127]
.179
(.043)
[128]
.225
(.011)
[127]
.219
(.015)
[122]
Client attend
selection .221
(.013)
[126]
.182
(.042)
[125]
Good quality
evaluation .428
(.000)
[128]
.259
(.004)
[122]
.180
(.045)
[125]
Add learning
effort .545
.000
122
.180
(.045)
[124]
Add testing
effort .212
(.020)
[119]
Follow
comp. update .224
(.011)
[129]
.368
(.000)
[124]
Track
provider .545
(.000)
[124]
Numbers in () are p-value
Numbers in [] are numbers of cases
C. RQ3: Risks and risk-reduction activities
The significant negative correlations between risk items and the risk-reduction activities by
Pearson’s correlation analysis are summarized in Table 9. The effectiveness of risk-reduction
21
activities was compared with stepwise multiple regression analysis (significant at .05 level,
including constant in equation, and excluding missing data listwise). All the regression models
that we built satisfy the basic assumptions [46, p. 533] of the multiple regressions. The results of
comparison are in Table 10 and show that:
- The occurrence of good quality evaluation of a component in the selection phase is
negatively correlated with occurrences of most development related risks.
- Devoting a significant portion of time to learning the OTS component is negatively
correlated with the occurrences of several risk items, such as unsatisfied estimation of
selection and later integration effort, inefficient to follow requirements changes, and
inefficient to locate defects.
- The occurrence of performing integration tests incrementally, instead of doing a
complete system test after all the components have been integrated, is negatively
correlated with the occurrence of inefficient requirements negotiation. However, it is
positively correlated with occurrence of inefficient following up with requirement
changes.
- The occurrence of monitoring support reputations of a provider is negatively correlated
with the risk of lacking support from the provider.
- However, certain risks, such as negative performance effect, negative security effect,
and hardness to plan maintenance of the system, have no negative correlation with
occurrences of any risk-reduction activities.
The effect of the project context variable was tested using hierarchical multiple regression. The
project context variables with a significant R2 change are in Table 11, which illustrates that:
22
TABLE. 9. CORRELATIONS BETWEEN THE RISK ITEMS AND RISK-REDUCTION ACTIVITIES
Risk-reduction activities in the selection and integration phases Risk-reduction activities in the
maintenance phase
Risk items
Client
attend
decision
Client
attend
select.
Architect
ure based
selection
Good
quality
evaluati
on
Add
learning
effort
Add
testing
effort
First
integrate
unfamiliar
comp.
Increm
ental
testing
Follow
comp.
update
Track
substitut
e comp.
Track
provider
Selection
effort -.177*
0.49
124
-.203*
.023
126
-.195*
.029
126
Integration
effort -.231*
.009
128
-.211*
.017
127
Negative
reliability -.273**
.003
114
-.224*
.018
111
Negative
security
Negative
perform.
Follow
req.
changes
-.252**
.004
129
-.198*
.025
128
.198*
.034
115
Negotiate
req. -.249**
.009
109
Locate
defect -.189*
.033
127
-.211*
.018
126
Incompatib
le deploy -.283**
.002
120
Plan
maintenan
ce
Update
comp.
Lack
provider
info.
Lack
support -.232*
.016
107
** Correlation is significant at the 0.01 level (2-tailed)
*Correlation is significant at the 0.05 level (2-tailed)
TABLE 10 THE RISKS AND CORRESPONDING MOST EFFECTIVE RISK-REDUCTION ACTIVITIES
Risk-reduction activities
Risk items Most effective risk-reduction activity Adjusted R2 (df1/df2) Standardized Beta
Selection effort Good quality evaluation .039* (1/119) -.217
Integration effort Good quality evaluation .047* (1/124) -.234
Negative reliability Good quality evaluation .068** (1/107) -.276
Negative security
Negative perform.
Follow req. changes Good quality evaluation .056** (1/127) -.252
Follow req. changes First integrate unfamiliar comp. .050* (1/112) .241
Negotiate req. First integrate unfamiliar comp. .053** (1/107) -.249
Locate defect Add learning effort .040* (1/123) -.218
Incompatible deploy Good quality evaluation .087** (1/118) -.308
Plan maintenance
Update comp.
Lack provider info.
Lack support Track provider .045* (1/105) -.232
** Significance of F change is less than 0.01
* Significance of F change is less than 0.05
23
- The correlations between risk items and the risk-reduction activities in Table 10 are
still valid when the project context variables are controlled
- The general experience of OTS component-based development of the project members
is negatively correlated with unsatisfied effort estimation, and inefficient debugging,
and costly system deployment. However, the number of different components used in
the project is positively correlated with costly system deployment, maintenance, and
debugging.
- It is not surprising that strictness of the reliability requirements of a project is
positively correlated with reliability of the system. One possible explanation is that
project members may put more effort into quality control when the project is
reliability-critical.
- Surprisingly, the experience the people is negatively correlated with their satisfactions
with the technical support from the provider. One possible explanation is that they may
have higher expectations of the provider support than less experienced people.
- The R2 of each stepwise regression was, in total, less than .015. This shows that our
investigated risk-reduction activities explain less than 15% of the variance of each
corresponding risk. This probably means that more efficient risk-reduction activities
had not been noted in the literature, and hence were not included in our study.
VI. DISCUSSION
A. Comparison with related studies
Both the effort expended on selecting OTS components and on integrating them are difficult to
estimate [3] [47]. Basili and Boehm [48] hypothesized that COTS-based development is
currently a high-risk activity, with effort and schedule overruns exceeding non-COTS-based
24
software overruns. The results of RQ1 show that inaccurate estimation of integration effort
occurs more frequently than other problems. Kotonya and Rashid [7] point out that OTS
components that offer similar functionality may have very different system resource
requirements. When a problem is identified, it may not be obvious where its root cause lies. It
may lie in one of the components, or in the integration code, or it could be due to a
misinterpretation of the semantics behind a component interface [2]. The results of RQ1 show
that another significant problem that occurs when using OTS components is the high cost of
locating defects.
TABLE 11 THE EFFECT OF THE PROJECT CONTEXT VARIABLES
Project context variable Risk-reduction activities
Risk items Name Standa
rd Beta Adjusted
R2 change Name Standa
rd
Beta
Added R2
change
Total R2
change
(df1/df2)
Selection effort Experience -.294 .080** Good quality evaluation -.197 .032* .112 (1/122)
Integration effort Experience -.328 .103** Good quality evaluation -.224 .044* .147 (1/124)
Negative reliability Reliability -.162 .046* Good quality evaluation -.217 .034* .080 (1/110)
Follow req. changes Reliability -.120 .036* Good quality evaluation -.209 .029* .065 (1/124)
Follow req. change Reliability -2.36 .032* First integrate unfamiliar
comp. .229 .044* .076 (1/111)
Negotiate req. First integrate unfamiliar
comp. -.249 .053** .053 (1/107)
Locate defect Experience -.258 .039* Add learning effort -.262 .060* .099 (1/122)
Number .164 .024* Add learning effort -.186 .027* .051 (1/119)
Incompatible deploy Experience -.182 .033* Good quality evaluation -.272 .066* .099 (1/116)
Number .192 .034* Good quality evaluation -.276 .069* .103 (1/114)
Lack support Experience .226 .067* Track provider -.164 .016* .083 (1/103)
Number .242 .056* Track provider -.197 .030* .086 (1/101)
** Significance of F change is less than 0.01
* Significance of F change is less than 0.05
One proposed risk-reduction strategy with respect to selecting proper OTS components is to
select components based on requirements and negotiation with clients [2] [3]. However, the
results for RQ2 show that very few projects involved their clients in the selection of OTS
components. Another risk-reduction strategy that has been proposed is to focus more on
architecture matches than requirements [13]. However, the results for RQ3 do not show that this
strategy has no negative correlation with any of the risk items investigated in our study.
25
B. Hypotheses for effectiveness of risk reduction activities
1) The possible effectiveness of adding possible efforts on learning OTS components
Boehm et al. [3] found that one common problem in OTS-based development is the overly
optimistic OTS learning curve, and propose that a most likely OTS learning curve must be
determined and taken into account during planning and scheduling. However, the mode value of
the variable “add learning effort”in Table 7 is only 2, which shows that most respondents did not
consider the possible learning curve seriously. As found by Rose [2], developers usually work
with several OTS components, of which they often have only a partial understanding.
The results for RQ3 illustrate that devoting a sufficient amount of time to learning about OTS
component that are candidates for inclusion has negative correlation with occurrence of
unsatisfied estimation of project effort. Again, allocating more time for developers to learn and
understand OTS components has negative correlation with occurrence of inefficient debugging at
a later stage. Thus, the first hypothesis is:
Hypothesis 1: Adding sufficient learing effort during the planning phase may reduce the
occurrences of unsatisified effort estimation and inefficient debugging.
2) The possible effectiveness of evaluating the quality of OTS components carefully
To develop a high-quality system, it is important to ensure, for every component in the system,
that it does not have any negative effects on the system as a whole. In the COTS component
market, the salesman may make false, inaccurate or exaggerated claims about the functionality
and other aspects of their products [3] [8] [47]. For OSS components, there is never enough
information provided for the developers to gain a full picture of the functions and the quality of
the components. Thus, the developers themselves need to test and evaluate the quality of possible
OTS components in the selection phase, by either reading the source code or doing black-box
26
testing. The results for RQ3 show that a thorough evaluation of the quality of OTS components
in the selection phase has negative correlation with occurrences of several risks, such as negative
effect of the component on the reliability of the system, unsatisfied estimation, inefficient
deployment, and inefficient of following requirements changes. Thus, the second hypothesis is:
Hypothesis 2: A thorough evaluation of the quality of OTS components may reduce the
occurrences of bad quality and inflexible OTS-based system.
3) The possible effectiveness of integrating critical and high-risk components first
An important issue regarding the integration of OTS components concerns changes in
requirements and mismatches with the functionality of OTS components [2] [3] [8] [47]. It is
difficult to change an OTS component to accord with the clients’ changes in requirements;
hence, it is important for the OTS component integrator to be able to (re)negotiate requirements
with the client [2] [3], and probably involve clients into the “acquire vs. build” decision and the
selection of OTS components [8]. However, the results for RQ2 show that very few integrators
have actually involved clients in these two processes. It has been found in [14] that it is not easy
to negotiate requirements with the client in OTS component-based development. One reason is
that the client typically cares only about the final product and lacks the willingness or capability
to assimilate and assess the technical details. The results for RQ3 show the occurrence of first
integrating the unfamiliar, high-risk, or critical OTS components has a negagtive correlation with
the occurrence of inefficient requirment negotiations. However, it has a positive correlation with
occurrence of inflexible system to follow the change requirements. The possible explaination is
that integrating such components first can help in the identificaton of problems in the early phase
of the project, which may give the integrator leeway to negotiate with the clients to redefine the
requirements [49]. However, developers may not feel familiar with the system if it involves
27
unfamiliar OTS components. The unconfidency may hider developers to make dramatic changes
of the system to follow changed customer requirements. Thus, the third hypothsis is:
Hypothesis 3: Integrating unfamiliar OTS components first may have two-fold effects on
requirement related risks. It may facilitate the requirement negotiation and hinder changes to
follow requirments changes.
4) The possible effectiveness of monitor OTS providers
Maintaining an OTS component-based system is difficult. The post-deployment costs may
exceed the development costs [48]. Different (non-overlapping) client-vendor evolution cycles
may result in uncertainty about how often the OTS components in a system may have to be
replaced and about the impact of such updates on the rest of the system [2] [7] [8] [47]. Hence, it
is important to receive sufficient technical support from the provider. Although the developers
have access to the source code for all OSS components (and for 1/3 of the COTS ones in our
investigated projects), few of them have either read or modified the code to meet their
requirements [50]. It is also advisable to avoid modifying OTS components, even when it is
possible [8]. COTS component users (here developers) can get support from the provider by
signing a support contract. However, COTS providers may discontinue support for their products
for different reasons (for example, the deployed version of a COTS component may be too old to
be supported), or may even go out of business [2] [48]. With respect to OSS components, some
of them are currently well-supported by volunteers in OSS projects. However, current support
does not ensure that the developers will receive the same level of support in the future. In
contrast to the situation with COTS components, when the developers can sign a support
contract, the developers have no control over the technical support that they would like from the
OSS community. Our study tried to identify common risk-reduction activities for both COTS and
28
OSS components; hence we did not investigate contract techniques, which are less applicable for
OSS-based developers. We therefore devoted our efforts to investigating those risk-reducing
activities that can be controlled by all OTS-based developers. Regarding risks related to provider
support, the results for RQ3 show that maintaining a continuous watch on the support reputation
of the OTS component providers, as proposed in [8] [47], has negative correlations with the
occurrence of insufficient support from providers. Unfortunately, the results for RQ2 show that
few projects actually do this. The hypothesis four is:
Hypothesis 4: Monitoring the support reputation of an OTS provider may help to select the
right provider, and therefore reduce the occurrence of insufficient support.
C. Hypotheses for possible effects of contextual factors
Due to the complexities of development with OTS component, not all issues can be
documented clearly. Personal capabilities and experience are probably important factors
influencing OTS-based development [48]. Donald et al. [39] conclude that the most significant
factor that influences the lifecycle cost of a COTS-based system is the number of COTS
packages that must be synchronized within a release. The results for RQ3 illustrate that several
contextual factors, such as experience with OTS-based development, the reliability requirements
of the system, and the number of different components used, have confounded effect on the
effectiveness of risk reduction activities mentioned above. Effect of these context variables need
to be adjusted before testing the hypotheses H1 to H4. Thus, the fifthe hypothsis is:
Hypothesis 5: The effectiveness of risk reduction activities may be confounded by factors, e.g.
developers’ experience, number of different components, and the system quality requirements.
D. Remaining issues of managing risks in OTS component-based development
The studied risk-reduction (independent) variables in the study explain only limited variations
29
of the actual risk (dependent) variable. That being so, we may have to look for “non-OTS-
specific” reduction activities, such as code reviews or general process improvement, to avoid
some risks more effectively. In addition, some advanced technologies that help us to manage the
assembly of components, for example, that allow us to make statements about components if
they are merged into one system, may also help to ease the integration, debugging, and
deployment of OTS components.
E. Possible threats to validity
1) Internal validity
We promised to send the respondents a final report and to hold a seminar (in Norway) to share
experiences. Our reasons for doing so were to get better feedback, honest answers, and to offer a
kind of payment. One positive effect of our strategy is that participants may have answered more
carefully because they knew that they would get feedback. One possible negative effect is that
since the participants knew that they were being observed, they may have altered their behaviour.
In general, we believe the participants wanted to share their experience and to learn from others.
Thus, we think that the participants answered the questionnaire truthfully. However, the projects
were selected by the respondents by convenience. The respondents may have selected the most
successful project to answer the questionnaire, although we asked for the most familiar one. We
have controlled this possible bias by asking respondents to select a project and answer questions
about the background information of a project in the early sections of the questionnaire. The
questions of this paper, which may involve sensitive information, are in later sections of the
questionnaire. Thus, possible side-effects of sensitive questions on the selection of projects have
been minimized.
Different persons in the same project might have had different opinions about the same project,
30
especially if it had been some time since the project had been completed. Hence, asking only one
person in each project might not reveal the whole picture. However, our samples were selected
randomly. In many cases, we had had no previous contact with the participants. Hence, it would
have been almost impossible to get two independent persons to answer questions on the same
project.
Although all questionnaires were completed by using the web-based tool in Norway and Italy,
for Germany, most of the questionnaires were completed by the researcher during telephone
interviews. Such different methods of completing the questionnaire may have biased the results
of the study.
2) External validity
Although we used different techniques to select samples in different countries, our study was
the first survey on component-based software engineering (and, indeed, software engineering in
general), to use stratified random sampling of IT companies in several countries. However, our
study focused on OTS components that satisfy our definition of a component that we presented
in Section II. Conclusions may be different for projects that use complex and large OTS
packages, such as ERP, CRM, or content management system solutions.
We primarily present overall results from the aggregated data set over three countries. In
addition, we analyzed possible diverging results using nationality as a grouping criterion.
Through dummy-variable coding [51, p.303], we have transferred the categorical variable
“country” into two binary variables v1 and v2 (v1=1 and v2=1 for Norway, v1=0 and v2=1 for
Italy, and v1=0 and v2=0 for Germany). We have used the hierarchical multiple regression as
shown in Section III to verify nationality effect on the risk and risk management correlations.
The country variables v1 and v2 are entered into the first block of the hierarchical multiple
31
regression analysis and the most effective risk-reduction activity is entered in the second block.
The results are summarized in Table 12 and show that most of our findings (shown in Table 10),
except the risk-reduction activity related to inefficient defect locating, are still valid when the
country variable is controlled. A further ANOVA analysis [46, p. 324] on the variables
“inefficient defect locating” and “add learning effort” illustrates that German respondents have
significantly devoted more learning effort and have met significantly fewer occurrences of the
costly debugging problem than what is the case for Italian and Norwegian respondents. Results
in Table 12 also illustrate that the country variables v1 and v2 have covariance with several risk
items. It reveals that some “cultural” differences between countries need to be considered
regarding risk management. Therefore, the generalization of our conclusions may need to be
verified country by country.
TABLE 12 THE EFFECT OF COUNTRY DIFFERENCES
Risk items Country code variable Risk-reduction activities
Adjusted R2 change Name Added adjusted R2 change (df1/df2)
Selection effort Good quality evaluation .034* (1/124)
Integration effort Good quality evaluation .100** (1/126)
Negative reliability .080** Good quality evaluation .059** (1/111)
Follow req. changes Good quality evaluation .056** (1/127)
Follow req. changes First integrate unfamiliar comp. .031**(1/113)
Negotiate req. First integrate unfamiliar comp. .053** (1/107)
Locate defect .454** Add learning effort .020* (1/123)
Incompatible deploy .051** Good quality evaluation .043** (1/117)
Lack support Track provider .036* (1/105)
** Significance of F change is less than 0.01
*Significance of F change is less than 0.05
3) Construct validity
In our study, most variables and alternatives were taken directly, or with little modification,
from the existing literature. However, we may have failed to consider some risks and risk-
reduction activities, because they were not mentioned in the literature. Due to the exploratory
nature of this study, we did not measure the risk item and risk-reduction activities with subitems.
Hence, a single-item bias may bring treats to construct validity of our results. However, the
questionnaire was pre-tested using a paper version by 10 internal experts and eight industrial
32
respondents before being published on the SESE tool [41]. About 15% of the questions were
revised on the basis of the pretest results. Another possible threat is that only self-reported
questionnaire was used to collect data in our study. That may bring mono-method bias [52].
4) Conclusion validity
We observed what had happened without being able to control any variables. We assumed that
the a priori probabilities of typical risks are similar in most OTS component-based projects and
examined only the relations between the performed risk-reduction activities and the actual
incidences of problems corresponding to the risks that arise during the projects. Therefore, we
cannot exclude the possibilities that:
- Projects that were less likely to realize a particular risk did not take any preventive
action, yet the risk did not materialize because it was unlikely.
- Projects that were more likely to realize a particular risk recognized that and employed
relevant activities, yet the risk materialized anyway.
Given that different projects might have slightly different a priori probabilities of typical risks,
our assumption might have biased our conclusions. To answer RQ3, we have analyzed
correlations between 11 risk reduction activities and 13 risk items, which include 143
comparisons. A possible threat to conclusion validity of our study is the issues of multiple
comparisons [53]. However, this study is designed as an exploratory study. Having significant
correlations is not essential and smaller p-values were used to formulate the hypotheses.
VII. CONCLUSION AND FUTURE WORK
OTS component-based development brings both benefits and risks. Although several studies
have investigated and proposed risk-reduction activities in OTS component-based development,
few studies have validated and compared the effects of the risk-reduction activities on the
33
corresponding risks. Our study explored the occurrences of typical risks in OTS-based projects
and compared the effectiveness of performed risk-reduction activities. The data was collected
from 133 OTS component-based projects in Norway, Italy and Germany.
The results show that two of the most frequent problems in OTS-based projects are the
incorrect estimation of the integration effort and costly debugging. The least frequent problems
are the possible negative effects of OTS components on the quality of the system as a whole. We
also illustrate several promising risk reduction activities, such as adding sufficient learning effort
in the plan phase, evaluating the quality of OTS component carefully in selection phase,
integrating unfamiliar components first, and monitoring the support reputation of component
provider, and formulate hypotheses based on the effectiveness these activities on certain risk
items. In addition, several context variables, such as experience of the developer, number of
components, and quality requirements of the system, have been discovered as confound factors
on the relationships between risk reduction activities and the occurrence of certain risk items.
This study was an exploratory one to identify valid (or significant) patterns in the collected
data material. Statistical correlation analysis can only reveal similar data patterns based on co-
variations in the given variables, in spite of all the world's "significant" p-values. That is, no
causal effects can be discovered, or hardly validated, based on statistics alone. Later causality
tests will require theory building, hypothesis formulation, design of further studies, and further
analysis of new data set.
We have assumed that the a priori probabilities of typical risks in the investigated projects are
similar. Hence, it is necessary to follow several OTS component-based projects from start to
finish by realistic case studies. We intend to examine several projects by estimating the risk
probabilities before the project starts, follow the execution of project, and measure the
34
occurrence of problems corresponding to the risks after the project has been completed. The
purpose is to investigate the causal efficacy of the risk-reduction activities on reducing the
occurrence of problems that correspond to the risks that are addressed by the risk-reduction
activities. Due to the possible single-item problem of this study, both the risk items and risk-
reduction activities will be measured with subitems in future studies. The reliability of the
measurements will also be tested.
Results of this study reveal that the country culture may require investigation when talking
about risk management. We are in the process of repeating the same study in China, which
probably has large cultural differences with “western” countries, to further investigate and verify
our findings.
The small variations of risk items explained by our investigated risk-reduction activities
illustrate that there are several other risk-reduction activities and general context variables (e.g.,
application domain, development processes, and integration technology) that need to be
investigated by future qualitative and quantitative studies.
REFERENCES
[1] C. Szyperski, D. Gruntz, and S. Murer, Component Software – Beyond Object-Oriented Programming. Addison-Wesley, 2002.
[2] L. C. Rose, “Risk Management of COTS Based System Development,” Component-Based Software Quality - Methods and Techniques,
Springer – Verlag LNCS vol. 2693, pp. 352-373, 2003.
[3] B. W. Boehm, D. Port, Y. Yang, and J. Bhuta, “Not All CBS Are Created Equally COTS-intensive Project Types,” Proc. Second Intl.
Conf. on COTS-Based Software Systems, pp. 36-50, 2003.
[4] J. Voas, “COTS Software – the Economical Choice?” IEEE Software, vol. 15, no. 2, pp. 16-19, March/April 1998.
[5] J. Voas, “The challenges of Using COTS Software in Component-Based Development,” IEEE Computer, vol. 31, no. 6, pp. 44-45, June
1998.
[6] C. Abts, B. W. Boehm, and E. B. Clark, “COCOTS: A COTS Software Integration Lifecycle Cost Model - Model Overview and
Preliminary Data Collection Findings,” Technical report USC-CSE-2000-501, USC Center for Software Engineering,
http://sunset.usc.edu/publications/TECHRPTS/2000/usccse2000-501/usccse2000-501.pdf, 2000.
[7] G. Kotonya and A. Rashid, “A Strategy for Managing Risk in Component-based Software Development,” Proc. 27th EUROMICRO Conf,
pp. 12-21, 2001.
[8] COTS risk factor, available at http://www.faa.gov/aua/resources/cots/Guide/CRMG.htm, 2003.
[9] B. Fitzgerald, “A Critical Look at Open Source,” IEEE Computer, vol. 37, no. 7. pp. 92-94, July 2004.
[10] G. Lawton, “Open Source Security: Opportunity or Oxymoron?” IEEE Computer, vol. 35, no. 3, pp. 18-21, March 2002.
[11] P. Vitharana, “Risks and Challenges of Component-Based Software Development,” Communications of the ACM, vol. 46, no. 8, pp. 67-72,
August 2003.
[12] M. Ruffin and C. Ebert, “Using Open Source Software in Product Development: A Primer,” IEEE Software, vol. 21, no. 1, pp. 82-86.
January/February 2004.
[13] M. Torchiano and M. Morisio, “Overlooked Facts on COTS-based Development,” IEEE Software, vol. 21, no. 2, pp. 88-93, March/April
2004.
[14] J. Li, F. O. Bjørnson, R. Conradi, and V. B. Kampenes, “An Empirical Study of Variations in COTS-based Software Development
Processes in Norwegian IT Industry,” Journal of Empirical Software Engineering, vol. 11, no. 3, Sept. 2006. pp. 433-461
[15] B. W. Boehm, “Software Risk management: Principles and Practices,” IEEE Software, vol. 8, no. 1, pp. 32-41, Jan.1991.
35
[16] B. W. Boehm, Software Risk Management, Tutorial, IEEE CS Press, 1989.
[17] H. Barki, S.Rivard, and J. Talbot, “Toward an Assessment of Software Development Risk,” J. Management Information Technology, vol.
22, no. 2, pp. 359-371, Dec. 1993.
[18] M. Carr, S. Kondra, I. Monarch, F. Ulrich, and C. Walker, “Taxonomy-Based Risk Identification,” Technical Report SEI-93-TR-006, SEI,
Pittsburgh, USA, 1993.
[19] S. A. Sherer, “The Three dimensions of Software Risk: Technical, Organizational, and Environmental,” Proc. 28th Hawaii International
Conference on System Sciences, pp. 369-378, 1995.
[20] C. G. Chittister and Y. Y. Haimes, “System Integration via Software Risk Management,” IEEE Trans Systems, Man, and Cybernetics, vol.
26, no. 5, pp. 521-532, Sep. 1996.
[21] J. Ropponen and K. Lyytinen, “Components of Software Development Risk: How to Address Them? A Project Manager Survey,” IEEE
Trans. Software Engineering, vol. 26, no. 2, pp. 98-112, February 2000.
[22] M. Keil, P.E. Cule, K. Lyytinen, and R.C. Schmidt, “A Framework for Identifying Software Project Risks,” Communications of the ACM,
vol. 4, no. 11, pp. 76-83, Nov. 1998.
[23] L. Wallace and M. Keil, “Software Project Risks and Their Effect on Outcomes,” Communications of the ACM, vol. 47, no. 4, pp. 68-73,
April 2004.
[24] B. W. Boehm, “A Spiral Model of Software Development and Enhancement,” IEEE Computer, vol. 21, no. 5, pp. 61-72, May 1988.
[25] A. Gemmer, “Risk Management: Moving Beyond Process,” IEEE Computer, vol. 30, no. 5, pp. 33-41, May, 1997.
[26] H. Hecht, Systems Reliability and Failure Prevention. Artech House Publishers, 2003.
[27] I. Sommerville, “Software Engineering”, 7th edition, Addison Wesley, 2004.
[28] T. Moynihan, “How Experienced Project Managers Assess Risk,” IEEE Software, vol. 14, no. 3, May/June 1997.
[29] R. L. Glass, “Frequently Forgotten Fundamental Facts about Software Engineering”, IEEE Software, vol. 18, no. 3, pp. 110-112, May/June,
2001.
[30] I. Crnkovic and M. Larsson, “Building Reliable Component-Based System,” Artech House, 2002.
[31] C. Szyperski, “Component Software: Beyond Object-Oriented Programming”, 2nd edition, Addison Wesley, 2002.
[32] M. Vigder, M. Gentleman, and J. Dean, “COTS Software Integration: State of the Art”, Technical Report NRC No. 39190, 1996.
[33] V. R. Basili, M. Lindvall, I. Rus, C. Seaman, and B. W. Boehm, “Lessons-Learned Repository for COTS-Based SW Development,”
Software Technology Newsletter, vol. 5, no. 3, pp. 4-7, available at: http://fc-md.umd.edu/ll/index.asp, 2002.
[34] T.R. Madanmohan and R. De’, “Open Source Reuse in Commercial Firms,” IEEE Software, vol. 21, no. 1, pp. 62-69, January/February,
2004.
[35] L. Bass, C. Buhman, S. Comella-Dorda, F. Long, J. Robert, R. Seacord, and K. Wallnau, “Volume I: Market Assessment of Component-
based Software Engineering,” SEI Technical Report number CMU/SEI-2001-TN-007, available at: http://www.sei.cmu.edu/, 2001.
[36] Component-based Software Engineering Network. CBSEnet, available at http://www.cbsenet.org, 2004.
[37] C. Abts, B. W. Boehm, and E. B. Clark, “COCOTS: A COTS Software Integration Cost Model - Model Overview and Preliminary Data
Findings”, Proc. of the 11th ESCOM Conf, Munich, Germany, pp. 325-333, April 2000.
[38] R. Likert: “A Technique for the Measurement of Attitudes”, Archives of Psychology, no. 140, pp. 5-55. 1932.
[39] J.R. Donald, V. Basili, B. Boehm, and B. Clark, “Eight Lessons Learned during COTS-Based Systems Maintenance”, IEEE Software, vol.
20, no., 5, pp.94-96, Sep. /Oct. 2003.
[40] Norwegian Census Bureau (SSB), Oslo, ICT company data, available at http://www.ssb.no/emner/10 /03/ikt/, 2002.
[41] E. Arisholm, D. I. K. Sjøberg, G. J. Carelius, and Y. Lindsjørn: “SESE – an Experiment Support Environment for Evaluating Software
Engineering Technologies”, Proc. of the 10th Nordic Workshop on Programming and Software Development Tools and Techniques,
Copenhagen, Denmark, pp. 81-98, Aug. 2002.
[42] R. Conradi, J. Li, O. P. N. Slyngstad, C. Bunse, M. Torchiano, and M. Morisio, “Reflections on Conducting an International CBSE Survey
in ICT Industry,” Proc. Forth IEEE Intl. Symposium on Empirical Software Engineering , pp. 214-223, 2005.
[43] P. Spector: “Ratings of Equal and Unequal Response Choice Intervals”, Journal of Social Psychology, vol. 112, pp. 115-119, 1980.
[44] P. F. Velleman and L. Wilkinson: “Nominal, Ordinal, Interval, and Ratio Typologies Are Misleading”, Journal of the American Statistician,
vol. 47, no. 1, pp. 65-72, February 1993.
[45] D. J. Hand: “Statistics and Theory of Measurement”, Journal of the Royal Statistical Society: Series A (Statistics in Society), vol. 159, no.
3, pp. 445-492, 1996.
[46] B. H. Cohen, “Explaining Psychological Statistics”, 2nd edition, Wiley, 2000.
[47] Common Risks and Risk Reduction Actions for a COTS-based System,
www.mitre.org/work/sepo/toolkits/risk/taxonomies/files/CommonRisksCOTS.doc, 2005.
[48] V. R. Basili, and B. W. Boehm, “COTS-Based Systems Top 10 List,” IEEE Computer, vol. 34, no. 5, pp. 91-93, May 2001.
[49] S. Lauesen, “COTS Tenders and Integration Requirements,” J. Requirements Engineering, vol. 11, no. 2, pp. 111-122, 2006.
[50] J. Li, R. Conradi, O. P. N. Slyngstad, C. Bunse, U. Khan, M. Torchiano, and M. Morisio, “Validation of New Theses on Off-The-Shelf
Component Based Development,” Proc. 11th IEEE Intl. Metrics Symp., pp. 26 (abstract), Sept. 2005.
[51] J. Cohen, P. Cohen, S. G. West, and L. S. Aiken, “Applied Multiple Regression/Correlation Analysis for the Behavioral Sciences”,
Lawrence Erlbaum Associates, 3rd edition, 2002.
[52] P. M. Podsakoof and D. W. Organ, “Self-Reports in Organizational Research: Problems and Prosects”, J. Management, vol. 12, no. 4, pp.
531-544, 1986.
[53] S. J. Pocock, M. D. Hughes, and R. J. Lee, “Statistical Problems in Reporting of Clinical Trials: A Survey of Three Medical Journals”, the
New England Journal of Medicine, vol. 317, no. 7, pp. 426-432, 1987.
... However, a formal direct and an indirect component coupling metrics are proposed to measure the quality of components with respect to complexity and performance [3]. The research investigates the risk-management activities and their correlations with the occurrences of typical risks in the development of COTS systems [4]. It is achieved by exploring the occurrences of typical risks in COTS systems and furtherly the effectiveness of the risk reduction activities are compared. ...
... The idea is proposed to establish to measure the effectiveness of reusable components. A State-of-the-Practice Survey of Risk Management in Development with Off-the-Shelf Software Components [4]. ...
... It is a common dilemma that increasing demand of working software and integration factors led to forget about the quality of selected components. Table 1 illustrates the limitations of related work [3][4][5][6][7][8]. ...
Article
Full-text available
An ultimate goal of software development is to build high quality products. The customers of software industry always demand for high-quality products quickly and cost effectively. The component-based development (CBD) is the most suitable methodology for the software companies to meet the demands of target market. To opt CBD, the software development teams have to customize generic components that are available in the market and it is very difficult for the development teams to choose the suitable components from the millions of third party and commercial off the shelf (COTS) components. On the other hand, the development of in-house repository is tedious and time consuming. In this paper, we propose an easy and understandable repository structure to provide helpful information about stored components like how to identify, select, retrieve and integrate components. The proposed repository will also provide previous assessments of developers and end-users about the selected component. The proposed repository will help the software companies by reducing the customization effort, improving the quality of developed software and preventing integrating unfamiliar components.
... Some of the risks we have identified apply in general to new technology adoption by companies, e.g. electronic data interchange (EDI), enterprise resource planning (ERP), and open source software platforms (Austin and Nolan 1999;Hart and Saunders 1997;Li et al. 2008;Poba-Nzaou et al. 2008;Riggins and Mukhopadhyay 1999). Specific business risks such as internal disruption, imbalances in attention, risk of missing out, and strategic and structural inflexibility are always front and center when adopting new technologies. ...
... On page 13, we now write: "Some of the risks we have identified apply in general to new technology adoption by companies, e.g. electronic data interchange (EDI), enterprise resource planning (ERP), and open source software platforms (Austin and Nolan 1999;Hart and Saunders 1997;Li et al. 2008;Poba-Nzaou et al. 2008;Riggins and Mukhopadhyay 1999). Specific business risks such as internal disruption, imbalances in attention, risk of missing out, and strategic and structural ...
Article
Blockchain technologies are quickly changing the competitive business landscape. Companies need to think strategically about how to best prepare for a future in which they might systematically enhance value and unleash new value using blockchain. In this article, we address how cooperating companies jointly create unique value with blockchain technology, the risks they face along the way, and how they can mitigate those risks. We briefly identify three different reasons a company might adopt blockchain – to enhance value creation, to strengthen existing value ecosystems, or to create new value ecosystems. Then, we identify three strategic risks of blockchain adoption as they relate to business issues, legal issues, and technological issues. Finally, we highlight four different forms of strategic maneuvers for minimizing these risks. The strategic maneuvers include the all-industry approach, the walled garden approach, the many gardens approach, and the options approach. We provide prescriptive advice to managers on how to strategically think about blockchain adoptions, how to identify the underlying risks, and how to consider strategic approaches to mitigate their adoption risk.
... For example, small and medium-sized businesses (SMEs) use preventative measures to reduce the impact of these risks and ensure that the project will be successful overall [15]. Risk management activities include [8], [9], [16]: ...
Article
Full-text available
The crafting of software is a continual procedure, and the success of each step of that process is contingent on effective management. Despite this, numerous organizations need help developing e-service systems, frequently dealing with budget constraints and tight deadlines. The lack of focus on risk management in software projects is likely to blame for these failures. Management of risks is crucial to ensuring the success and efficacy of software development projects, as it assists in identifying areas of vulnerability and provides valuable insights into the project's most important aspects. This study identifies and analyzes tools and techniques to support software development projects’ risk management activity. A systematic literature review (SLR) methodology was employed to collect and evaluate relevant research articles. The findings highlight various risk management tools and techniques, including brainstorming, root cause analysis, risk probability assessment, artificial intelligence, and risk response planning. These tools and techniques contribute to identifying, analyzing, planning, and controlling risks in software projects. The research provides insights into the state of the art in risk management. It complements previous studies by offering practical guidance on software development project risk management tools and techniques.
... To answer RQ1 and RQ2, we opted for conducting an opinion survey [Linaker et al. 2015]. Opinion surveys are largely conducted in the field to characterize the state of practice by gathering practitioners' perceptions about software engineering activities [de Mello et al. 2014b, de O. Passos et al. 2018] and the daily work [Li et al. 2008, de Souza et al. 2023). ...
Conference Paper
Unit testing is an important and largely disseminated software engineering activity, contributing to the prevention of defects in source code elements before running more comprehensive tests. However, developers typically perform unit tests ad-hoc, lacking in coverage and quality. Consequently, the unit testing practice remains informal and strongly influenced by developers’ initiative. We report in this paper an opinion survey on the developers’ perceptions of unit testing and its practice. We conducted the survey with 32 developers from two Brazilian companies. The survey findings revealed that developers from both companies tend to share positive beliefs about the relevance of unit testing. However, they also tend to share negative perceptions about its practice in their working environments. Besides, we found a positive moderate correlation between the developers’ motivation and their perceptions about the training, frequency, and time allocated for unit testing. The survey results reveal the dissonance between the developers’ beliefs about unit testing and their practice, influenced by issues in their working environments. This dissonance may lead to a lack of commitment and internal conflicts.
... Thus, a risk list was defined based on the expertise of these managers. Additionally, Li et al. (2008) surveyed RM in the development of Commercial Off-The-Shelf (COTS) components. They investigated existing RM activities and their correlations with the occurrences of typical risks in COTS development. ...
Conference Paper
Full-text available
Software Product Line (SPL) Engineering is a software development paradigm focused on systematic reuse, which provides companies with several benefits, such as improved quality of delivered products and reduced time to market. However, major investments and considerable risks are also inherent. In this context, managing the risks and providing strategies to avoid and mitigate them are mandatory tasks during software development. In this study, we present the results of an expert survey, carried out with the aim to figure out how the SPL experts have been worked with Risk Management (RM) in their projects. We observed that experts do not always address the RM activities during real world project development, what can be justified that RM is an open issue when related to SPL.
... The papers summarised under these cause-effect relationships are arranged into Table 2a, Table 2b and Table 2c respectively, where Flyvbjerg's "Challenges-Causes-Cures" framework is employed to further synthesise the literature and draw out common themes. (Antoniadis et al., 2011;Catalão et al., 2019;Geraldi et al., 2011;Grant, 2016;Hetemi et al., 2017;Jolivet and Navarre, 1996;Li et al., 2008;Montealegre and Keil, 2000;Patanakul, 2014;Patanakul et al., 2016;Pich et al., 2002;Sauser et al., 2009;Williams, 2005;Yu et al., 2015) Failure of a range of complex projects, such as IS/IT, major infrastructure, airport baggage handling systems and scientific projects such as NASA's Climate Orbiter project. ...
Article
Full-text available
Recent research on the origins of risk during the planning and delivery of major projects broadly addresses two root causes: (i) complexity at the planning phase and also during project delivery, and; (ii) ‘the inside view’ at the planning phase and the associated issues of strategic misrepresentation and cognitive biases such as optimism bias. This paper presents the results of a systematic review that finds a schism in the literature showing theoretical and empirical treatment of project delivery risk polarises into considering either the effect of complexity or the inside view; rarely are they considered jointly. This work discusses the implications for theory and practice and identifies Case Based Decision Theory and Bayesian modelling, both of which are outside view techniques, as having potential to reconcile complexity and the inside view and thus provide for their joint treatment.
Article
The trend toward global software development (GSD) has grown tremendously in recent years because of the rapid acceleration in information and communication technologies (ICTs). The reason for the changing trend toward GSD is to develop high‐quality software with minimum cost and time with round the clock. Despite the benefits gained from GSD, there are certain challenges associated with it. Literature reveals that software integration is an integral challenge in the GSD domain and vendors face numerous difficulties in integrating the software components to build the final product. The main aim of this research study is to develop a software integration model (SIM) that will assist GSD vendors to address the factors linked with various stages of software integration. This model is basically designed for GSD vendor organizations to assess and improve their software integration‐related activities. However, it is also beneficial for GSD client organizations in getting knowledge about the status of the GSD vendor organization's software integration capabilities. The research design is composed of well‐known research strategies including systematic literature review (SLR), questionnaire survey, and case study approach. This research study yielded the SIM. We identified nine critical success factors (CSFs) and 10 critical barriers (CBs) in software integration through SLR‐1 by extracting the data from a sample of 105 papers. Similarly, we also identified a total of 132 practices/solutions, for the identified CSFs and CBs in software integration, through SLR‐2 from a sample of 40 papers. These identified factors and practices were validated from 96 global software industry experts/practitioners through online survey. The identified CSFs, CBs, and their associated practices have been arranged adequately across the six software integration levels of SIM. We have adapted SIM structure from capability maturity model integration (CMMI), implementation maturity model (IMM), and software outsourcing vendors readiness model (SOVRM). We also conducted six case studies in the software industry for SIM applicability and validity. The participants' feedback from the six case studies in GSD vendor's organizations portray that the SIM is beneficial for GSD vendors to assess their software integration capability.
Thesis
Full-text available
Nos setores como a indústria de software, que utilizam o conhecimento como recurso para as suas atividades, existe uma atividade intensa de conhecimento, visto que adotam constantemente novas tecnologias e novas práticas. Outra característica desse ambiente é que são, particularmente, susceptíveis a falhas. Nesse contexto, o objetivo desta pesquisa é analisar a integração de técnicas de gestão do conhecimento à atividade de análise de riscos em projetos de desenvolvimento de software de micro e pequenas empresas de base tecnológica incubadas. A escolha de empresas de desenvolvimento de software incubadas como objeto de estudo é justificada devido a sua importância econômica, assim como por ser um ambiente rico em inovação tecnológica e se sustentar basicamente na geração do conhecimento. O método de pesquisa adotado foi o de estudos de caso múltiplos, realizados com gerentes e desenvolvedores de software de quatro empresas incubadas. O Analytic Hierarchy Process foi utilizado na escolha da abordagem de gestão do conhecimento que serviu de base para a pesquisa e na seleção da taxonomia de risco para compor o protocolo. Como resultados, destaca-se a seleção da abordagem de Nonaka e Takeuchi como a mais adequada, de acordo com os critérios estabelecidos, e escopo ou objetivos pouco claros ou mal interpretados como principal fator de risco para os gerentes e desenvolvedores. Outro resultado importante, que merece atenção por parte das empresas avaliadas, é com relação à utilização das técnicas de gestão do conhecimento para a análise dos riscos. Os respondentes consideraram que as técnicas de gestão do conhecimento referente ao modo de conversão “combinação” seriam as mais aplicáveis para uso. Entretanto, as mais utilizadas atualmente se referem ao modo de conversão de “internalização”.
Preprint
Full-text available
Empirical Standards are brief public document that communicate expectations for a specific kind of study (e.g. a questionnaire survey). The ACM SIGSOFT Paper and Peer Review Quality Initiative generated empirical standards for common research methods in software engineering. These living documents, which should be continuously revised to reflect evolving consensus around research best practices, can be used to make peer review more transparent, structured, harmonious and fair.
Article
Full-text available
Self-reports figure prominently in organizational and management research, but there are several problems associated with their use. This article identifies six categories of self-reports and discusses such problems as common method variance, the consistency motif, and social desirability. Statistical and post hoc remedies and some procedural methods for dealing with artifactual bias are presented and evaluated. Recommendations for future research are also offered.
Article
Individuals acquire knowledge while working in software development projects but too often this knowledge is not documented or captured so that it can be shared or later reused. Dissemination of experience related to new development paradigms, such as development based on commercial off-the-shelf (COTS) components, can be particularly useful. To support sharing experiences about COTS-based software (CBS) development, we have built and made available to the software engineering community a webbased repository of lessons learned. This collection of practical knowledge is currently seeded with lessons extracted from published experiences and online Workshops. The repository offers capabilities for online search and retrieval, submission of lessons and feedback, plus a visual query interface that allows for analysis of the lessons learned and their usage. The repository will grow organically in the directions indicated by usage and contributions from its users.
Article
Just as there are different interpretations of probability, leading to different kinds of inferential statements and different conclusions about statistical models and questions, so there are different theories of measurement, which in turn may lead to different kinds of statistical model and possibly different conclusions. This has led to much confusion and a long running debate about when different classes of statistical methods may legitimately be applied. This paper outlines the major theories of measurement and their relationships and describes the different kinds of models and hypotheses which may be formulated within each theory. One general conclusion is that the domains of applicability of the two major theories are typically different, and it is this which helps apparent contradictions to be avoided in most practical applications.